BATO BAP-2856L Built-In Bathtub Installation Guide

June 1, 2024
BATO

INSTALLATION GUIDE
FOR BUILT-IN BATHUB

BATO BAP-2856L Built-In Bathtub

BAP -28 56L

CUPC FILE NO.: 7136
CERTIFIED MODEL: WTM-02856L

ATTENTION

BEFORE STARTING
OUR PRODUCTS ARE CAREFULL Y INSPECTED IN OUR WAREHOUSE AND PACKAGED FOR SHIPPING. ONL Y REM OVE THE PROTECTIVE FILM AT THE VERY END OF THE INSTALLATION TO ENSURE MAXIMUM PROTECTION. (EXCEPT  WHERE BATH SURFACES WILL BE IN PERMANENT CONTACT WITH ANOTHER SURFACE (I.E., FAUCETS, ETC.) IT IS VERY IMPORTANT THAT YOU CAREFULLY INSPECT THE PRODUCT BEFORE INSTALLATION. IF A PRODUCT IS DEFECTIVE, PLEASE CONTACT THE COMPANY BEFORE INSTALLATION. THE INSTALLER WILL BE HELD RESPONSIBLE FOR ANY BREAKAGE OR DAMAGES FOLLOWING THE USE OF A DEFECTIVE PRODUCT. TO PROTECT THE UNIT DURING  INSTALLATION, PLACE A CARDBOARD IN THE BOTTOM OF THE BATHTUB. VERIFY THAT THE BATHROOM FLOOR IS LEVELED AND STRONG ENOUGH TO SUPPORT A MINIMUM WEIGHT OF 1500 LBS. REINFORCE THE EXISTING FLOORING IF NEEDED. THE DRAIN IN YOUR BATHTUB MAY BE TO THE LEFT, THE MIDDLE OR THE RIGHT. VERIFY THE DRAIN LOCATION BEFORE DRILLING A HOLE IN THE FLOOR ACCESS PANEL MUST BE FORESEEN NEAR THE PLUMBING, PUMP AND/OR CONTROL BOXES TO TAKE THEN EASIL Y APART AND/OR REPAIR THESE COMPONENTS. THE WHIRLPOOL/THERAPEUTIC SYSTEMS MUST BE CONNECTED BEFORE THE FINAL INSTALLATION (SEE THE INSTALLATION AND USER’S GUIDE FOR WHIRLPOOL/THERAPEUTIC).

REQUIRED TOOLS

BATO BAP-2856L Built-In Bathtub - TOOLS

IMPORTANT

BATO BAP-2856L Built-In Bathtub - Fig 2

INSTRUCTIONS ARE TO BE PRESERVED BY FINAL USER.
READ CAREFULLY BEFORE PROCEEDING WITH INSTALLATION.
MAKE SURE THAT THE PLUMBING IS DONE BY A CERTIFIED PLUMBER.
MAKE SURE THAT YOU RESPECT THE PLUMBING CODE AND/OR BUILDING CODE OF YOUR REGION.

INSTALLATION INSTRUCTIONS

  • lt is highly recommended to be two people for the installation.

Step: 1. Make sure the studs is straight and square

Step: 2. After carefully verify the drain location , drill the drain hole.

BATO BAP-2856L Built-In Bathtub - Fig 4

Picture for reference only. For actual measure, you need a certified plumber to install it.
Step: 3. If the floor is not fiat or level,it is recommended to put down a mortar bed where the base will be positioned.

BATO BAP-2856L Built-In Bathtub - Fig 5

Step: 4. Make sure ail the legs of the tub are entirely touch the floor.lf not, adjust them or set the level or use a mortar bed for proper installation.

BATO BAP-2856L Built-In Bathtub - Fig 6

Step: 5. Use a level and a bracket to make sure that the bathtub is straight and perpendicular.

NOTE: Put a little bit of water in the bath to make sure that the water flows into the tub and not to the ground.

**** Bathtub bottom must be in contact with a perfectly straight and level surface.

Step: 6. Drill 3/16″ holes at the stud locations on top flanges

**** Gap between flanges and studs must be less than 1 /8″

Step: 7. lnstall the drain onto the tub.

BATO BAP-2856L Built-In Bathtub - Fig 9

Step: 8. Secure the tub with the stud : Place a cardboard or drop cloth inside the tub, stand inside to press it to floor when securing to wall studs. Secure flanges to studs with 1-1/4″ screws.

BATO BAP-2856L Built-In Bathtub - Fig 10

**** Do not overtight screws, as it can crack the flange.

Step: 9. Apply silicon and removed the protection film. After the installation is completed, apply silicon to all outer edges and where the base and the wall meet.

BATO BAP-2856L Built-In Bathtub - Fig 11

**** Apply silicone sealer around all external joints of the bath and leave and allow it to dry for at least 24 hours.

CARE AND CLEANING

For regular cleaning use only mild detergents or warm. soapy water. Use only non-abrasive cloth or sponge.Always rinse surfaces after cleaning.Before cleaning this products with cleaning products, test a small inconspicuous area.

Parts list:

BATO BAP-2856L Built-In Bathtub - Fig 12

Required tools:

BATO BAP-2856L Built-In Bathtub - Fig 13

Installation step

Step 1. Place the tub on the packaging upside down and install the metal supports.

BATO BAP-2856L Built-In Bathtub - Fig 14

Step 2. Use a level to make sure the apron is vertical and level to the the ground.

BATO BAP-2856L Built-In Bathtub - Fig 15

Step 3. Install the metal bars on the wood part of the base using the provided screws and repeat for the 2 remaning bars.

Step 4. Adjust the 5 feets to level the tub.

BATO BAP-2856L Built-In Bathtub - Fig 17

Remarque:
The 3 Metal Supports must be xed with screws to assure that the apron of tub is straight.