signify Linear ID-23 TruGroove Recessed Micro Drywall Corner Installation Guide

June 16, 2024
signify

Linear
ID-23 Drywall Corners
TruGroove Recessed Micro

System Overview

These instructions review how to install drywall versions of TruGroove recessed micro corners. Please refer to layout drawings supplied by Ledalite with these installation instructions. These instructions must be used in conjunction with TruGroove recessed micro Drywall Ceiling Standalone and Continuous Run Installation Instructions. The graphics below show the corner types available, and steps required to correctly install TruGroove recessed micro corners in drywall ceilings. These instructions apply to trim and trimless TruGroove product configurations.
IMPORTANT: Read all instructions including fixture/sensor wiring AND mechanical details before beginning installation.

Ceiling Cutout Information

IMPORTANT:
Continuous run ceiling and wall cutout dimensions shown below come from supplied layout drawings.
Layout drawings for all patterns show dimensions to corner centers. Framing, ceiling and wall preparation must be done according to provided layout drawing pattern leg dimensions and detailed instructions.

IMPORTANT INSTALLATION STEPS (TRIMLESS VERSION):

  1. Install required mounting brackets (if applicable) and power feed.
  2.  Install framing/blocking as per supplied layout drawings and instructions.
  3. Install drywall.
  4. Install all lighting fixtures.
  5. Install corner bead(s) and tape.
  6. Mud, sand and finish wall(s) and ceiling(s).

ATTENTION: Install in accordance with local and national building and electric codes.

ID-23 TruGroove Drywall Trim Installation Instructions

This equipment has been tested and found to comply with the limits for a Class A digital device, pursuant to part 15 of the FCC Rules. These limits are designed to provide reasonable protection against harmful interreference when the equipment is operated in a commercial environment. This equipment generates, uses, and can radiate radio frequency energy and, if not installed and used in accordance with the instruction manual, may cause harmful interference to radio communications. Operation of this equipment in a residential area is likely to cause harmful interference in which case the user will be required to correct the interference at his own expense.

Important Notes

Installation Notes

  • ‘C’ Channels (or equivalent) must be properly braced to ensure accuracy of cut-out in drywall.
  • Use appropriate tools to outline specified dimensions of ceiling cutout to ensure straightness of cutting.
  • Lens will not insert properly if fixture trim has mud or paint buildup.

Warning, Shock Hazard
Fixture must be connected to building ground via the provided ground wire before connecting to mains power supply.
Disconnect or turn off power before attempting any installation, service or maintenance.

Avoid

The straightness and accuracy of the cut-out in the drywall is crucial in ensuring proper fit for the fixture.

Flat Corner In-Ceiling

For continuous run fixtures, the cutout in the drywall ceiling should be measured and cut as shown on page 2 and  3. Referto Drywall Ceiling Standalone and Continuous Run Installation Instruction for fixture mounting locations details.
Determine corner location and refer to figure A for specific in-ceiling corner mounting dimensions.
NOTE: Flat corners installed in ceiling require 3 mounting locations

Ceiling Mounting Details

ATTENTION: Install in accordance with local and national building and electric codes.

  1. Install Mount and Power Cables Install mounting brackets, suspension cables and power cables at required locations. Use one bracket and one suspension cable at end condition. Use one bracket and two suspension cables at a joint condition. Mounting bracket must be centered above fixture joint. NOTE: Mounting hardware by others.

  2. Install Framing & Drywall Install ‘C’ channel along full fixture perimeter to cutout specified drywall and cut opening to dimensions shown.
    IMPORTANT: See detail on page 2 for proper fixture and corner fit.

  3. Finish Ceiling Preparation After drywall is installed, check that fixture opening is straight and that it meets required dimensions of minimum 3-7/8” to maximum 4”

  4. Prepare Fixtures/References Layout Drawings
    Arranged box fixtures on floor in specified mounting locations, based on supplied layout drawings. Match up each fixtures based on the spec. tag and ID number labeled on each box for the specified run.

  5. Install Corners and Fixtures
    Follow TruGroove drywall ceiling standalone and continuous run installation instructions.
    Installation Tip: Begin installation by suspending corners unit first and work outwards to complete a continuous run.

ATTENTION: Install in accordance with local and national building and electric codes.

© 2021 Signify Holding. All rignts reserved. The information provided herein is subject to change. without notice. Signify does not give any representation or warranty as to the accuracy or completeness of the information included herein and shall not be liable for any action in reliance thereon. The information presented in this document is not intended as any commercial offer and does not form part of any quotation or contract, unless otherwise agreed by Signify.

Signify North America Corporation
400 Crossing Blvd, Suite 600
Bridgewater, NJ 08807
Telephone: 855-486-2216
Signify Canada Ltd.
281 Hillmount Road,
Markham, ON, Canada L6C 283
Telephone: 800-668-9008
All trademarks are owned by Signify Holding or their respective owners.
www.signify.com
www.ledalite.com

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

signify User Manuals

Related Manuals