Steel-Line Series-AA Aluminium Guide Roller Door Installation Guide

June 9, 2024
Steel-Line

Series-AA Aluminum Guide Roller Door

  Series ’AA’ Roller Door Installation Guide

SERIES ‘AA’ ALUMINIUM GUIDE ROLLER DOOR

INSTALLATION GUIDE

THESE INSTRUCTIONS ARE PROVIDED FOR THE USE BY EXPERIENCED INSTALLERS OF GARAGE DOORS
BY UNDERTAKING THE INSTALLATION OF THIS DOOR, THE INSTALLER UNDERSTANDS THE DANGERS ASSOCIATED WITH THE INSTALLATION.
Steel-Line Garage Doors IS NOT RESPONSIBLE FOR ANY AND ALL LIABILITY RESULTING IN THE INJURY AND OR DEATH DERIVED FROM AN IMPROPER INSTALLATION.

 Call 1300 427 243 | steel-line.com.au

 Series ’AA’ Roller Door Installation Guide

GENERAL WARNING

SPECIAL SAFETY WARNINGS OR REMARKS IN THIS MANUAL ARE INDICATED WITH THIS SYMBOL. PLEASE READ ALL WARNINGS CAREFULLY.

To install this door safely, several precautions must be taken. For the safety of all concerned, please pay attention to all warnings and instructions given below.

  • Please read this installation manual completely prior to installation. It is very important to install this door per the manual to achieve proper and safe operation
  • The Steel-Line Series ‘AA’ roller doors are designed as light industrial chain operated doors to suit a maximum opening of 3000mm High x 5500mm Wide and depending on size can weigh as much as 165kg (364lbs). The forces generated in the springs are generally equal to the door weight. Proper care must be taken not to release those forces violently as it could result in serious physical injury.
  • All the components which have been supplied are designed for this specific roller door. Replacement or additional components may have an adverse effect on the performance, safety and the warranty of the door.
  • Alterations to the spring tension should only take place when the door is in the open (up) position and undertaken by a trained installer.
  • All instructions are given as if viewing the door from the inside looking out.

SAFETY CHECK LIST

Care must be taken to avoid any chance of risk of accidents or injury. Please check for the following hazards before and during installation.

General Housekeeping


Checklist item

|

Yes/No

|

Correction

1

|

Is the site housekeeping safe to install a door?

|

|

2

|

Is the area around the installation site free of obstruction?

|

|

3

|

Have appropriate signage and notices around the site to  keep work area clear of people been put in place?

|

|

Manual Handling

Checklist item

|

Yes/No

|

Correction

---|---|---

1

|

Are the correct lifting techniques for different sized doors  available? i.e. doors above 2.5m wide will require a lifting  device

|

|

2

|

Are two people available for lifting operations?

|

|

3

|

Are mechanical aids available where required? i.e. lifting  stands, forklifts, scissor lifts or cranes

|

|

4

|

Are correct lifting techniques being practiced by installers? i.e. a lifting device is used for doors over 2.5m

|

|

5

|

Is the top rung being avoided during use of ladders?

|

|

6

|

Are ladders correctly placed and used during installation?

|

|

7

|

Are correct techniques used for ropes and temporary  fastening operations?

|

|

Safety Equipment

Checklist item

|

Yes/No

|

Correction

1

|

Are installers wearing the appropriate PPE?

|

|

2

|

Are the operator manuals being followed?

|

|

3

|

Are appropriate noise/hearing protection being used?

|

|

4

|

Is everyone involved supplied with appropriate fire  protection in the case that flammable liquids or materials  are removed from the work area?

|

|

Spring Tension

Checklist item

|

Yes/No

|

Correction

1

|

Is the door correctly secured and in the up and open  position?

|

|

2

|

Is the stilsons fitted correctly to the axle and locked off  against a wall?

|

|

3

|

Are the stilsons of an adequate length?

|

|

4

|

Are the correct nuts and bolts tightened and loosened to  ensure the control of the tension of the spring to avoid any  unexpected release of the spring?

|

|

5

|

Are body parts i.e. arms and head, clear of the stilsons at  all times?

|

|

Door Position

Checklist item

|

Yes/No

|

Correction

1

|

Has the door been fastened to the bracket on both ends  using appropriate fixings?

|

|

2

|

Are people safely maneuvering around the door while it is  sitting on the brackets?

|

|

Call 1300 427 243 | steel-line.com.au Page 4 of 16

 Series ’AA’ Roller Door Installation Guide

PRE-INSTALLATION CHECKS

REQUIREMENTS

A roller door is designed to be fitted behind the opening and the following dimensions and conditions need to  be checked before fully unpacking the door for installation.

OPENING WIDTH

Check that the curtain is wider than the opening by a minimum of 50mm each side – 100mm overall

SIDE CLEARANCE

Door Type

|

Minimum Non-Drive Side Dim. ‘H’

|

Minimum Operator/Gear Driven Side Dim ‘F’

---|---|---

Series ‘AA’

|

125mm

|

150mm

|

‘H’

|

‘F’

NB: If the door is to be motorised, check with the motor installation instructions for side room required for the  motor.

HEADROOM

A minimum clearance between the underside of the lintel/headroom and the ceiling. This varies with the  height of the door. See chart below.

Door Height (mm)

|

Minimum Headroom ’B’  * (mm)

---|---

2200 – 2600

|

480

2700 – 3000

|

510

*This clearance must extend for a minimum of 500mm  for ‘AA’ doors horizontally back from the opening. The  minimum headroom is required to reveal the complete  daylight opening height. Fitting a door where less than  the recommended headroom is supplied will result in  less drive-through height.

Call 1300 427 243 | steel-line.com.au Page 5 of 16

Series ’AA’ Roller Door Installation Guide

STRUCTURAL CONDITION OF OPENING

IT IS THE INSTALLER’S RESPONSIBILITY TO ENSURE THAT THE AREA AROUND THE OPENING IS STRONG ENOUGH TO SUPPORT THE DOOR.

The lintel and jamb surfaces where the door is to be fitted to must be flush and reasonably smooth  (small irregularities are acceptable).

FITTING NOTES

a) For doors over 2.5m wide, it is recommended that two people are available for fitting.

b) The door must be installed SQUARE AND LEVEL irrespective of the shape of the opening. Under  no circumstances should any compensation be made to the door to suit an irregular opening.

c) Ensure that all necessary tools are available at hand before starting.

d) Ensure the area around the opening is free of any obstructions.

e) The door package and its contents should be checked for obvious damage before removal of wrapping.

The package should contain (see Appendix A for parts list):

1. The curtain rolled up and wrapped.

2. One pair of guides – these come in standard length.

3. One pair of ‘Bk5’ brackets.

4. One yellow bag containing the hardware required to fit the door.

5. One lead-in kit box.

NB: Some of the hardware fixing supplied may not be suitable for fixing curtain brackets to opening substrate.  The installer should select suitable fixings to suit substrate and curtain size and weight.

IF THERE IS ANY OBVIOUS DAMAGE OR PARTS MISSING, CONTACT YOUR STEEL-LINE SUPPLIER.

Call 1300 427 243 | steel-line.com.au Page 6 of 16

Series ’AA’ Roller Door Installation Guide

INSTALLATION

DO NOT CUT PACKAGING AROUND ROLLED CURTAIN UNTIL INSTRUCTED TO DO SO IN  STEP 6.

1.0 MARK DOOR POSITION

1. Mark the curtain overlaps 50mm at each side of the opening.

2.0 INSTALL BRACKETS

1. Use the appropriate fixings to suit the opening substrate.

2. For motorised doors, check the motor instructions for the dimensions required from the edge of curtain  (curtain overlap) to the inside of the bracket.

3. Fit the brackets and ensure the minimum clearance for plain side and drive side.

4. Use a levelling device to ensure that the brackets are level with each other and fix to the substrate.

5. Re-check level and fix both brackets securely.

6. The minimum dimensions from the lintel to the top of the bracket is as follows:

Specified Door Height (mm)

|

Minimum Roll Clearance ‘C’ (mm)

|

Dim. ‘D’ Minimum Distance from Underneath Lintel to Top  of Bracket (mm)

---|---|---

2200 – 2600

|

260

|

220

2700 – 3000

|

275

|

235

Note: if there is a lack of headroom, refer to the minimum roll clearance for bracket positioning. If the  headroom is over the minimum, refer to Dim. ‘D’ for bracket positioning to ensure maximum daylight opening.

Call 1300 427 243 | steel-line.com.au Page 7 of 16

 Series ’AA’ Roller Door Installation Guide

3.0 FIT DRIVE UNIT

Fit the motor to the door according to the instructions provided if required.

4.0 MOUNT DOOR CURTAIN TO BRACKETS

1. Leave plastic wrap packaging in place on door.  Ensure there are no loose parts or packaging  inside the door.

2. Float the shaft by rotating in either direction  then releasing.

3. Fit anti-coning collar on the non-drive side of  the door leaving a 1mm gap between the  collar and drum wheel.

4. Check protruding shaft lengths will fit within the side clearances. Trim the shaft if necessary.

5. Position the heavy-duty cast saddle on top of and in-line with the slots on the bracket.

6. Position the door to ensure the sheet unravels adjacent to the opening and lift door onto brackets.

7. Secure the heavy-duty saddle clamps with the provided U-bolts and nuts finger tight only.

DO NOT USE BRACKET AS A LIFTING DEVICE AS IT IS NOT DESIGNED FOR LIFTING

Call 1300 427 243 | steel-line.com.au Page 8 of 16

 Series ’AA’ Roller Door Installation Guide

5.0 CUT AND POSITION GUIDES

BEFORE GUIDES ARE FITTED, BE VERY CAREFUL NOT TO ALLOW CURTAIN TO ROLL UP UNAIDED AS DAMAGE AND INJURY MAY RESULT.

1. Cut the guide to achieve dimension ‘Y’ for the applicable ‘Door Height’.

Specified Door  Height (mm)

|

Min. Dimension ‘Y’ Top of  Bracket to Top of Guide

---|---

2200 – 2600

|

195

2700 – 3000

|

210

2. Fix the nylon lead-in to the top of the guide with the provided 8G-18×1½” self-tapping  screw.

3. Use the nylon lead-in holes as a guide to drill  6.5mm sized holes for the screws.

4. Install the stop and fix the tapped plate with  the provided fixings to the inside of the guide.

5. Fix the guide to the substrate through the top and bottom slots loosely.

6. Position the guide against the jamb ensuring it is vertical.

THE EXTREME TOP EDGE OF THE GUIDE MUST NOT BE HIGHER THAN THE HORIZONTAL  LEG OF THE SUPPORT BRACKETS TO ENSURE PROPER OPERATION.

Call 1300 427 243 | steel-line.com.au Page 9 of 16

 Series ’AA’ Roller Door Installation Guide

6.0 POSITION THE DOOR

1. Ensure the curtain overlaps the opening equally on both sides. If not, centralise door by rocking back  and forth ensuring the nuts are still secured finger tight only.

2. Rotate the rolled door in the direction shown until the bottom rail is level with the shaft. 3. Tighten the saddle clamp nuts on both sides.

4. If an operator drive unit has been installed tighten the fixings and disengage the drive for manual  operation.

5. Pre-tension the door by rotating in the same direction as shown in the figure by 1¼ to 1¾ turns.

6. While holding the wrapped curtain, carefully cut and remove the packaging and slowly pull the curtain  into the guides, removing any cardboard and tape.

7. Carefully re-roll the curtain ensuring the bottom rail stays horizontal, leaving 500mm unrolled.

8. For drive operated doors, lock off the motor.

9. For manual doors fit a soft wood chock (300-400mm long) between bottom rail and door roll to prevent  door from winding back up.

10. Fix the door stop to each end of the bottom rail through the punched hole in the bottom rail as per  instructions.

11. A small slit will be required to be made in the weather seal to insert the bolt.

12. Secure the guide at the top slot allowing approximately 2-3mm running clearance per side from the  edge of curtain.

13. Lower the door and position the guide maintaining the clearance and secure at the bottom slot.

14. Remove any excess packaging and check the door runs freely to the floor, if not reposition guides as  required and secure at the slots.

15. Lower the door to the fully closed position and apply additional screws (PINNING) through the  curtain into the end drum wheels where curtain leaves the roll.

16. Use appropriate fixings to secure the guide to the jamb along the v-groove at 400mm intervals.

7.0 ADJUST DOOR TENSION

The initial door tension on the springs may either be too great or too little, making the door feel either light or  heavy. Ideal tensions make the door a little heavy in the down position ensuring it stays down and a little light in the up position ensuring it stays up. Two people are required to adjust the tension.

1. Door must be fully open (up) for one side to  retain spring tension.

2. Roll up the door and tie a rope or strap around the door in the centre to prevent the door from accidentally running down.

3. Loosen the saddle bolts on one side and fit a set of ‘stilsons’ to the axle on this end. The axle will try to turn in the direction that decreases tension.

4. While holding the stilsons firmly, have your assistant loosen the nuts of the saddle bolts on the other side.

5. Increase or decrease tension as required by rotating the axle a quarter of a turn at a time.

6. Your assistant can now tighten the nuts on the other side.

7. When tight, tighten the bolts at your side as well and then remove the stilsons.

8. Carefully try the door again. It may be necessary to repeat steps 3-6 several times until the tension is  correct.

NEVER ALTER DOOR TENSION UNLESS THE DOOR IS FULLY OPENED AND SECURED  WITH A ROPE. WHEN ADJUSTING TENSION, NEVER STAND CLOSE TO AND IN LINE WITH  STILSONS. KEEP HEAD AND BODY AWAY FROM THE STILSONS.

Call 1300 427 243 | steel-line.com.au Page 11 of 16

8.0 CONFIRM DOOR OPERATION

Series ’AA’ Roller Door Installation Guide

Operate the door several times and confirm that it runs smoothly.

When an automatic or chain-controlled operator is fitted the curtain should be pinned by putting suitable  length screws through curtain layers and into the drum wheels at each end of the curtain. The pinning is to  lock the curtain in place preventing potential conning occurring due to the operator driving from one end.

Call 1300 427 243 | steel-line.com.au Page 12 of 16

Series ’AA’ Roller Door Installation Guide

POST INSTALLATION

1.0 DIFFICULT TO OPERATE

a) Decrease or increase spring tension (see step 8.0, P11)

b) Check curtain isn’t jamming in the guides

c) Check running clearance in guide is (≈2mm per side)

d) Check guides are upright and clean. Do not lubricate, if cleaned ensure guide is dry before door  operation

2.0 DIFFICULT TO CLOSE OR OPEN

a) Decrease OR increase spring tension (see step 8.0, P13)

3.0 GUIDE/SHAFT RELATIONSHIP

If the door is very difficult to close the last 600mm, check the guides are fitted in correct relationship to the  brackets and that the axle is the correct distance from the wall (210 – 250mm) (see step 6.0, P11)

4.0 CONING

If the curtain rolls up un-evenly (cones out at one end) and the bottom rail appears out of parallel with door roll  and guides, confirm the following:

a) Brackets are level with each other

b) Axle is correctly centralised in roll (see step 3.0). If brackets are level, removing coning by moving the  axle through the roll in the opposite direction to coning and distance roughly equal to length of coning.

APPENDIX A

  Series ’AA’ Roller Door Installation Guide

BoM for Steel-Line Roller Door Hardware Boxes


PICTURE

|

DESCRIPTION

|

Yellow

‘AA’ QTY.

|

CAST SADDLE
CONFIGURATION

|

‘U’-BOLT

|

1

|

2

CAST SADDLE

|

1

3/8” HEX NUTS (GRADE 8.8)

|

2

3/8” WASHER

|

2

|

5/16″ – 9×2″ LAG SCREW

|

24

|

5/16″ FLAT WASHER

|

24

|

NYLON PLUG A10x50

|

24

|

ANTI-CONING COLLAR  CONFIGURATION

|

ANTI-CONING COLLAR

|

1

|

2

NUT

|

1

CARRIAGE BOLT

|

1

|

¼”-20×1½” TEK SCREW

|

18

|

5/16” – 18×18 HEX HEAD MACHINE SCREW

|

6

|

5/16” – 18 HEX NUTS

|

6

|

AA/B DOOR-STOP

CONFIGURATION

|

AA/B DOOR-STOPS

|

1

|

2

¼”-20×1” CUPHEAD BOLT

|

1

FLAT WASHER

|

1

NYLOC NUT

|

1

Call 1300 427 243 | steel-line.com.au Page 14 of 16

 Series ’AA’ Roller Door Installation Guide

BoM for Steel-Line Roller Door Kit Boxes


PICTURE

|

DESCRIPTION

|

‘AA/B’ Lead-in Kit  Box QTY.

|

AA/B DOOR NYLON LEAD-IN PAIR (LHS & RHS)

|

1

|

AA/B STOPPER PAIR (LHS & RHS)

|

1

|

8 – 1½” PAN HEAD PHILLIPS DRIVE SELF TAPPING  SCREW

|

2

|

M6x12 PAN HEAD MACHINE SCREW

|

4

|

16x3mm TAPPED PLATE

|

2

Call 1300 427 243 | steel-line.com.au Page 15 of 16

Series ’AA’ Roller Door Installation Guide

APPENDIX B

steel guide

Call 1300 427 243 | steel-line.com.au Page 16 of 16

References

Read User Manual Online (PDF format)

Read User Manual Online (PDF format)  >>

Download This Manual (PDF format)

Download this manual  >>

Related Manuals