BATO BAP-2848L Alcove Bathtub Installation Guide
- June 1, 2024
- BATO
Table of Contents
GUIDE D’INSTALL ATION
BAP -28 4 8L
INSTALLATION GUIDE
ATTENTION
BEFORE STARTING
Our products are carefully inspected and packaged in our warehouse for shipping. Only remove the protec-tive film at the very end of the installation to ensure maximum protection. (Except where bathtub surface will be in permanent contact with another surface (I.E., Wall / faucet, etc)). It is very important that you carefully inspect the product before installation. If a product is defective, please contact the company before installation. The installer will be held responsible for any breakage or damages following the use of a defective product. To protect the unit during installation, place a cardboard in the bottom of the bathtub. Verify that the bathroom floor is leveled and strong enough to support a minimum weight of 1500 Ibs, reinforce the existing flooring if needed. It is IMPORTANT to verify the drain location (it can be place of the left, middle of right) before drilling a hole in the floor. It is important to provide an access near the plumbing, pump and/or control boxes allowing to easily disassemble and/or repair these components. The whirpool/Therapeutic systems must be connected before the final installation. (see the installation and user’s guide for whirpool/therapeutic system).
REQUIRED TOOLS
IMPORTANT
BAP-2848L
INSTRUCTIONS ARE TO BE PRESERVED BY FINAL USER
READ CAREFULLY BEFORE PROCEEDING WITH INSTALLATION.
MAKE SURE THAT THE PLUMBING IS DONE BY A CERTIFIED PLUMBER.
MAKE SURE THAT YOU RESPECT THE PLUMBING CODE AND/OR BUILDING CODE OF YOUR
REGION.
ALCOVE BATHTUB
INSTALLATION INSTRUCTIONS
Important point to remember before beginning installation:
- Verify that floor is structurally sound and level, floor must be able to support the full load of the tub including water to the overflow level.
- Provide access to all plumbing connections.
- Observe all local building and plumbing codes.
Prepare area by framing the area where the tub will be installed.
Place the tub at the location where the tub will be installed, level tub on all sides and mark the location of the drain and the wall studs on the ile flange.
Remove the tub and install the drain, predrill holes on tile flange at the marked location of the studs.
Apply a thin layer (1″ to 2°) of mortar mix cement to the area where your tub basin will be siting.
Move the tub into place, make sure tis level and plumb adjust feet or shim as necessary.
Secure the wall with galvanized screws at the predrilled screw location, apply weight to the middle of the tub until the mortar sets.
Connect the tub drain to your drain system.
Install water resistant gypsum board and finish surface material (tile, stone) and seal all edges with silicone caulking to prevent water damage.
CLEANING
Clean with a damp cloth only.
Avoid using metal or abrasive polishes.
Parts list:
Required tools:
Screwdriver | Level |
---|---|
Installation steps :
Step 1. Place the tub on the packaging upside down and install the metal supports.
Step 2. Use alevel to make sure the apron is vertical and level to the the ground.
Step 3. Install the metal bars on the wood part of the base using the provided screws and repeat for the 2 remaning bars.
Step 4. Adjust the 5 feets to level the tub.
Remarks:
The 3 Metal Supports must be fixed with screws to assure that the apron of tub is straight.
Rev. Mar. 26, 2024