CG1 Gas Fired Unit Heaters

STEPDOWN TRANSFORMER KIT INSTALLATION FOR GAS-FIRED UNIT HEATERS

OPTIONS CG1, CG2, AND CG4 FOR MODELS UDAP, UDAS, UDX, AND UDZ AND UNIT SIZES 030–125 OF MODELS UDBP, UDBS, UBX, AND UBZ
DANGER

  • Improper installation, adjustment, alteration, service, or maintenance can cause property damage, injury, or death.
  • Read the installation, operation, and maintenance instructions thoroughly before installing or servicing this equipment.
  • Installation should be done by a qualified agency in accordance with these instructions and in compliance with all codes and requirements of authorities having jurisdiction.
  • The stepdown transformer steps down the supply power from 208V, 230V, or 460V to 115V for models UDAP, UDAS, UDBP, UDBS, UBX, UBZ, UDX, and UDZ.
  • Refer to the installation manual provided with the unit for important safety information.

KITS AND KIT COMPONENTS

NOTE: The transformer is shipped in its original carton. Other parts are shipped in a separate carton.
Ensure that all of the applicable following components are available before beginning installation.

Table 1. Stepdown Transformer Kits

Option (Voltage)| Model| Unit Size
030| 045| 060, 075| 100| 125| 150, 175| 200| 225, 250| 300, 350,

400

PN
CG1 (208/115)| UDAP, UDAS| 260919| 262851| 262850| 262851| 262850| 260922| 260923
UDX, UDZ| 260920| 260921
UDBP, UDBS, UBX, UBZ| 260924| 260925| 260926| —
CG2 (230/115)| UDAP, UDAS| 197150| 197151| 262852| 262853| 262852| 197153| 197154
UDX, UDZ| 197152
UDBP, UDBS, UBX, UBZ| 202976| 202977| 202978| —
CG4 (460/115)| UDAP, UDAS| 197150| 197151| 262852| 262853| 262852| 197153| 197154
UDX, UDZ| 197152
UDBP, UDBS, UBX, UBZ| 202976| 202977| 202978| —

Table 2. Stepdown Transformer Kit Components

Table 2.  Stepdown Transformer Kit Components

Component| Description| Model| Unit Size
030, 045, 060,
075, 100, 125| 150, 175, 200| 225, 250, 300,
350, 400
PN (Quantity)
Stepdown transformer| Refer to Table 3
Bracket| Transformer| UDAP, UDAS, UDBP, UDBS| 197080
UDX, UDZ| 197079| 197080
UBX, UBZ| 197079| —
Gasket| Transformer bracket| UDAP, UDAS, UDBP, UDBS| 195663
UDX, UDZ, UBX, UBZ| 236155
Quantity is one (1) unless otherwise indicated.

DO NOT DESTROY. PLEASE READ CAREFULLY. KEEP IN A SAFE PLACE FOR FUTURE REFERENCE.

Table 2.  Stepdown Transformer Kit Components—Continued

Component| Description| Model| Unit Size
030, 045, 060,
075, 100, 125| 150, 175, 200| 225, 250, 300,

350, 400

PN (Quantity)
Wiring and conduit| Refer to Table 4
Bushing| Anti-short| All| 16358 (2)
Wire connector| 73B (Ideal #3-0253)| 16354 (10)
Conduit clamp| 1/2 (Heyco #3328)| 16227
Conduit connector| Straight (T&B #253)| UDAP, UDAS, UDX, UDZ| 16199
Straight (T&B #302)| UDBP, UDBS, UBX, UBZ| 16202| —
90-degree (T&B #XC-290)| All| 1417
Capscrew| Hex head, 3/8 × 1| UDAP, UDAS, UDX, UDZ| 32253
Washer| Flat, 3/8| 6593 (2)
Lockwasher| 3/8| 5197
Screw| Sheet metal, #10 × 1/2| All| 11813 (3)
Quantity is one (1) unless otherwise indicated.
Table 3.  Stepdown Transformers

kVA| Option| Model| Unit Size| Transformer PN
0.25| CG1| UDAP, UDAS, UDX, UDZ| 030| 260927
CG2, CG4| 11279
0.50| CG1| UDAP, UDAS| 045, 060, 075, 100, 150, 175| 260928
UDX, UDZ| 045, 060, 075, 100
UDBP, UDBS, UBX, UBZ| 030, 045
CG2, CG4| UDAP, UDAS| 045, 060, 075, 100, 150, 175| 11100
UDX, UDZ| 045, 060, 075, 100
UDBP, UDBS, UBX, UBZ| 030, 045
0.75| CG1| UDAP, UDAS| 125, 200| 260929
UDX, UDZ| 125, 150, 175, 200
CG2, CG4| UDAP, UDAS| 125, 200| 11217
UDX, UDZ| 125, 150, 175, 200
1.00| CG1| UDAP, UDAS, UDX, UDZ| 225, 250| 223462
UDBP, UDBS, UBX, UBZ| 060, 075
CG2, CG4| UDAP, UDAS, UDX, UDZ| 225, 250| 16065
UDBP, UDBS, UBX, UBZ| 060, 075
1.50| CG1| UDAP, UDAS, UDX, UDZ| 300, 350, 400| 260930
CG2, CG4| 197085
2.00| CG1| UDBP, UDBS, UBX, UBZ| 100, 125| 260931
CG2, CG4| 202979
Table 4.  Stepdown Transformer Wiring and Conduit

Component| Length (Inches)| Model| Unit Size| Color
Black| White| Green
PN
Wire, #14AWG,
rated for 105 ° C| 54| UDAP, UDAS, UDX, UDZ| 030| 32520| 201243| 201241
UDBP, UDBS, UBX, UBZ| 030, 045
62| UDAP, UDAS| 045, 060, 075, 100, 125| 7208| 201242| 201240
UDX, UDZ| 045, 060, 075, 100
UDBP, UDBS, UBX, UBZ| 060, 075
65| UDAP, UDAS| 150, 175, 200| 123150| 123152| 201468
UDX, UDZ| 125, 150, 175, 200
UDBP, UDBS, UBX, UBZ| 100, 125
72| UDAP, UDAS, UDX, UDZ| 225, 250| 48862| 48861| 201462
86| 300, 350, 400| 201466| 201467| 201469
Conduit, 3/8-inch| 38| UDAP, UDAS, UDX, UDZ| 030| 45097
UDBP, UDBS, UBX, UBZ| 030, 045
46| UDAP, UDAS| 045, 060, 075, 100, 125| 174394
UDX, UDZ| 045, 060, 075, 100
UDBP, UDBS, UBX, UBZ| 060, 075
49| UDAP, UDAS| 150, 175, 200| 63292
UDX, UDZ| 125, 150, 175, 200
UDBP, UDBS, UBX, UBZ| 100, 125
56| UDAP, UDAS, UDX, UDZ| 225, 250| 10460
70| 300, 350, 400| 201465

INSTALLATION

NOTE: Install the stepdown transformer before or while suspending the heater. The transformer mounts on the side of the heater opposite the access door (left side when facing the front of the heater).

  1. Determine where to install transformer bracket (refer to installation manual provided with unit):
    a. For models UDAP, UDAS, UDX, and UDZ, bracket is installed in unused 3/8-inch suspension hole on top of heater. If two-point suspension is used, locate hole near back of heater. If four-point suspension is used, locate center hole.
    b. For models UDBP, UDBS, UBX, and UBZ, bracket is installed on hanger bar at suspension point and MUST be done as part of suspension process.

  2. On back of transformer bracket flange that will be against heater cabinet, position transformer bracket gasket at bottom of bracket and carefully peel off backing and adhere gasket.

  3. Install transformer bracket at location determined in step 1:
    a. For models UDAP, UDAS, UDX, and UDZ, secure bracket using capscrew, flat washer, and lockwasher (see Figure 1, DETAIL A).
    b. For models UDBP, UDBS, UBX, and UBZ, secure bracket at suspension point using field-supplied hanger rod or optional swivel and field-supplied 3/8-inch hex nuts and lockwashers (see Figure 1, DETAIL B).REZNOR CG1 Gas Fired Unit
Heaters - Figer 1 CAUTION
    The transformer has primary and secondary voltages—note the wire colors and use care when making transformer wiring connections.

  4. Connect transformer wiring:
    a. Run black, white, and green wires through 3/8-inch conduit.
    b. Install anti-short bushing on each end of conduit.
    c. Install straight conduit connector on transformer—either at knockout hole in left side or in bottom. Run black, white, and green wires through connector, connect wires to transformer using wire connectors in accordance with wiring diagram on transformer, and connect straight conduit connector to conduit.
    NOTE: Depending on the transformer, it is secured either to the installed mounting bracket or to a secondary bracket included with the transformer.

  5. Install transformer on transformer bracket and secure using sheet metal screws. If transformer has integral mounting foot, install as shown in Figure 2, DETAIL A. If transformer has slot in back and secondary bracket, slide transformer slot over top of secondary bracket and install as shown in Figure 2, DETAIL B.REZNOR CG1 Gas Fired Unit Heaters - Figer 2

  6. Connect supply wiring to transformer:
    a. Install 90-degree conduit connector at line voltage inlet on rear of heater so that entrance is facing fan or blower.
    b. Run 3/8-inch conduit from transformer to bottom rear of heater and across to 90-degree conduit connector.
    Run black, white, and green wires through connector and connect conduit to connector.
    c. Locate cabinet screw in path of conduit. Remove screw and use it to secure conduit to cabinet using conduit clamp.
    d. Remove heater access panel and connect supply wiring to taps inside transformer in accordance with wiring diagram on transformer label.

  7. Complete heater installation in accordance with installation and venting manuals provided with unit.

Specifications and illustrations subject to change
without notice or incurring obligations.
Latest version of this manual is available at
www.reznorhvac.com.
©2022 Nortek Global HVAC LLC, O’Fallon, MO.
All rights reserved.
OPT-CG1-CG2-CG4
(12-22) 201244-Ahttp://www.reznorhvac.com

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

Reznor User Manuals

Related Manuals