Dil-0496-0001 Tanek
Installation Guide
Tanek Installation
Dil-0496-0001 Tanek
WARNING: Luminaire must be earthed. Risk of electric shock from LED boards if operated with cover removed. Installation / operation outside of luminaires intended scope invalidates warranty. Suitable only for domestic / light industrial / industrial applications within the scope of EN55015. Tested to compliance with BSEN 60598: specification for general requirements and tests. Must be installed by a suitably qualified person in accordance with all relevant legislation. Ambient operating temperature of 0°C to 25°C. If maximum operating temperature is exceeded luminaire will automatically dim / switch off. Terminal blocks are rated to 16A unless stated otherwise. The light source is non replaceable. LUMINAIRES WITH EMERGENCY PACK: When supply is isolated battery output terminals may be live if battery is connected. Isolate mains and battery before servicing. Emergency luminaires require unswitched live connection taken from same phase as switched supply. When unswitched supply is connected status indicator illuminates green, when unswitched supply is disconnected indicator extinguishes and luminaire operates in emergency mode. 24 hour charge period required before undertaking full discharge test. Emergency test sheets provided should be used to record all emergency tests. Batteries should be replaced when 3 hour duration is not met. Excessive switching of permanent live may result in premature battery failure. Battery electrolyte can be harmful to eyes / open wounds, do not puncture, if electrolyte touches skin / eyes flush with water. Do not incinerate batteries.
-
Unpack the luminaire and undo the 10 x M5 6 Lobe Pin Drive screws securing the frame. Remove the frame and proceed to hang it on the tethers.
-
Remove the screw holding the gear tray in place. (1) Push the tray to one side. (2) Lift and tilt the gear tray to remove.
-
Knockout the semi-shear from the housing if bringing the cable in through the side. Cornice Housing – Drill 20mm cable hole in desired location.
Drill the rear of the housing if a central cable entry is required instead. -
Drill suitable fixings to suit required installation.
Please note, it is the contractor’s responsibility to ensure the holes are suitably sealed. Failure to do so will invalidate the luminaire’s IP rating. -
Feed flex through preferred cable entry (contractor tosupply suitable grommet). Make relevant electrical connection (all fittings will have 6 pole terminals due to generic housing to tray connector loom).
-
Connect the tray to the housing using the internal loom.
-
(1) Slide one end of the gear tray into the housing. (2) Then lower the gear tray into place. Secure the tray with the screw that was removed earlier in step 2.
-
Offer the frame up to the housing.
-
Rest the frame on top of the housing. Insert andfasten the 10 x M5 6 Lobe Pin Drive screws.
-
Installation is now complete.
Power
L1| Switched Live
E| Earth
N| Neutral
Emergency
L2| Unswitched Live
DA/AT3| DALI Autotest
DA/AT3| DALI Autotest
Dimming
-/D1/DA| Analogue/DSI/DALI
+/D2/DA| Analogue/DSI/DALI
L3| Switch Dim /
Corridor Function
220-240V / 50-60Hz
IP65
IK10
Terminal Labelling: DIL-0496-0001
Revision – D
14/02/2023
Documents / Resources
|
Dextra Dil-0496-0001
Tanek
[pdf] Installation Guide
Dil-0496-0001 Tanek, Dil-0496-0001, Tanek
---|---
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>