Safety Instructions

WARNING – RISK OF FIRE, EXPLOSION, AND ELECTRICAL SHOCK

  • This product shall be installed, inspected, and maintained by a qualified electrician only in accordance with NEC (National Electric Code) and all local codes.

  • Turn off electrical power before inspection, installation, or removal.

  • Use only UL (or other NTRL) approved wire for input/output connections. Minimum size 18 AWG for continuous runs.

  • Ensure LEDs and drivers are cool to touch when performing maintenance and supply voltage is same as rated voltage of luminaire.

  • Do not install in a hazardous atmosphere, except where ambient temperature does not exceed rated operating temperature of fixture.

  •  Keep tightly closed when in operation.

Prepare electrical wiring

Electrical requirements

LED driver must be supplied with 120 to 277 V, 50/60 Hz and connected to an individual, properly grounded branch circuit protected by a 20 Ampere circuit breaker. Use min. 75° C supply.

Grounding instructions

Grounding and bonding of overall system shall be done in accordance with NEC Article 600 and local codes.

Installation

  1. Tools required: Wire strippers, Phillips-head screwdriver, 9/16″ combination wrench.
    Installation

  2. . Before you begin: Ensure power is OFF.
    Unpack fixture and ensure there are no damaged parts. Use supplied cardboard template to set anchor bolts in concrete, ensuring base of concrete is elevated from surrounding area to keep bollard from standing in water. Allow concrete to properly set.
    Installation

  3. Remove three (3) 8-32UNC Phillipshead screws from bollard to remove base assembly. Be sure to disconnect orange disconnect from cable on terminal block.
    Once base has been removed, it can be installed onto anchor bolts previously installed in Step 2. Bolt down base using included nuts and washers.
    Installation

Wiring Diagram

Wiring Diagram

Once secured, attach main connections to terminal block on top of base.
Be sure to connect cables as seen in Wiring Diagram above. Once all connections have been made, replace bollard body onto base and secure with three (3) 8-32UNC Phillips-head screws.

Customer service and technical support

SloanLED Headquarters
5725 Olivas Park Drive, Ventura, CA, USA
888.747.4LED (888.747.4533) • [email protected]
SloanLED.com

P/N 403132 Rev A 2022-11-02

SloanLED Europe b.v.
Argonstraat 110, 2718 SN Zoetermeer, NL
+31 88 12 44 900 • [email protected]

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

Related Manuals