- 1. Inspection upon delivery
- 2. Installation Environment Requirement
- 3. Floor-mounted installation
- 4. Wall-Mounted Installation
- 5. Wire Connection
- 6. Terminal Connection
- 7. Key operation
- 8. Service and contact
- Specifications
- FAQ
- Read User Manual Online (PDF format)
- Download This Manual (PDF format)
GROWATT APX HV Battery
INSTALLATION GUIDE
APX 5.0~30.0P-S1
Shenzhen Growatt New Energy Co.,Ltd.
Environment requirements
Installation tools
Dimensions
1. Inspection upon delivery
1.1 Checking the APX 98020-P1 packing list
Please check that the contentsare complet
1.2 Checking the APX 1-2 5.0P-B1 packing list
1.3 Check accessories
2. Installation Environment Requirement
3. Floor-mounted installation
3-1 Installation Location Requirements
Note: When mounted on the ground,a maximum of six battery modules can be
stacked.
If you are installing more than four modules you are advised to install them
in two columns.
3-2 Installation Procedure
STEP: 1
STEP: 2
STEP: 3
STEP: 4
4. Wall-Mounted Installation
4-1 Installation Location Requirements
Note: When mounted on the wall,a maximum of five battery modules can be
stacked.
Please ensure that the load-bearing capacity of the wall exceeds 280 kg.
34-2 Installation Procedure
STEP: 1
STEP: 2
STEP: 3
STEP: 4
STEP: 5
STEP: 6
5. Wire Connection
5.1 APX 98020-P1 terminal & key description
5.2 APX 5.0P-B1 Connection 5-2 end face introduction
5.3 BATTERY CAPACITY Description
The battery supports power and capacity expansion. A maximum of six battery modules can be connected to a single power module.
5.4 Wiring diagram
Wire Connection Sequesce
Ground Cable → Communication cable → Power cable
Note : It is not recommended to install a DC circuit breaker between the
battery system and the PCS.
If you want to install a DC circuit breaker with rated working voltage greater
than 1000V and rated working current greater than 63A, do not operate the DC
circuit breaker with power-on,otherwise the machine may be damaged.
5.5 Routing Cables Out of the Cable Hole
5.6 Communication Port Connection
6. Terminal Connection
6.1 Power terminal
Note : Please check the diagram carefully and insert the metal terminal to the corresponding connectors referring to the diagram.
6.2 Installing the trim-cover
7. Key operation
Note: 1. Before performing maintenance and repair work, ensure that the AC circuit breaker and the PV switch of the PCS, as well as the switch of the APX are disconnected. Wait for 15 minutes after the sys-tem is powered off and make sure that the LOGO (GROWATT) indicator on the APX is off. Do not perform any operations until the system is completely shut down.
2. When multiple battery systems are used in parallel connection, you only need to press the start key of one module to start the system.
8. Service and contact
Shenzhen Growatt New Energy Co., Ltd.
4-13/F, Building A, Sino-German (Europe) Industrial Park,
Hangcheng Blvd, Bao’an District, Shenzhen, China
T +86 755 2747 1942
E-Mail: service@ginverter.com
w: www.ginverter.com
GR-UM-358-A-01
Specifications
-
Model: APX 5.0~30.0P-S1
-
Manufacturer: Shenzhen Growatt New Energy Co.,Ltd.
-
Environment Requirements:
- Operating Temperature: Max. +50°C, Min. -10°C
- Relative Humidity: +5% to +95%
-
Installation Tools: M6
-
Dimensions:
- APX 98020-P1 (Power Module): 690mm x 295mm x 185mm
- APX 5.0P-B1 (Battery Module): 690mm x 295mm x 185mm
-
-
FAQ
Q: How many battery modules can be stacked when mounted on the ground?
A: A maximum of six battery modules can be stacked on the ground. If installing more than four modules, it is recommended to install them in two columns.
Read User Manual Online (PDF format)