Atlas PV10 Adjustable Overhead Two Post Lift Instruction Manual

May 15, 2024
Atlas

Atlas PV10 Adjustable Overhead Two Post Lift

Product Information

Specifications

  • Model: PV10
  • Style: Clear-floor Direct-drive
  • Lifting Capacity: 10000 LBS
  • Lifting Time: 55 seconds
  • Lifting Height: Variable
  • Overall Height: Variable
  • Overall Width: Variable
  • Width Between Columns: Variable
  • Minimum Pad Height: Variable
  • Motor: 2.0HP

Product Usage Instructions

Installation Requirement
A. Tools Required

  • Rotary Hammer Drill (19)
  • Carpenter’s Chalk
  • Hammer

B. Equipment Storage and Installation Requirements
The equipment should be stored or installed in a shady, moderately temperate, ventilated, and dry place.

C. Unloading and Transfer
The equipment should be unloaded and transferred by forklift.

E. Power Supply
220 volt single-phase motor on a 30 amp breaker with a minimum of 10 gauge wire. The operating voltage range is 208v-230v.

Installation Steps
A. Location of Installation
Check and ensure the installation location (concrete, layout, space size, etc.) is suitable for lift installation.

Frequently Asked Questions (FAQ)

  • Q: What should I do if the lifting capacity is exceeded?
    A: It is crucial to never exceed the specified lifting capacity to prevent damage to the equipment and ensure safety.

  • Q: Can the lift be operated outdoors?
    A: It is recommended to install and operate the lift in a suitable indoor environment to protect it from weather elements and ensure optimal performance.

PRODUCT FEATURES AND SPECIFICATIONS

CLEAR-FLOOR DIRECT-DRIVE MODEL FEATURES
Model PV10 (See Fig. 1)

  • Direct-drive design minimizes the lift wear parts and breakdown ratio.
  • Dual hydraulic cylinders, designed and made to high standards, utilizing imported oil seal in the cylinder.
  • Self-lubricating UHMW Polyethylene slide blocks and bronze bushings.
  • Single-point safety release with dual safety design.
  • The clear-floor design provides unobstructed floor use.
  • Overhead safety shut-off device prevents vehicle damage.

MODEL PV10 SPECIFICATIONSAtlas-PV10-Adjustable-Overhead-Two-Post-Lift-
fig-2

Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-
fig-3 Atlas-PV10-Adjustable-Overhead-Two-Post-
Lift-fig-4INSTALLATION REQUIREMENT

**A. TOOLS REQUIRED

**Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-5

B. Equipment storage and installation requirements.
The equipment should be stored or installed in a shady, moderately temperate, ventilated and dry place.

C. The equipment should be unloaded and transferred by forklift.Atlas-
PV10-Adjustable-Overhead-Two-Post-Lift-fig-6

D. SPECIFICATIONS OF CONCRETE (See Fig. 6)
Concrete specifications must be followed accordingly.
WARNING : Failure to do so may result in lift and/or vehicle falling.

  1. Concrete must be 4 inches minimum thickness, without reinforcing steel bars, and must be completely cured before lift installation.
  2. Concrete must be in good condition and must be of test strength of 3,000psi (210kg/cm²) minimum.
  3. Floors must be level with no cracks or holes.

Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-7

E. POWER SUPPLY
The 220-volt single-phase motor on a 30 amp breaker with a minimum of 10 gauge wire. The operating voltage range is 208v-230v.

INSTALLATION STEPS

A. Location of installation
Check and ensure the installation location (concrete, layout, space size, etc.) is suitable for lift installation.

B. Use a carpenter’s chalk line to establish the installation layout of the baseplate.(See Fig. 7)Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-
fig-8

C. Check the parts before assembly.

  1. Packaged lift and hydraulic power unit (See Fig. 8).vAtlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-9
  2. Move the lift aside with a forklift or hoist, and open the outer packing carefully and move aside the top connecting assy. and parts box (See Fig. 9).Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-10
  3. Lift the upper column with a forklift or hoist and loosen the bolts on the upper package stand. Remove the upper column and take out the parts in the bottom column. (See Fig. 10)
  4. Lift the lower column with a forklift or hoist, remove the package stand, then take off the lower column and remove the parts from the inner column (See Fig. 11).
  5. Move aside the parts and check the parts according to the shipment parts list.Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-13Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-14
  6. Check the parts of parts bag 1 according to the parts bag list (See Fig. 14).Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-15
  7. Check the parts of parts bag 2 according to the parts bag list (See Fig. 15).Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-16

D. Install the hydraulic hose and lock release cable brackets onAtlas-
PV10-Adjustable-Overhead-Two-Post-Lift-fig-17

E. Install hydraulic cylinder
Wrap both ends of straight fittings with white Teflon tape, and install straight fittings in each cylinder (See Fig. 17).

Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-18

F. Install columns
Lay down two columns on the installation site parallel of each other. Position the power side column according to the installation site. This lift is designed with 2- section columns. Adjust lift height according to the ceiling height and connect the inner and extension columns.

  1. 1. When the ceiling height is less than 147 5/8”, connect the extension columns with the top and middle holes on the extension (See Fig. 18)Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-20
  2. When the ceiling height is over 147 5/8”, connect the extension columns with the bottom and middle hole on the extension (See Fig. 19)

G. Position the columns
Position the columns so the base plates line up with a chalk line. Position the offside column parallel to the power side column. Install the overhead cross beam. Level and plumb the columns, shim where necessary. Drill 3/4” anchor holes. If the top of the anchor exceeds 2 inches above the floor grade, you DO NOT have enough embedment, tighten the anchor bolts to 150 Ft Lbs.
Do not drill holes for anchor bolts until overhead cross beam has been installed.(See Fig. 20)

Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-22 Note : Minimum embedment of Anchors is 4”.Atlas-PV10
-Adjustable-Overhead-Two-Post-Lift-fig-23

H. Install overhead top beam

  1. With help of the hook of top beam, put one side of top beam on top of the extension column and connect the top beam to the extension column by bolts, tighten the bolts.(See Fig. 21).Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-24
  2. Assemble the overhead top beam, and tighten the column’s anchor bolts (See Fig. 22).

I. Installing the limit switch control bar and limit switch (See Fig. 23)

J. Install safety device (See Fig. 24 & Fig. 25).Atlas-PV10-Adjustable-
Overhead-Two-Post-Lift-fig-27 Atlas-PV10
-Adjustable-Overhead-Two-Post-Lift-fig-28

K. Lift the carriages up manually and set on the 1st set of locks. (See Fig. 26).

L. Install cables

  1. High-setting cable connection:
  2. Take out the carriage’s plastic cover, cable pass through from the bottom of the
  3. Connecting cable for high setting (See Fig. 28)Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-31
  4. Low-setting cable connection (See Fig. 29).
    Note : Cable should go inside of the carriage.Atlas-PV10-Adjustable-
Overhead-Two-Post-Lift-fig-32

M. Install power unit (See Fig. 30)

N. Install oil hose
At high setting and low setting oil hose connection (See Fig. 31).Atlas-
PV10-Adjustable-Overhead-Two-Post-Lift-fig-33

O. Install safety cable.
Install safety cable from offside safety device to power-side safety device, pass through the top beam (See Fig. 32)Atlas-PV10-Adjustable-Overhead-Two-
Post-Lift-fig-34

P. Install hose retainers on both columns (See Fig. 33).

Q. Install lifting arms and adjust the arm locks

  1. Install lifting arms (See Fig. 34).
  2. Lower the carriages down to the lowest position, then use an 8mm Allen wrench to loosen the socket bolt (See Fig.35).
  3. Adjust the moon gear in the direction of the arrow (See Fig.36).
  4. Adjust the moon gear and arm lock to make it meshed, then tighten the socket bolts of the arm lock (See Fig.37).

Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-36

R. Tighten All Hydraulic Fittings and Fill the reservoir with Hydraulic Oil.
Approximately 4 gallons are required.
Note : For the best performance it is recommended to use AW32 or AW46 series hydraulic oil.

S. Install electrical system

  • Connect the power source according to the data plate on the Power Unit.
  • Remove the short “Pig Tail” wire connected to the AC contactor terminals. This wire was used to test the motor after production.

ATLAS Single-phase motor
Please Note : This motor is powered by Alternating Current and the terminals on the AC contactor are not wire color specific. There are no positive or negative terminals.
Single phase motor (See Fig. 38).

Remove Existing Pigtail From Lift (Do Not Operate Until Completed)

EXPLODED VIEW

Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-
fig-38

PV-10P PARTS LIST

Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-
fig-39Atlas-PV10-Adjustable-Overhead-Two-Post-
Lift-fig-40

TEST RUN

  1. Adjust the equalizing cable (See Fig. 44)Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-41Use a wrench to hold the cable end, meanwhile, use a ratchet to tighten the cable nuts until both cables have the same tension. If the two carriages do not lift at the same time, screw and tighten the cable nuts on the lower of the two carriages.

  2. Adjust safety cable
    Lift the carriages and lock at the same height, pull the safety cable and then release a little, and then tighten the safety cable nuts. Make sure the safety locks click at the same time.

  3. Bleeding air from oil cylinder (See Fig. 45)Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-42This hydraulic system is designed to bleed air by loosening the bleeding screw on top of the cylinders. Lift the carriages to about 12 inches and loosen the bleeding plug.
    Lower the lift until fluid comes out. Tighten the screws after bleeding.

  4. Adjust the lowering speed (Only for ATLAS power unit)
    (Adjust with a load on the lift) (See Fig. 46)
    You can adjust the lowering speed of the lift if needed: Loosen the locking nut on the throttle valve, and then turn the throttle valve clockwise to decrease the lowering speed, or counterclockwise to increase the lowering speed.Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-
fig-43

  5. Test with load
    After finishing the above adjustment, test running the lift with load. Run the lift in low position several times first. Run the lift to the top completely.
    NOTE : If the lift vibrates on the way up with a load, lubricate all pulley shafts and wear blocks. If the lift vibrates on the way down, the cylinders need to be bled.

Hydraulic Schematic DiagramAtlas-PV10-Adjustable-Overhead-Two-Post-Lift-
fig-44

OPERATION INSTRUCTIONS

Please read the safety tips carefully before operating the lift
To lift vehicle

  1. Keep the lift area clean and free of clutter;

  2. Position lift arms to the lowest position, on the floor;

  3. Open or swing lift arms away from the center of the lift;

  4. Position vehicle between columns;

  5. Move or swing arms to the vehicle’s lifting points;
    NOTE : The four lift arms must make contact at the same time with the vehicle’s lifting and both axles must rise off the ground at the same time

  6. Push the “UP” button until the lift pads contact the underside of the vehicle. Raise the vehicle just enough that the wheels are off the floor. Recheck to make sure the vehicle is secure.

  7. Continue to raise the lift slowly to the desired working height.

  8. Push the lowering handle to lower lift onto the nearest safety lock. The vehicle is ready to repair.
    NOTE : The lift must always be on the safety locks when holding a vehicle.

To lower vehicle

  1. Keep the lift area clean and free of clutter.
  2. Push the “UP” button to raise the vehicle slightly, and then pull the safety lock handle to release the safety locks, and lower the vehicle by depressing the power unit and lowering the handle.
  3. Lower the vehicle completely to the floor, until arms no longer contact the vehicle.
  4. Open the arms and position them to the shortest length.
  5. Drive the vehicle out of the lift.

MAINTENANCE SCHEDULE

Monthly:

  1. Re-torque the anchor bolts to 85 Ft Lbs;
    Note : All anchor bolts should take full torque. If any of the bolts do not for any reason, DO NOT use the lift until the bolt has been replaced.

  2. Check all connectors, bolts and pins to ensure proper mounting;

  3. Lubricate cable with lubricant;

  4. Make a visual inspection of all hydraulic hoses/lines for possible wear or leakage;

  5. Check Safety locks and make sure they are in proper condition;

  6. Lubricate all Rollers and Pins with 90wt. Gear oil or equivalent;

Every six months:

  1. Make a visual inspection of all moving parts for possible wear, interference or damage.
  2. Check and adjust as necessary the tension of the equalizer cables to ensure level lifting.
  3. Check columns for plumbness.
  4. Check Rubber Pads and replace as necessary.
  5. Check Safety locks and make sure proper condition.

Oil cylinder maintenance:
In order to extend the service life of the oil cylinder, please operate according to the following requirements.

  1. Recommend the use of AW32 or AW46 anti-wear hydraulic oil.
  2. The hydraulic oil of the lifts should be replaced regularly during use. Replace the hydraulic oil 3 months after the first installation, Replace the hydraulic oil once a year afterwards.
  3. Make at least one full trip raising and lowering per day. To bleed any air from the system, which could effectively avoid the corrosion of the cylinder and damage to the seals caused by presence of air or water in the system.

Protect the outer surface of the oil cylinder’s piston rod from bumping and scratching, and clean any debris on the oil cylinder dust-ring and the piston rod as soon as possible.

TROUBLE SHOOTING

Atlas-PV10-Adjustable-Overhead-Two-Post-Lift-fig-45

LIFT DISPOSAL

When the car lift cannot meet the requirements for normal use and needs to be disposed of, it should follow local laws and regulations.

WARRANTY

This item is warranted for five (5) years on structural components, two (2) years on hydraulic cylinders, and one (1) year on electric or air / hydraulic power units from invoice date. Wear items are covered by a 90-day warranty.
This LIMITED warranty policy does not include a labor warranty.
NOTE : ALL WARRANTY CLAIMS MUST BE PRE-APPROVED BY THE MANUFACTURER TO BE VALID.
The Manufacturer shall repair or replace at their option for this period those parts returned to the factory freight prepaid, which prove after inspection to be defective. This warranty will not apply unless the product is installed, used, and maintained under the Manufacturer’s installation, operation and maintenance instructions. This warranty applies to the ORIGINAL purchaser only and is non-transferable. The warranty covers the products to be free of defects in material and workmanship but, does not cover normal maintenance or adjustments, damage or malfunction caused by: improper handling, installation, abuse, misuse, negligence, carelessness of operation or normal wear and tear. In addition, this warranty does not cover equipment when repairs or alterations have been made or attempted to the Manufacturer’s products. THIS WARRANTY IS EXCLUSIVE AND IS IN LIEU OF ALL OTHER WARRANTIES EXPRESSED OR IMPLIED INCLUDING ANY IMPLIED WARRANTY OR MERCHANTABILITY OR ANY IMPLIED WARRANTY OF FITNESS FROM A PARTICULAR PURPOSE, AND ALL SUCH IMPLIED WARRANTIES ARE EXPRESSLY EXCLUDED. THE REMEDIES DESCRIBED ARE EXCLUSIVE AND IN NO EVENT SHALL THE MANUFACTURER, NOR ANY SALES AGENT OR OTHER COMPANY AFFILIATED WITH IT OR THEM, BE LIABLE FOR SPECIAL CONSEQUENTIAL OR INCIDENTAL DAMAGES FOR THE BREACH OF OR DELAY IN PERFORMANCE OF THIS WARRANTY. THIS INCLUDES BUT IS NOT LIMITED TO, LOSS OF PROFIT, RENTAL OR SUBSTITUTE EQUIPMENT OR OTHER COMMERCIAL LOSS.
PRICES : Prices and specifications are subject to change without notice. All orders will be invoiced at prices prevailing at the time of shipment. Prices do not include any local, state or federal taxes.
RETURNS : Products may not be returned without prior written approval from the
Manufacturer. DUE TO THE COMPETITIVENESS OF THE SELLING PRICE OF THESE LIFTS, THIS

WARRANTY POLICY
WILL BE STRICTLY ADMINISTERED AND ADHERED TO.
Revise Date:09/29/23

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

Related Manuals