The copyright of this manual belongs to Solax Power Network Technology(Zhe jiang) Co,. Ltd.. Any corporation or individual should not plagiarize, partitially or fully copy (including software,etc.), and no reproduction or distribution of it in any form or by any means. All rights reserved. SolaX Power Network Technology (Zhe jiang) Co.,Ltd. (SolaX Power Co.,Ltd.). reserves

Notes on this Manual

1.1 Scope of Validity
This manual is an integral part of X1-Hybrid, It describes the assembly, installation, commissioning, maintenance and failure of the product. Please read it carefully before operating.

X1-Hybrid-3.0-N-E X1-Hybrid-3.7-N-E X1-Hybrid-4.6-N-E X1-Hybrid-5.0-N-E
X1-Hybrid-3.0-D-E X1-Hybrid-3.7-D-E X1-Hybrid-4.6-D-E X1-Hybrid-5.0-D-E
X1-Hybrid-3.0-N-I X1-Hybrid-3.7-N-I X1-Hybrid-4.6-N-I X1-Hybrid-5.0-N-I
X1-Hybrid-3.0-D-I X1-Hybrid-3.7-D-I X1-Hybrid-4.6-D-I X1-Hybrid-5.0-D-I
X1-Hybrid-3.0-N-C X1-Hybrid-3.7-N-C X1-Hybrid-4.6-N-C X1-Hybrid-5.0-N-C
X1-Hybrid-3.0-D-C X1-Hybrid-3.7-D-C X1-Hybrid-4.6-D-C X1-Hybrid-5.0-D-C

Note: “3.0” means 3.0kW.
“D” means with “DC Switch”, ”N” means without “DC Switch”.
“E” means “EPS function” will be available with an external changeover device installed.
“I” means “EPS function” available as unit already content an internal changeover device.
“C “means without”EPS function”.
Store this manual where it will be accessible at all times.
1.2 Target Group
This manual is for qualified electricians. The tasks described in this manual only can be performed by qualified electricians.
1.3 Symbols Used
The following types of safety instructions and general information appear in this document as described below:
Danger!
“Danger” indicates a hazardous situation which, if not avoided, will result in death or serious injury.
Warning!
“Warning” indicates a hazardous situation which, if not avoided, could result in death or serious injury.
Caution!
“Caution” indicates a hazardous situation which, if not avoided, could result in minor or moderate injury.
Note!
“Note” provides tips that are valuable for the optimal operation of our product.

Safety

2.1 Important Safety Instructions

Danger!
Danger to life due to high voltages in the inverter!
All work must be carried out by qualified electrician.
The appliance is not to be used by children or persons with reduced physical sensory or mental capabilities, or lack of experience and knowledge, unless they have been given supervision or instruction.
Children should be supervised to ensure that they do not play with the appliance.
Caution!
Danger of burn injuries due to hot enclosure parts!
During operation, the upper lid of the enclosure and the enclosure body may become hot.
Only touch the lower enclosure lid during operation.
Caution!
Possible damage to health as a result of the effects of radiation!
Do not stay closer than 20 cm to inverter for any length of time.
Note!
Grounding the PV generator.
Comply with the local requirements for grounding the PV modules and the PV generator. It is recommends connecting the generator frame and other electrically conductive surfaces in a manner which ensures continuous conduction and ground these in order to have optimal protection of system and persons.
Warning!
Ensure input DC voltage ≤Max. DC voltage .Over voltage may cause permanent damage to inverter or other losses, which will not be included in warranty!
Warning!
Authorized service personnel must disconnect both AC and DC power from inverter before attempting any maintenance or cleaning or working on any circuits connected to inverter.
WARNING !
Do not operate the inverter when the device is running.
WARNING !
Risk of electric shock!

  • Prior to the application, please read this section carefully to ensure correct and safe application. Please keep the user manual properly. Accesories only together with the inverter shipment are recommanded here.
  • Otherwise may result in a risk of fire, electric shock, or injury to person. Make sure that existing wiring is in good condition and that wire is not undersized.
  • Do not disassemble any parts of inverter which are not mentioned in installation guide. It contains no user-serviceable parts. See Warranty for instructions on obtaining service. Attempting to service the inverter yourself may result in a risk of electric shock or fire and will void your warranty.
  • Keep away from flammable, explosive materials to avoid fire disaster.
  • The installation place should be away from humid or corrosive substance.
  • Authorized service personnel must use insulated tools when installing or working with this equipment.
  • PV modules shall have an IEC 61730 class A rating.
  • Never touch either the positive or negative pole of PV connecting device. Strictly prohibit touching both of them at the same time.
  • The unit contains capacitors that remain charged to a potentially lethal voltage after the MAINS , battery and PV supply has been disconnected.
  • Hazardous voltage will present for up to 5 minutes after disconnection from power supply.
  • CAUTION-RISK of electric shock from energy stored in capacitor, Never operate on the inverter couplers, the MAINS cables, Battery cables, PV cables or the PV generator when power is applied. After switching off the PV , battery and Mains, always wait for 5minutes to let the intermediate circuit capacitors discharge before unpluging DC ,battery inplug and MAINS couplers.
  • When accessing the internal circuit of inverter, it is very important to wait 5 minutes before operating the power circuit or demounting the electrolyte capacitors inside the device. Do not open the device before hand since the capacitors require time to sufficiently discharge!
  • Measure the voltage between terminals UDC+ and UDC- with a multi-meter (impedance at least 1Mohm) to ensure that the device is discharged before beginning work (35VDC) inside the device.

Surge protection devices (SPDs) for PV installation
WARNING !
Over-voltage protection with surge arresters should be provided when the PV power system is installed.
The grid connected inverter is not fitted with SPDs in both PV input side and MAINS side.
Lightning will cause a damage either from a direct strike or from surges due to a nearby strike.
Induced surges are the most likely cause of lightning damage in majority or installations, especially in rural areas where electricity is usually provided by long overhead lines. Surge may be included on both the PV array conduction and the AC cables leading to the building.
Specialists in lightning protection should be consulted during the end use application. Using appropriate external lightning protection, the effect of a direct lightning strike into a building can be mitigated in a controlled way, and the lightning current can be discharged into the ground.
Installation of SPDs to protect the inverter against mechanical damage and excessive stress include a surge arrester in case of a building with external lightning protection system (LPS) when separation distance is kept.
To protect the DC system, surge suppression device (SPD type2) should be fitted at the inverter end of the DC cabling and at the array located between the inverter and the PV generator, if the voltage protection level (VP) of the surge arresters is greater than 1100V, an additional SPD type 3 required for surge protection for electrical devices.
To protect the AC system, surge suppression devices (SPD type2) should be fitted at the main incoming point of AC supply (at the consumer’s cutout), located between the inverter and the meter/distribution system; SPD (test impulse D1) for signal line according to EN 61632-1.
All DC cables should be installed to provide as short a run as possible, and positive and negative cables of the string or main DC supply should be bundled together. Avoiding the creation of loops in the system. This requirement for short runs and bundling includes any associated earth bundling conductors.
Spark gap devices are not suitable to be used in DC circuits once conducting, they won’t stop conducting until the voltage across their terminals is typically more than 30 volts.
► Anti-Islanding Effect
Islanding effect is a special phenomenon that grid-connected PV system still supply power to the nearby grid when the voltage loss is happened in the power system. It is dangerous for maintenance personnel and the public. X1-Hybrid seires inverter provide Active Frequency Drift(AFD) to prevent islanding effect.
► PE Connection and Leakage Current

  • All inverters incorporate a certified internal Residual Current Device(RCD) in order to protect against possible electrocution and fire hazard in case of a malfunction in the PV array, cables or inverter.There are 2 trip thresholds for the RCD as required for certification (IEC 62109-2:2011). The default value for electrocution protection is 30mA,and for slow rising current is 300mA.

  • If an external RCD is required by local regulations,check which type of RCD is required for relevant electric code. It recommends using a type-A RCD. The recommended RCD values is 100mA or 300mA unless a lower value is required by the specific local electric codes.When required by local regulations,the use of an RCD type B is permitted.
    WARNING!
    High leakage current!
    Earth connection essential before connecting supply.

  • Incorrect grounding can cause physical injury, death or equipment malfunction and increase electromagnetic.

  • Make sure that grounding conductor is adequately sized as required by safety regulations.

  • Do not connect the ground terminals of the unit in series in case of a multiple installation. This product can cause current with a d.c component, Where a residual current operated protective (RCD) or monitoring (RCM) device is used for protection in case of direct or indirect contact, only an RCD or RCM of type B is allowed on the supply side of this product.

For United Kingdom

  • The installation that connects the equipment to the supply terminals shall comply with the requirements of BS 7671.
  • Electrical installation of PV system shall comply with requirements of BS 7671 and IEC 60364-7-712.
  • No protection settings can be altered.
  • User shall ensure that equipment is so installed, designed and operated to maintain at all times compliance with the requirements of ESQCR22(1)(a).

For Australia and New Zealand

  • Electrical installation and maintenance shall be conducted by licensed electrician and shall comply with Australia National Wiring Rules.

► Battery Safety Instructions
SolaX X1-Hybrid Series inverter should be worked with high voltage battery, for the specific parameters such as battery type, nominal voltage and nominal capacity etc., please refer to section 4.3.
As accumulator batteries may contain potential electric shock and short- circuit current danger, to avoid accidents that might be thus resulted, the following warnings should be observed during battery replacement:

  1. Do not wear watches, rings or similar metallic items.
  2. Use insulated tools.
  3. Put on rubber shoes and gloves.
  4. Do not place metallic tools and similar metallic parts on the batteries.
  5. Switch off load connected to the batteries before dismantling battery connection terminals.
  6. Only personal with proper expertise can carry out the maintenance of accumulator batteries.

2.2 Explanation of Symbols
This section gives an explanation of all the symbols shown on the inverter and on the type label.
Symbols on the Inverter

Symbol Explanation
Operating Display.
Battery communication is active.
An error has occurred, please inform your installer immediately.

Symbols on the Type Label

Symbol Explanation
CE mark.

The inverter complies with the requirements of the applicable CE guildlines.
| TUV certified.
| RCM remark.
| SAA certification.
| Beware of hot surface.
The inverter can become hot during operation. Avoid contact during operation.
| Danger of high voltages.
Danger to life due to high voltages in the inverter!
| Danger.
Risk of electric shock!
| Observe enclosed documentation.
****| The inverter can not be disposed together with the household waste.
Disposal information can be found in the enclosed documentation.
| Do not operate this inverter until it is isolated from battery,mains and on- site PV generation suppliers.
| Danger to life due to high voltage.
There is residual voltage existing in the inverter after powering off, which needs 5 min to discharge.
•  Wait 5 min before you open the upper lid or the DC lid.

2.3 CE Directives
This chapter follows the requirements of the European low voltage directives, which contains the safety instructions and conditions of acceptability for the endues system, which you must follow when installing, operating and servicing the unit. If ignored, physical injury or death may follow, or damage may occur to the unit. Read this instructions before you work on the unit. If you are unable to understand the dangers, warnings, cautions or instructions, please contact an authorized service dealer before installing. Operating and servicing the unit.
The Grid connected inverter meets the requirement stipulated in Low Voltage Directive (LVD) 2014/35/EU and Electromagnetic Compatibility (EMC) Directive 2014/30/EU. The unit is based on:
EN 62109-1:2010 ; EN 62109-2:2011 ; IEC 62109-1(ed.1) ; IEC62109-2(ed.1) EN 61000-6-3:2007+A:2011 ; EN 61000-6-1:2007 ; EN 61000-6-2:2005 In case of installation in PV system, startup of the unit (i.e. start of designated operation) is prohibited until it is determined that the full system meets the requirements stipulated in EC Directive (2014/35/EU,2014/30/EU, etc.) The grid connected inverter leave the factory completely connecting device and ready for connection to the mains and PV supply ,the unit shall be installed in accordance with national wiring regulations. Compliance with safety regulations depends upon installing and configuring system correctly, including using the specified wires. The system must be installed only by professional assemblers who are familiar with requirements for safety and EMC. The assembler is responsible for ensuring that the end system complies with all the relevant laws in the country where it is to be used.
The individual subassembly of the system shall be interconnected by means of the wiring methods outlined in national/international such as the national electric code (NFPA) No.70 or VDE regulation 0107.

Introduction

3.1 Basic features
X1-Hybrid Seires is a high-quality inverter which can convert solar energy to AC energy and store energy into battery.
The inverter can be used to optimize self consumption, store in the battery for future use or feedin to public grid. Work mode depends on PV energy and user’s preference. It can provide power for emergency use during the grid lost by using the energy from battery and inverter(generated from PV).
► System Diagram
X1-Hybrid Series is designed with two EPS versions for customer to choose based on the local rules.
E Version applies to the wiring rules that requires the Live line and Neutral line of EPS must be disconnected with the Live line and Neutral line of grid. (applies to most countires)

I Version applies to the wiring rules that requires Neutral line of alternative supply must NOT be isolated or switched (applies to wiring rules AS/NZS_3000:2012 for Australia and New Zealand).

Note!

  • Please control the home loads, and make sure it’s within the “EPS output rating” under EPS mode, otherwise the inverter will shutdown with an “overlaod fault” warning.
  • Please confirm with the mains grid operator whether there is any special regulations for grid connection.

3.2 Work Modes
X1-Hybrid Series inverter provides multiple work modes based on different requirements.

| Work modes:  Self-use (with PV Power)
Priority: load>battery>grid
This mode applies the area that has low feed-in tariff and high energy price.
The power generated from PV will be used to supply the local loads firstly, then to charge the battery. The redundant power will export to the public grid.
---|---
| Work modes:  Self-use (without PV Power)
When no PV supplied, battery will discharge for local loads firstly, and grid will supply power when the battery capacity is not enough.
| Work modes:  Force time use
Priority:battery>load>grid(when charging)
Priority:load>battery>grid(when discharging)
This mode applies the area that has electricity price between peak and valley. User can use offpeak electricity to charge the battery.
The charging and discharging time can be set flexibly, and it also allows to choose whether charge from the grid or not.
| Work modes:  Feed in Priority
Priority:load>grid>battery
This mode applies the area that has high feed-in tariff and export control.
The PV generated power will be used to supply the local loads firstly, then export to the public grid. The redundant power will charge the battery.
| Work modes:  Back up mode
Priority:battery>load>grid
This mode applies the area that has frequent power outages. And  this mode ensures the battery will has enough energy to supply when the grid is off.
In this mode battery will be charging forcibly in the setting time and will never be discharged when the grid is on, and it also allows to choose whether charge from the grid or not.
| EPS Status
When the grid is off, system will supply emergency power from PV or battery to supply the home loads. (Battery is necessary in EPS mode.)

3.3 Dimension

3.4 Terminals of PV inverter

Object Description
A DC switch (optional)
B PV connection area
C Battery connection area
D EPS output
E Grid output
F Battery communication
G WiFi port for external Pocket WiFi
H Earthing screw
I Waterproof valve
J CAN communication port for parallel operation/ Generator communication port

(Both functions are being developed.)
K| Ethernet port
L| DRM / External meter port
M| External port for smart plug

WARNING !
Qualified electrician will be required for the installation.

Technical Data

4.1 DC input ( apply to version E, I, C )

Model| X1-Hybrid-3.0-D
X1-Hybrid-3.0-N| X1-Hybrid-3.7-D
X1-Hybrid-3.7-N| X1-Hybrid-4.6-D
X1-Hybrid-4.6-N| X1-Hybrid-5.0-D
X1-Hybrid-5.0-N
---|---|---|---|---
Max. recommended DC power [W]| A:3000,B:3000| A:3000,B:3000| A:3000,B:3000| A:3000,B:3000
Max. DC voltage[V]| 600| 600| 600| 600
Norminal DC operating voltage[V]| 360| 360| 360| 360
MPPT voltage range [V]| 125-550| 125-550| 125-550| 125-550
MPPT voltage range@full load [V]| 133-500| 162-500| 200-500| 217-500
Max. input current [A]| 12/12| 12/12| 12/12| 12/12
Max. short circuit current [A]| 14/14| 14/14| 14/14| 14/14
Start input voltage [V]| 100| 100| 100| 100
Start output voltage [V]| 150| 150| 150| 150
No. of MPP trackers| 2| 2| 2| 2
Strings per MPP tracker| 1| 1| 1| 1
Backfeed current to PV array| 0| 0| 0| 0
DC disconnection swtich| optional

4.2 AC output/input ( apply to version E, I, C )

Model| X1-Hybrid-3.0-D
X1-Hybrid-3.0-N
| X1-Hybrid-3.7-D
X1-Hybrid-3.7-N
| X1-Hybrid-4.6-D
X1-Hybrid-4.6-N
| X1-Hybrid-5.0-D
X1-Hybrid-5.0-N

---|---|---|---|---
AC output
Norminal AC power[VA]| 3000| 3680| 4600| 4999
Max. apparent AC power[VA]| 3300| 4048| 5060| 5499
Rated grid voltage(range)[V]| 220/230/240 (180 to 270)
Rated grid frequency[Hz]| 50/60
Norminal AC current[A]| 13| 16| 20| 21.7
Max.AC current[A]| 14.3| 17.6| 22| 23.9
Displacement power factor| 0.8 leading 0.8 lagging
Total harmonic distortion( THDi)| < 2%
Load control| optional
AC input
Norminal AC power[VA](E&C Version)| 3000| 3680| 4600| 4999
Norminal AC power[VA](I Version)| 3000+4000(bypass)| 3680+4000(bypass)| 4600+5000(bypass)| 4999+5000(bypass)
Rated grid voltage(range)[V]| 220/230/240 (180 to 270)
Rated grid frequency[Hz]| 50/60
Norminal AC current[A](E&C Version)| 13| 16| 20| 21.7
Max.AC current[A](E&C Version)| 14.4| 16| 21| 21.7
Norminal AC current[A](I Version)| 13+17.4(bypass)| 16+17.4(bypass)| 20+17.4(bypass)| 21.7+17.4(bypass)
Max. AC current[A](I Version)| 14.4+21.7(bypass)| 16+21.7(bypass)| 21+26.0(bypass)| 21.7+26.0(bypass)
Displacement power factor| 0.8 leading 0.8 lagging
AC inrush current| 35| 35| 35| 35
AC maximum output fault current| 80| 80| 80| 80

4.3 Internal Charger ( apply to version E, I, C )

Model| X1-Hybrid-3.0-D
X1-Hybrid-3.0-N| X1-Hybrid-3.7-D
X1-Hybrid-3.7-N| X1-Hybrid-4.6-D
X1-Hybrid-4.6-N| X1-Hybrid-5.0-D
X1-Hybrid-5.0-N
---|---|---|---|---
Battery type| Lithium battery
Battery voltage range[V]| 85-400
Recommended battery voltage[V]| 300VDC
Recommended battery capacity[KWh]| 4.8-16.8
Max. charge/discharge current[A]| 20A(adjustable)
Peak charge/discharge current[A]| 30A, 30s
Communication interfaces| CAN/RS485
Reverse connect protection| Yes

4.4 Efficiency, Safety and Protection ( apply to version E, I,C )

Model| X1-Hybrid-3.0-D
X1-Hybrid-3.0-N| X1-Hybrid-3.7-D
X1-Hybrid-3.7-N| X1-Hybrid-4.6-D
X1-Hybrid-4.6-N| X1-Hybrid-5.0-D
X1-Hybrid-5.0-N
---|---|---|---|---
MPPT efficiency| 99.90%| 99.90%| 99.90%| 99.90%
Euro efficiency| 97.00%| 97.00%| 97.00%| 97.00%
Max. efficiency| 97.80%| 97.80%| 97.80%| 97.80%
Max. Battery charge efficiency (PV to BAT )(@full load)| 98.50%| 98.50%| 98.50%| 98.50%
Max. Battery discharge efficiency (BAT to AC)(@full load)| 97.00%| 97.00%| 97.00%| 97.00%
Safety & Protection|
Over/under voltage protection| YES
DC isolation protection| YES
Monitoring ground fault protection| YES
Grid protection| YES
DC injection monitoring| YES
Back feed current monitoring| YES
Residual current detection| YES
Anti-islanding protection| YES
Over load protection| YES
Over heat protection| YES

4.5 EPS output ( apply to version E, I )

Model| X1-Hybrid-3.0-D
X1-Hybrid-3.0-N| X1-Hybrid-3.7-D
X1-Hybrid-3.7-N| X1-Hybrid-4.6-D
X1-Hybrid-4.6-N| X1-Hybrid-5.0-D
X1-Hybrid-5.0-N
---|---|---|---|---
EPS rated power[VA]| 4000| 4000| 5000| 5000
Max. EPS power[VA]| 5000| 5000| 6000| 6000
EPS rated voltage[v], Frequency[Hz]| 230VAC, 50/60
EPS rated current[A]| 17.4| 17.4| 21.7| 21.7
Max. EPS current[A]| 21.7| 21.7| 26.0| 26.0
EPS peak power[W]| 6000,10s| 8000,10s
Switch time[s]| <500ms
Total harmonic distortion( THDv)| <2%
Parallel operation| Yes
Compatible with the generator| Yes(signal provided only)

4.6 General Data ( apply to version E, I, C )

Model| X1-Hybrid-3.0-D
X1-Hybrid-3.0-N| X1-Hybrid-3.7-D
X1-Hybrid-3.7-N| X1-Hybrid-4.6-D
X1-Hybrid-4.6-N| X1-Hybrid-5.0-D
X1-Hybrid-5.0-N
---|---|---|---|---
Dimension W/H/D| 476464180
Dimension of packing W/H/D| 600540350
Net weight [kg]| 24| 24| 24| 24
Gross weight [kg]| 27| 27| 27| 27
Installation| Wall-mounted
Operating temperature range[℃]| -20~+60 (derating at 45)
Storage temperature [℃]| -20~+60
Storage/Operation relative humidity| 4%~100% (Condensing)
Altitude [m]| <2000
Ingress Protection| IP65(for outdoor use)
Protective Class| Ⅰ
Night-time consumption| <3W
Over Voltage Category| Ⅲ(MAINS),Ⅱ(PV,Battery)
Pollution Degree| III
cooling| Nautral
Noise level| <40dB
Inverter Topology| non-isolated
Communication interface| Ehternet, Meter, Wifi(optional), RF(optional), DRM, USB

Installation

5.1 Check for Physical Damage
Make sure the inverter is intact during transportation. If there is any visible damage, such as cracks, please contact your dealer immediately.
5.2 Packing List
Open the package and take out the product, please check the accessories first.
The packing list shown as below.

Object Description
A Inverter
B Bracket
C Expansion tubes & Expansion screws
D PV connectors (2positive, 2negative)
E Battery connectors (1positive, 1negative)
F PV pin connectors (2positive, 2negative)
G 4 6AWG AC terminals and 4 10AWG AC terminals for Version I

4 10AWG AC terminals and 4 8AWG AC terminals  for Version E and Version C
H| Ring terminal(for external enclosure grounding)
I| Ring terminal(for internal enclosure grounding)
J| gasket( for using thin cable to connect on the AC port)
K| Grounding nut
L| Set screw( for mounting)
M| User manual
N| Warranty card
O| Quick installation guide
P| Wifi module (optional)
Q| 8pin positive terminal
R| cable connector

5.3 Mounting
Installation Precaution
X1-Hybrid Series inverter is designed for outdoor installation (IP 65).
Make sure the installation site meets the following conditions:

  • Not in direct sunlight.
  • Not in areas where highly flammable materials are stored.
  • Not in potential explosive areas.
  • Not in the cool air directly.
  • Not near the television antenna or antenna cable.
  • Not higher than altitude of about 2000m above sea level.
  • Not in environment of precipitation or humidity (>95%).
  • Under good ventilation condition.
  • The ambient temperature in the range of -20℃ to +60℃.
  • The slope of the wall should be within ±5°.
  • The wall hanging the inverter should meet conditions below:
    1.solid brick/concrete, or strength equivalent mounting surface;
    2.Inverter must be supported or strengthened if the wall’s strength isn’t enough(such as wooden wall, the wall covered by thick layer of decoration)

Please AVOIDE direct sunlight, rain exposure, snow laying up during installation and operation.

Space Requirement

Table Available Space Size

Position Min.size
Left 300mm
Right 300mm
Top 300mm
Bottom 300mm
Front 300mm

Mounting Steps
Tools required for installation.
Installation tools : crimping pliers for binding post and RJ 45, screwdriver, manual wrench and φ10 driller.

Step 1: Screw the wall bracket on the wall
1.1 Place the bracket on the wall and mark down the position of the 4 holes.
1.2 Drill holes with driller, make sure the holes are deep enough (at least 60mm) to support the inverter.
1.3 Install the expansion tubes in the holes, and tighten them. Then install the wall bracket with the expansion screws.
Step 2: Place the inverter on the wall mounted bracket by holding the handle on the side.
Step 3: Screw the set screw on the left-bottom of inverter tightly.
Step 4: If necessary, costomer can install an anti-theft lock on the left- bottom of the inverter.

Electrical Connection

6.1 PV connection
X1-Hybrid can be connected in series with 2-strings PV modules for 3.0KW, 3.7KW, 4.6KW and 5KW.
Select PV modules with excellent function and reliable quality. Open-circuit voltage of module arrays connected in series should be <Max. DC input voltage; operating voltage should be conformed to MPPT voltage range.
Max.DC Voltage Limitation

Model| X1-Hybrid-3.0-D
X1-Hybrid-3.0-N| X1-Hybrid-3.7-D
X1-Hybrid-3.7-N| X1-Hybrid-4.6-D
X1-Hybrid-4.6-N| X1-Hybrid-5.0-D
X1-Hybrid-5.0-N
---|---|---|---|---
Max. DC Voltage (V)| 600
MPPT Voltage Range(V)| 125-550

Warning!

  • PV module voltage is very high, which already achieve dangerous voltage range, please comply with electric safety rules when connecting.
  • Please do not make PV positive or negative ground!

Note!

  • Please choose a fitting external DC switch if the model (X1-Hyrbid-3.0N, X1-Hyrbid-3.7-N, X1-Hyrbid-4.6-N, X1-Hyrbid-5.0-N) is purchased.
  • The following requirements of PV modules need to be applied for each input area; – Same type – Same quantity – Identical alignment – Identical tilt Please do not make PV positive or negative ground!
  • In order to save cable and reduce the DC loss, we suggest to install the inverter near PV modules.

Note!
PV connection mode below is NOT allowed!

Connection Steps
Below tools are needed before connection.

a) Turn off the DC switch, then Choose 12 AWG wire to connect the PV module.
b) Trip 7mm of insulation from the wire end by using the strpping pliers.

c) Insert striped wire into pin contact and ensure all conductor strand are captured in the pin contact.

d) Crimp pin contact by using the wire crimper.

e) Separate the DC connector as two parts: the plug and the cable nut.
Then insert the wire with pin contact through the cable nut.

f ) Insert the wire into plug forcibly, when a “click” is heard or felt the pin contact assembly is seated correctly. Then tighten the cable nut.

6.2 Grid Connection
X1-Hybrid series inverter are designed for single phase grid. Voltage is 220/230/240V, frequency is 50/60Hz. Other technical requests should comply with the requirement of the local public grid.
Table 4 Cable and Micro-breaker recommended

Model| X1-Hybrid-3.0-D
X1-Hybrid-3.0-N| X1-Hybrid-3.7-D
X1-Hybrid-3.7-N| X1-Hybrid-4.6-D
X1-Hybrid-4.6-N| X1-Hybrid-5.0-D
X1-Hybrid-5.0-N
---|---|---|---|---
E Version & C Version
Cable| 4-5mm²| 4-5mm²| 5-6mm²| 5-6mm²
Micro-breaker| 20A| 20A| 32A| 32A
I Version
Cable| 8-10mm²| 8-10mm²| 10-13mm²| 10-13mm²
Micro-breaker| 50A| 50A| 63A| 63A

Micro-breaker should be installed between inverter and grid, any load should not be connected with inverter directly.
Connection Steps:
Step1. Check the grid voltage.
1.1 Check the grid voltage and compare with the permissive voltage range (Please refer to technical data).
1.2 Disconnect the circuit board from all the phases and secure against re- connection.
Step2. Remove the top-down cover from the inverter.
Step3. Make AC wires.
3.1 Choose the appropriate wire(Cable size: refer to Table 4).
3.2 Reserve about 60mm of conductor material sectional area.
3.3 Remove 12mm of insulation from the end of wire.
3.4 Insert stripped wires into AC terminal and ensure that all conductor strands are captured in the AC terminal.
3.5 Compress the AC terminal head by using a crimping pliers and screw down screw cap tightly.
Step4. Insert AC cable into Grid port through screw cap and then tighten the screw cap. Insert L wire and N wire into corresponding ports of AC terminal.
Compress the PE wire with earth terminal , then screw it on the grounding stud.

6.3 EPS Connection( apply to I Version and E Version only)
X1-Hybrid series inverter has On and Off grid function, the inverter will deliver output power through AC port when the grid is on, and it will deliver output power through EPS port when the the grid is off.

  • I Version & E Version
    X1-Hybrid series inverter provides two versions for customer to choose based on the local rules.
    “I Version” means inverter has an build-in changeover switch. This version applies to the wiring rules which requires Neutral line of alternative supply must not be isolated or switched.(applies to wiring rules AS/NZS3000:2014 of Australia and New Zealand.)
    “E Version” means inverter needs to install an external changeover device for EPS function. This version applies to the wiring rules which allows Neutral line of alternative supply can be isolated or switched.( applies to most of the countries)

  • Auto & Manual
    EPS function can be achieved automatically or manually according to user’s wishes. For “I Version” inverter, EPS function can only be triggered automatically. For “E Version” inverter, EPS function can be triggered either automatically or manually according to user’s preference.
    If user wants to use this function manually, it will need to be installed an external switch. Please refer to specific wiring diagram below. For automatical solution, please contact our sales.

● I Version ● Auto ● Do not required for Changeover Switch

● E Version ● Manual ● Required for Changeover Switch

● E Version ● Auto ● Required for Changeover Switch

Please contact our sales for any compatible contactor purchase requirement .
Note!
In case of discrepancies between wiring mode of local policy and the operation guide above, espescially for the wiring of neutral line, grounding and RCD, please contact us before any operation!

Connection Steps:
Step1. Make EPS wires.
3.1 Choose the appropriate wire(cable size: refer to picture below).
3.2 Reserve about 60mm of conductor material sectional area.
3.3 Remove 12mm of insulation from the end of wire.
3.4 Insert stripped wires into AC terminal and insure all conductor strands are captured in the AC terminal.
3.5 Compress the AC terminal head by using a crimping pliers and screw down screw cap tightly.
Step2. Insert EPS cable into EPS port through screw cap and then tighten the screw cap. Insert L wire, N wire and PE wire( PE wire applies to E Version only) into corresponding ports of EPS terminal and screw them tightenly.

Table 5 Cable and Micro-breaker recommended

Model| X1-Hybrid-3.0-D
X1-Hybrid-3.0-N| X1-Hybrid-3.7-D
X1-Hybrid-3.7-N| X1-Hybrid-4.6-D
X1-Hybrid-4.6-N| X1-Hybrid-5.0-D
X1-Hybrid-5.0-N
---|---|---|---|---
EPS Cable| ≥5mm²| ≥5mm²| ≥5mm²| ≥5mm²
EPS breaker| 25A| 25A| 32A| 32A

Step 2

Requirements for EPS load
WARNING !
Make sure the EPS load power rating is within EPS output rating, otherwise the inverter will shutdown with an “over load” warning. When an “over load” is appeared, adjust the load power to make sure it is within the EPS output power range, then turn the inverter back on.
For the nonlinear load, please make sure the inrush power should be within the EPS output power range.
Below table shows some common feasible loads for you reference.

Type Power Common equipment Example
Start Rated Equipment Start
Resistive load X 1 X 1

100VA   1 ( W)

|

00VA ( W)

Capacitive load| X 2| X 1.5| Fluorescent lamp| 40W Fluorescent lamp| 80VA ( W)| 60VA ( W)
Inductive load| X 3~5| X 2| | 150W Fridge| 50-750VA (W)| 300VA (W)

6.4 Battery Connection
Charging & discharging system of X1-Hybrid series inverter is designed for high-voltage lithium battery.
Before choosing battery, please note the maximum voltage of battery can not exceed 400V and the rated voltage of battery can not exceed 350V, and the battery communication should be compatible with X1-Hybrid inverter.
Battery breaker
Before connecting to battey, please install a nonpolarized DC breaker to make sure inverter can be securely disconnected during maintanance.

Model| X1-Hybrid-3.0-D
X1-Hybrid-3.0-N| X1-Hybrid-3.7-D
X1-Hybrid-3.7-N| X1-Hybrid-4.6-D
X1-Hybrid-4.6-N| X1-Hybrid-5.0-D
X1-Hybrid-5.0-N
---|---|---|---|---
Voltage| Nominal voltage of DC breaker should be larger than maximum voltage of battery.
Current[A]| 32A

Battery connection diagram

Note: When working with Pylontech batteries, It is recommended the number of battery module (H48050-15S) is 2-7 and the number of battery manager system (SC0500A-100S) is 1.
When working with SOLAX batteries, It is recommended the number of battery module (HV10045/HV10063) is 1-3 and the number of battery controller (MC0500) is 1.
BMS PIN Definition
Communication interface bewteen inverter and battery is RS485 or CAN with a RJ45 connector.

PIN 1 2 3 4 5 6 7 8
Definition N TC GND GND BMS_CANH BMS_CANL X BMS_485A BMS_485B

Note!
The battery communication can only work when the battery BMS is compatible with the inverter.
Power Connection Steps:
Step1. Choose the 9 AWG wire and strip the cable to 15mm.
Step2. Insert the stripped cable up to the stop ( negative cable for DC plug(-) and positive cable for DC socket(+) are live). Hold the housing on the screw connection.
Step3. Press down spring until it clicks audibly into place.(it must be possible to see the fine wire strands in the chamber)
Step4. Tighten the screw connection(tighten torque:2.0Nm)
Step5. Plug the PV conntector into the corresponding PV connector on inverter.

Note: The positive line and negative line are not allowed to access anti- Line
Communication Connection Steps:
Step1. Prepare a communication cable (without sheath) and insert the commu nication cable through the cable connector which can be found in the accessories package .
Step2. Crimp the communication cable with a Rj45 plug which is inside of the cable connector.
Step3. Insert the cable connector into BMS port inside of inverter and screw it tightly. Then insert other side of communication cable into RS485 or Can port on the battery.
Battery BMS module(Pylontech: RS485 port; Triple Power: CAN port; Please check the battery manual for more details).

6.5 Earth Connection (mandatory)
Users must addtionally earth the inverter to the enclosure of a second earthing or equipotential bonding. This prevents electric shock if the original protective conductor fails.
Earth Connection Steps:
Step1. Strip the earthing cable insulation and insert the stripped cable into the ring terminal, then clamp it .
Step2. Place the ring terminal into the earthing rod and screw the earthing screw tightly.

6.6 Meter Connection
Meter is used for monitoring the power usage for entire house, at the meantime,  inverter will also need the data from Meter to achieve the Export Control Function.
Note!
It is necessary to connect meter to inverter otherwise inverter will shutdown with a “Meter fault” alert.
The meter communication only works when meter is compatible with the inverter.
Meter connection diagram

Meter PIN Definition
Communication interface bewteen inverter and meter is RS485 with two wires.

Meter Connection Steps:
Step1. Prepare a connector and two communication wires.
Step2. Unscrew the nut of Meter connector and insert two communication wires through it.
Step3. Trip the insulation from the communication wires, then insert one side of wires into pin1 and pin2 holes of the 8 pin positive terminal which can be found in accessories package. And then screw them tightly.
Step4. Insert the positive terminal into the corresponding negative terminal block inside of the inverter. And then screw it tightly.

6.7 COM Connection
COM communication is the standard communication interface. It can transmit the data between the router and inverter via the local network.
Application Occasion
This function is appliable for the below situation:
When the wifi signal is too weak to transmit data, user can use LAN port for the monitoring with a data cable.
Note: The wifi module still needs to be connected when using LAN connection.

COM PIN Definition
Communication interface bewteen inverter and router is RS485 with a RJ45 connector.

1 2 3 4 5 6 7 8
TX+ TX- RX+ X X RX- X X

Communication Connection Steps:
Step1. Prepare a communication cable (without sheath) and insert the commu nication cable through the cable connector which can be found in the accessories package .
Step2. Crimp the communication cable with a Rj45 plug which is inside of the cable connector.
Step3. Insert the cable connector into COM port inside of inverter and screw it thightly. Then insert other side of communication cable into home router or other device.

6.8 DRM Connection
DRM is provided to support several demand response modes by emitting control signals as below.
Note: Only PIN6(DRM0) is available now, and other PIN functions are being developed.

1 2 3 4 5 6 7 8
DRM1/5 DRM2/6 DRM3/7 DRM4/8 +3.3V DRM0 GND GND

DRM Connection Steps:
Step1. Prepare a standard network cable (without sheath) and a RJ45 plug.
Step2. Insert the network cable through the DRM/Meter port on the bottom of the inverter.
Step3. Crimp the network cable with the RJ45 plug by using a cable clamp.
Step3. Insert the RJ45 plug into the DRM port, and screw the cable nut tightly.

6.9 WiFi Connection(optional)
Inverter provides a WiFi port which can collect data from inverter and transmit it to monitoring-website via a Pocket WiFi. (Purchase the product from supplier if needed)
Diagram

WiFi Connection Steps:
Step1. Plug Pocket Wifi into “WiFi” port at the bottom of the inverter.
Step2. Build the connection between the inverter and router.
Step3. Create a user account online.( Please check the Pocket WiFi user manual for more details.)

6.10 Inverter Manipulation
Start inverter after checking all below steps:

  1. Ensure the inverter fixed well on the wall.
  2. Make sure all the DC wirings and AC wirings are completed.
  3. Make sure the meter is connected well.
  4. Make sure the battery is connected well.
  5. Make sure the external EPS contactor is connected well. (if needed)
  6. Turn on the AC switch and EPS switch
  7. Turn on the PV/DC switch and battery switch.
  8. Press the “Enter” key for five seconds to exit Off Mode.(The mode is factory defaulted as Off Mode)

Check the inverter:
Step1. Check the status of indicators and LCD screen. The left indicator should be blue and the indicator screen should display the main interface.
Note!
If the left indicator is not blue please check below the three points:

  • All the connections are correct.
  • All the external breakers are switched on.
  • The DC switch on the inverter is in the “ON” position.

Step2. There is a setting guide on the LCD screen if it is the first time to start up, pls follow it. For specific setting, please refer to section 8 (Setting).
Step3. Set WiFi according to wifi user manual.
Step4. Operate “Self Test”. (applies to Italy only)
Self-test in accordance with CEI 0-21(applies to Italy only)
The self-test is only required for inverters, which are commissioned in Italy. The Italian standard requires that all inverters feeding into the utility grid are equipped with a self-test function in accordance with CEI 0-21. During the self-test, the inverter will consecutively check the protection reaction times and values for overvoltage, undervoltage, overfrequency and underfrequency.
Selftest function is available at any time, and the test report will show on the LCD display for end-user.
Shut down the inverter :
Step1. Press the “Enter” key for five seconds to enter Off Mode.
Step2. Turn off the AC switch, EPS switch and battery switch.
Step3. Wait 5 min before you open the upper lid.(if in need of repair)

Firmware Upgrading

User can upgrade inverter’s firmware via an U-disk.
Preparation
Please ensure the inverter is steadily powered on.
Inverter must connect PV panels and keep the battery on through whole procedure of upgrading.
Please prepare a PC and an U-disk.
Warning!
Make sure the PV input power is more than 150V (operate the upgrade on a sunny day), otherwise it may result in serious failing during upgrading.
Upgrading Steps:
Step1. Please contact our service support to get the update , and extract it into your U-disk as follow:
“update\ARM\618.00050.00_Hybrid_X1G3_Manager_VX.XX_XX-XX.usb”;
“update\DSP\618.00084.00_Hybrid_X1G3_Master_VX.XX_XXXXXXXX”;
(Vx.xx is version number, xxxxxxxx is
Warning!
Make sure the directory is in accordance with above form strictly!
Do not modify the program file name, or it may cause the inverter not work anymore!
Step2. Press the “Enter” key for 5 seconds to enter Off Mode. Then unscrew the waterproof lid and insert U-disk into the “upgrade” port at the bottom of the inverter.
Step3. The LCD will be shown as picture 3-1. Then press up and down to select the one that you want to upgrade and press “OK” to confirm to upgrade.
Step4. After the upgrade is finished, the LCD will display “succeed”(only for DSP upgrades), please remember to pull off the U-disk, screw the waterproof lid and press the “Esc” to return to the Main interface. Then press the “Enter” key to exit Off Mode.

Warning!
If the upgrading is broken off during operation, please ensure the inverter is steadily powered on and reinsert the U-disk.

Setting

8.1 Control Panel

Object Name Description
A LCD Screen Display the information of the inverter.
B Indicator LED lit in blue: The inverter is in normal status or in EPS

mode. flash in blue: The inverter is in waiting status.
Off: The inverter is in fault status.
C| lit in green: The battery communication is normal. flash in green: The battery is in idle mode.
Off: The communication between inverter and battery is failed
D| lit in red: The inverter is in fault status. Off: The inverter has no errors.
E| Function Button| ESC button: Return from current interface or function.
F| Up button: Move cursor to upside or increase value.
G| Down button: Move cursor to downside or decrease value.
H| OK button: Confirm the selection.

8.2 Menu Structure
*All advance setting can only be set by the technician or the installer with the installer password.

Register1 SN: it indicates the serial number of the external monitoring devices,such as pocket WiFi, pocket LAN and pocket GPRS.
Register2 SN: it indicates the serial number of built -in Ethernet.
8.3 LCD Operation
LCD Digital Display
The main interface is the default interface, the inverter will automatically jump to this interface when the system started up successfully or not operated for a period of time.
The information of the interface is as below. “Power” means the instant output power; “Today” means the power generated within the day. “Battery” means the left capacity of battery energy.

Menu interface
The menu interface is a transfer interface for user to get into another interface to change the setting or getting the information.
-User can get into this interface by pressing “OK” button when LCD displays the main interface.
-User can select interface by moving the cursor with function button,and press “OK” to confirm.

Status

● Status
The status function contains five items of the inverter(grid, solar, charger, eps and Load).
Press up and down to select and press “OK” to confirm the selection, press “ESC” to return to Menu.

a) Grid
This status shows the current grid condition such as voltage, current, output power and the local consumed power.
Pout measures the output of the inverter;
Pgrid measures power export to or import from grid.
Positive value means the energy feeds into grid, negative value means the energy used from the grid.

b) Solar
This status shows the real time PV condition of the system, such as input voltage, current and power situation of each PV input.

C) Charger
This status shows the charger situation of the system. Include the battery voltage, charge or discharge current. Charge or discharge power, battery capacity and battery temperature. “+” means in charging; “-” means in discharging.

d) Charger-setting
If the inverter is plugged with a smart plug, this status shows the real time load power, include load1 power and load 2 power.

e) EPS
EPS will only have data when the inverter is working in EPS mode, it will show the real time data of the EPS output such as voltage, current, power, frequency.

History

● History
The history function contains five items of the information: Inverter yield, charger yield, load consume, feed in energy and error logs.
Press up and down to select ,and press “OK” to confirm the selection, press “ESC” to return to Menu.

a) Inverter Yield
This Inverter Yield contains four items: OutputGridToday, OutputGridTotal, InputGridToday and InputGridTotal.

b) EPS Yeild
The EPS Yield function contains EPS yield for today and total.

c) Meter Yield
The Meter Yield contains four items: FeedInToday, FeedInTotal, ConsumeToday and ConsumeTotal.

d) Error Logs
The Error logs record the lastest six error messages happened.

e) Inv warning
You can see the most recent warning of the inverter here.

Setting

● Setting
This function is used for setting of the inverter time, connection, battery,grid and so on.
Enduser can set Date Time, Language and Ethernet directly.
But for advance setting, it requires installer password to operate most of the professional settings.

a) Date Time
This interface is for user to set the system date and time.

b) Language
This inverter provides several languages for customer to select.

c) Ethernet
There are two modes to obtain IP address: static and DHCP.
User can set the information about ethernet such as IP address, subnet mask number, default gateway number and Mac address.

d) Work mode
For “Force Time Use” mode, there are 8 parameters that needs to be set.

Parameter Comment
Charger start time1 The start time of the iod.
Charger end time1 The end time of the iod.
Charger start time2 The start time of the second charger period.
Charger end time2 The end time of the second charger period.

There are 4 work modes for choice.
All these work modes is available for on-grid condition only:

Parameter Comment
Self Use (default) The PV generated power will be used to supply the local

loads first, then to charge the battery. The redundant power will export to the public grid.
When there is no PV supplied, battery will discharge for local loads first, and grid will supply power when the battery capacity is not enough.
The priority of inverter output power is: supplying the load → charging the battery → feeding to the grid
Back Up Mode| Battery will stop discharging to keep higher capacity when the grid is on. when the power generated by PV is not enough, the battery will discharge to supply the local loads too. And if still not enough, the grid will power the local loads together. This work mode applies to the area where suffering from blackout regularly.
Feed in Priority| The priority of inverter output power is: feeding to the grid → supplying the load → charging the battery.
This work mode applies to the area with high feed-in tariff.
Force Time Use| In this work mode the charging and discharging time can be set flexibly, and it also allows to choose whether charge from the grid or not. Other time it follows the priority of Self Use mode.

e) Advanced
All the advance setting can be set here, such as battery, grid, EPS and so on.
“Advanced” is divided four parts: On-grid, Battery, Reset, User-define. And every part has lower level parts.
Pls contact with your installer or factory for the installer password to enter.

e-1-1) Safety
User can set safety standard according to different countries and grid tied stanndards.There are 8 standards to select. (May change without notice)

Item Standard German
1 VDE 0126 Country
2 ARN 4015 German
3 AS 4777 Australia
4 EN 50549_EU Netherland
5 G98/G99 UK
6 EN 50438_NL Netherland
7 CEI 0-21 Italy
8 IEC61727_In India

e-1-2) Power Factor ( For specific country if required by the local grid.)
There are 5 modes for selecting: Off , Under-Excited, Over-Excited, Curve, Q( u ).

Mode Comment
Off
Under-Excited PF value
Over-Excited PF value
Curve Upper limit

Lower limit
Power Upper
Power Lower
PFLockInPoint ( CEI 0-21 only)
PFLockOutPoint ( CEI 0-21 only)
Q( u )| QuVupRate
( EN50438_NL  only)
QuVlowRate
( EN50438_NL only)

Reactive power control, Reactive standard curve cos φ = f(P)
For VDE ARN 4105, curve cos φ = f(P) should refer to curve A. default value of setting is as shown in curve A.
For E 8001, curve cos φ = f(P) should refer to curve B. default value of setting is as shown in curve B.
For CEI 0-21, default value of PFLockInPoint is 1.05, when Vac > 1.05Vn, and Pac> 0.2 Pn, curve cos φ = f(P) should refer to curve C. Default value of PFLockOutPoint is 1 when Vac < 1 Vn, cos φ = f(P) will exit curve C.

e-1-3) Grid
The enduser do not need to set the grid parameters. All default value has set on factory according to safety rules.
If need to reset, any changes should according to the requirement of local grid.

Parameter Comment

Normally
Vac upper| Voltage high protect
Vac lower| Voltage low protect
Vac upper slow| Voltage high slow protect
Vac lower slow| Voltage low slow protect
Fac upper| Frequency high protect
Fac lower| Frequency low protect
Fac upper slow| Frequency high slow protect
Fac lower slow| Frequency low slow protect
Vac 10m avg| 10 min voltage high protect
Apply to Italy(CEI0-21) only.
Tuvp_Fast| Overvoltage protect fast time
Tovp_Fast| Undervoltage protect fast time
Tufp_Fast| Overfrequency protect fast time
Tofp_Fast| Underfrequency protect fast time
Tuvp_Slow| Overvoltage protect slow time
Tovp_Slow| Undervoltage protect slow time
Tufp_Slow| Overfrequency protect slow time
Tofp_Slow| Underfrequency protect slow time
FreDrpDlyTime| Frequency droop delay time
Apply to EN50438_NL only.
FreqSetPoint| Frequency set point
FreqDropRate| Frequency droop rate
Apply to EN50549_EU only.
OFPL_Start Point| Over frquency power limit start point
T_Start| Chacking time set
UFPL_StartPoint| Under frequency power limit start point
FreqDropRate| Frequency droop rate
UFPL_Stetting| Under frequency power limit switch set
oFPL_Stetting| Over frequency power limit switch set

e-1-4) Export control
This function allows the inverter able to control energy.There are user value and factory value. The factory value is default which can not be changed by user. The user value setting by installer must be less than the factory value.
Choose”Disable” means the function will be shut off.
The meaning of the set number is the max. output power allowed. If the user do not want feed any power into grid, then please set it to 0.

e-1-5) Remote Control
Remote control function allows external control device to make the inverters remote cluster control through LAN port on the inverter. And it can control the inverter’s active power output and reactive power output.
The default value is “enable”. Choose “disable” means the funciton is turn off.

e-1-6) GlblMPPTFunc
GlblMPPTFunc means global Max. power point shadow track function.
When a part of PV panel is covered by a shadow, it might procduct two or more top points(refer to Curve B), and inverter can track the max. power point to improve the inverter yield effectively.
This function applies to the cirumstance when the sun is not steady.
Choose”Enable”means this function is turned on and it is the default value.
Choose”Disable” means the function will be shut off.

e-1-7) )Power Limit
Power limit function is able to set AC port maximum power by percentage.

e-1-8H/LVRT Function
When the grid appears unusual situation in a very short time, this function can make the inverter keeping in a no-power and no-alarm situation in this short time and will make the inverter resume normal work immediately once the grid is normal.
The effctive time is 800ms default, but it will be different according to choose different safety.
Choose “Enable” means this function is turned on and it is the default value.
Choose “Disable” means the function will be shut off.

e-1-9) P(u) Function( applies to NZS4777.2)
P(U) function is Volt-watt response mode which is required by standard NZS4777.2 .and applies to NZS4777.2 only.
The default value is “enable”. Choose “disable” means the funciton is turn off.

e-1-10) DRM Function( applies to NZS4777.2)
DRM function is Demand Response Mode which is required by standard NZS4777.2 .and applies to NZS4777..2 only.
The default value is “enable”. Choose “disable” means the funciton is turn off.

e-1-11)W(Gra) (applies to NZS4777.2)
W(Gra) is Gradient of power rate limit which is required by standard NZS4777.2 and applies to NZS4777.2 only. This function is defined as a percentage of rated power per minute.
The default value is “enable”. Choose “disable” means the function is turned off.

e-1-12)Self Test (applies to CEI 0-21 only)
The self test function allows user to test the following items.”ALL test” , ” Ovp (59.S2) test”,
” Uvp(27.S1) test”, ” Uvp(27.S2) test”, ” Ofp(81>.S1) test”, ” Ufp(81<.S1) test”, ” Ofp(81>.S2) test”, ” Ufp(81<.S2) test”, ” Ovp10(59.S1) test”.
In the self test interface, user can test choose “ALL test” or individual test item.
Please make sure the inverter is grid-tied before testing test.
For all test, it needs about 6 minutes. And it will display”success” then “Pass” on the display.
For individual test item, it needs about several seconds or minutes.
Click test report to obtian all items test result.

e-2-1) Charger
Here the user can set the parameters of charger on this page, the inverter is only compatible with lithium battery. Users can set the charge & discharge parameters and awaken mode.
For the detailed parameters , please refer to below table.

Parameter Comment
Min capacity * The remaining capacity of the battery when inverter is working

in online mode.
Charge Max Current| The charge current can be set for 0-20A.
Discharge Max Current| The discharge current can be set for 0-20A.

NOTE !
Please connverter setting for maximum charge/discharge  current is within the range of  battery rated charge/discharge current.
e-2-2) EPS system ( For E &I Version only)
X1-Hyrbid inverter with E Version and I Version can work on the EPS mode. EPS parameters can be set as below.
“Mute”means you can set the warning of system which has entered EPS mode.
-”No”means there will be a buzzing and it is the default value.
-”Yes”means you choose to shut down the warning function.
Besides ,if the buzzing is sharp, it means EPS output is over loads.“
Frequency “here can be set 50Hz or 60Hz please based on correlative loads.

NOTE!

  • When you want to use the EPS function, the setting of the discharge cut voltage need to be higher than the Battery backup discharge Volt.
  • The Battery backup discharge Volt is the min Voltage of the battery.

e-3-1) Reset Errorlog
User can reset all inverter errorlog record here.

e-3-2) Reset Meter Energy
User can reset the meter energy record here.

e-3-3) Reset Mgr EE
User can reset the inverter manager parameter records here.

e-3-4) Config guide
This interface will trigger the initial setting guide re-play again.

e-3-5) Reset Inv Energy
User can reset the inverter energy record here.

e-3-5) Function Reset
User can restore factory Settings here.

e-4) CT/Meter Setting
X1-Hybrid need to work with an energy meter or a CT to achieve hybrid functions. To choose meter or CT used is according to user’s wishes. If meter is chosen, user also can turn off meter function so that X1-hybrid inverter can work as normal grid-tied inverter without meter connected.
In hybrid system, it can install two meters to monitor both solax inverter and other power device. These two meters need to be set different addresses.
Address 001 and address 002 are default and will be written to meters in factory.
And user do not need to change the address except specific situation.

f-5) New Password
User can set the new password here.

System Switch
●”System Switch” can be chosen from “ON” or “OFF”.
“ON” means the inverter is on working condition and it is inverter default status..
“OFF” means the inverter stop delivering all power, but the LCD remains on.

Register1 SN: it indicates the serial number of the external monitoring devices,such as pocket WiFi, pocket LAN and pocket GPRS.
Register2 SN: it indicates the serial number of built -in Ethernet.
About
● This interface shows information of the inverter including inverter serial number, Register1 serial number, Register2 serial number, inverter type, master DSP1,manager and internal code and so on.

Troubleshooting

9.1 Trouble shooting
This section contains information and procedures for solving possible problems with X1-Hybrid inverters, and provides you with troubleshooting tips to identify and solve most problems that could occur with the X1-Hybrid inverters.
This section will help you narrow down the source of any problems you may encounter. Please read the following troubleshooting steps.
Check warnings or fault messages on System Control Panel or Fault codes on the inverter information panel. If a message is displayed, record it before doing anything further.
Attempt the solution indicated in below table.

Faults Diagnosis and solution
TZ Protect Fault Over current Fault.

• Wait for a while to check if go back to normal status.
• Disconnect PV+ , PV- and battery, reconnect them.
• Or seek help from us, if can not go back to normal state.
Grid Lost Fault| Grid is Lost.
• Please wait for a while and system will reconnect if the utility is back to normal.
• Please check whether the cable connection at AC side is normal or not.
• Or seek help from us.
Grid Volt Fault| Grid Voltage Out of Range
• Please wait for a while and system will reconnect if the utility is back to normal.
• Please check whether the grid voltage is in the normal range.
• Or seek help from us.
Grid Freq Fault| Grid Frequency Out of Range
• System will reconnect if the utility is back to normal.
• Or seek help from us.
PV Volt Fault| PV Voltage Out of Range
• Check the output voltage of the PV panels.
• Or seek for help from us.
Bus Volt Fault| Bus Voltage Out of Normal Range
• Disconnect PV+ , PV- and battery, reconnect them.
• Check if the PV input is within the range of the inverter.
• Or seek help from us, if can not go back to normal state.
Bat Volt Fault| Battery Voltage Fault
• Check if the battery input voltage.is within the normal range
• Or seek help from us.
AC10M Volt Fault| The grid voltage is out of range for the last 10 Minutes.
• The system will back to normal if the grid is back.
• Or seek for help from us.
DCI OCP Fault| DCI over current protection Fault.
• Wait for a while to check if back to normal.
• Or seek for help from us.
DCV OVP Fault| DCV EPS over voltage protection Fault.
• Wait for a while to check if back to normal.
• Or seek for help from us.
SW OCP  Fault| Over current fault detected by software.
• Wait for a while to check if back to normal.
• Turn off the PV, battery and grid , reconnect them.
• Or seek for help from us.
RC OCP Fault| DCI over current protection Fault.
• Please check if the insulation of electric wires are damaged.
• Wait for a while to check if back to normal.
• Or seek for help from us.
Isolation Fault| Isolation Fault
• Please check if the insulation of electric wires are damaged.
• Wait for a while to check if back to normal.
• Or seek for help from us.
Temp Over Fault| Temperature over the limitation
• Check if the envirement temperature is over limitation.
• Or seek help from us.
BatConDir Fault| Battery Reverse Connection Fault
• Check if the positive pole and negtive pole of battery are connected in a contrary way
• Or seek help from us.
Sample Fault| The detection circuit Fault
• Disconnect PV+ , PV- and battery, reconnect them.
• Or seek help from us.
OverLoad Fault| Over Load in EPS Mode.
• Turn off  high power device , press “ESC” to restart the inverter.
• Or seek help from us, if can not go back to normal state.
EPS OCP Fault| Over Current in EPS Mode.
• Make sure the load power is within the EPS power range.
• Check if any nonlinear load is connect on the EPS. Remove this load to check if can recover.
• Or seek help from us, if can not go back to normal state.
Input Cnf Fault| PV Panel connection abnormal
• Check if two MPPTs connect in a parallel mode. Please connect the two MPPTs indepedently.
• Or seek help from us, if can not go back to normal state.
BMS Lost| BMS Communication Lost
• Check if the BMS cable is loose or broken.
• Or seek help from us, if can not go back to normal state.
Inter Com Fault| Internal Communication Fault
• Turn off the PV, battery and grid , reconnect them.
• Or seek help from us, if can not go back to normal state.
Fan Fault| Fan Fault
• Turn off the PV, battery and grid , reconnect them.
• Or seek help from us, if can not go back to normal state.
AC HC T  Fault| AC Current Sensor Fault
• Turn off the PV, battery and grid , reconnect them.
• Or seek help from us, if can not go back to normal state.
Inv EEPROM  Fault| Inverter EEPROM Fault
• Turn off the PV, battery and grid , reconnect them.
• Or seek help from us, if can not go back to normal state.
RCD Fault| Residual Current Device Fault
• Check the impedance of DC input and AC output.
• Disconnect PV+ , PV- and battery, reconnect them.
• Or seek help from us, if can not go back to normal state.
EPS Relay Fault| EPS Relay Fault
• Disconnect PV+ , PV- , grid and battery, reconnect them.
• Or seek help from us, if can not go back to normal state.
Grid Relay Fault| EPS Relay Fault
• Disconnect PV+ , PV- , grid and battery, reconnect them.
• Or seek help from us, if can not go back to normal state.
OtherDevideFault| Other Devide Fault
• Disconnect PV+ , PV- , grid and battery, reconnect them.
• Or seek help from us, if can not go back to normal state.
BMS_External_Err| Battery Fault-extarnal fault
• Please contact battery suppiler.
BMS_Internal_Err| Battery Fault-intarnal fault
• Please contact battery suppiler.
BMS_OverVoltage| Battery Fault-overvoltage fault
• Please contact battery suppiler.
BMS_LowerVoltage| Battery Fault-undervoltage fault
• Please contact battery suppiler.
BMS_ChargeOCP| Battery Fault-charge overcurrent fault
• Please contact battery suppiler.
BMS_DischargeOCP| Battery Fault-discharge overcurrent fault
• Please contact battery suppiler.
BMS_TemHigh| Battery Fault-over-temperature fault
• Please contact battery suppiler.
BMS_TemLow| Battery Fault-under-temperature fault
• Please contact battery suppiler.
BMS_CellImblance| Battery Fault-cell imbalance fault
• Please contact battery suppiler.
Mgr EEPROM Fault| Manager EEPROM Fault.
• Turn off the PV, battery and grid , reconnect them.
• Or seek for help from us if can not back to normal.
Meter Fault| Meter Fault.
• Please check if the meter is in normal working.
• Or seek for help from us if can not back to normal.

  • If your inverter’s information panel is not displaying a Fault light, check the following list to make sure that the present state of the installation allows proper operation of the unit.
    — Is the inverter located in a clean, dry, adequately ventilated place?
    — Have the DC input breakers been opened?
    — Are the cables adequately sized and short enough?
    — Are the input and output connections and wiring in good condition?
    — Are the configurations settings correct for your particular installation?
    — Are the display panel and the communications cable properly connected and undamaged?

Contact SolaX Customer Service for further assistance. Please be prepared to describe details of your system installation and provide model and serial number of the unit.

9.2 Routine maintenance
Inverters do not need any mainteinance or correction in most condition,but if the inverter often loses power due to overheating,this can be the following reason:

  • The cooling fins on the rear of house are coverd by dirts.
    Clean the cooling fins with a soft dry cloth or brush if necessary.
    Only trained and authorized professional personnel who are familiar with the requirements of safety was allowed to perform servicing and maintenance work.

➢ Safety checks
Safety checks should be performed at least every 12 mouths, please contact manufacturer to arrange qualified person who has adequate training,kownledge, and practical experience to perform these tests.(Please kindly noted this action is not covered by  warranty).The data should be recorded in an equipment log.If the device is not functioning properly or fails any of test,the device has to be repaired.For safety check details ,refer to this manual,section 2 Safety instruction and EC Directives.

➢ Maintain Periodically
Only qualified person may perform the following works.
During the process of using the inverter,the manage person shall examine and maintain the machine regularly.The concrete operations are follow.

  1. Check that if the cooling fins on the rear of house are covered by dirts, and the machine should be cleaned and absorbed dust when necessary.This work shall be check time to time.
  2. Check that if the indicators of the inverter are in normal state,check if the keys of the inverter are in normal state,check if the display of the inverter is normal.This check should be performed at least every 6 months.
  3. Check that if the input and output wires are damaged or aged.This check should be performed at least every 6 months.
  4. You should keep the inverter panels clean and their security checked at least every 6 months.

Decommissioning

10.1 Remove the Inverter
Disconnect the inverter from DC Input and AC output.
Wait for 5 minutes for de-energizing.
Disconnect communication and optional connection wirings.
Remove the inverter from the bracket.
Remove the bracket if necessary.

10.2 Packaging
Please pack the inverter with the original packaging.
If the original package is no longer available, you can also use an equivalent carton that meets the following requirements.

  • Suitable for loads more than 30 kg.
  • With handle.
  • Can be fully closed.

10.3 Storage and Transportation
Store the inverter in a dry environment where ambient temperature keep always between -20 °C – +60 °C. Take care of the inverter during the storage and transportation,keep less than 4 cartons in one stack.
When the inverter or other related components need to be disposed. Have it carried out according to local waste handling regulations. Please be sure to deliver wasted inverters and packing materials to certain site, where can assist relevant department to dispose and recycle.

Solax Power Network Technology(Zhe jiang) Co,. Ltd.
No.288 Shizhu Road, Tonglu Economic Development Zone,
Tonglu City, Zhejiang province, China.
Tel: +86 0571-56260011
E-mail:info@solaxpower.com
614.00184.03

Documents / Resources

| SOLAX POWER X1 Hybrid G3 Boost Solar Power Inverter [pdf] User Manual
X1 Hybrid G3 Boost Solar Power Inverter, X1, Hybrid G3 Boost Solar Power Inverter, Boost Solar Power Inverter, Solar Power Inverter, Power Inverter
---|---

References

Read User Manual Online (PDF format)

Read User Manual Online (PDF format)  >>

Download This Manual (PDF format)

Download this manual  >>

SOLAX POWER User Manuals

Related Manuals