Fronius Eco 25.0-3-S Solar Inverter User Guide
- June 13, 2024
- Fronius
Table of Contents
APPLICATION GUIDE
FRONIUS SNAPINVERTER
SA DYNAMIC EXPORT COMMISSIONING SETUP
Procedure as of 1st
July 2023
Application Guide
© Fronius Australia Pty Ltd.
Version 2.0/2023
Fronius reserves all rights, in particular rights of reproduction,
distribution and translation.
No part of this work may be reproduced in any way without the written consent
of Fronius. It must not be saved, edited, reproduced or distributed using any
electrical or electronic system.
You are hereby reminded that the information published in this document,
despite exercising the greatest of care in its preparation, is subject to
change and that neither the author nor Fronius can accept any legal liability.
Gender-specific wording refers equally to female and male form.
CHANGE LOG
Date | Version | Comments | Author |
---|---|---|---|
2/7/2023 | 1 | First release (Single Inverter sites only) | Fronius Australia |
24/08/2023 | 2 | Revised Solarweb setup and device registration | Fronius |
Australia
SCOPE
This document outlines the necessary commissioning procedure required to set
up the SnapINverter series inverters to operate under a SAPN Dynamic Export
agreement as a part of the SA Smart Homes Scheme. The commissioning steps
outlined in this document are “additional” steps required on top of the
standard inverter commissioning process. Please consult our other
documentation for information on how to perform the standard commissioning
steps.
IMPORTANT: This version 1.0 release of this document is ONLY valid for
“single inverter” and “Inverter inbuilt” communication sites. Multi-Inverter
sites are not yet possible with the “inverter inbuilt / native” solution. For
multi-inverter sites an external 3rd
party devices MUST be used instead. Multi-Inverter functionality will be
released in the coming months once available.
The following Fronius Inverter series are relevant to this document:
- Fronius Primo SnapINverter series
- Fronius Symo SnapINverter series
- Fronius Eco SnapINverter series
For more information on the Dynamic Export Regulations installers are
encouraged to visit the following website:
https://www.energymining.sa.gov.au/industry/modern-energy/solar-batteries-
and-smarter-homes/regulatorychanges-for-smarter-homes/dynamic-export-limits-
requirement
GENERAL INFORMATION & REQUIREMENTS
The SA Dynamic Export control function uses the IEEE 2030.5 based CSIP-AUS
communication protocol to communicate from a Utility Server (SAPN) to the
Fronius Cloud Aggregator. The Utility Server publishes varying “export limits’
which the Fronius Aggregator retrieves and forwards to the relevant inverter
(Client). For identification of the correct inverter, the protocol requires an
LFDI (Long Form Device Identifier) to be created/issued for the inverter to
then be supplied to SAPN.
Compatible inverters are listed on the CEC Approved Inverter list and have an
entry under the column:
“SOFTWARE CLIENT”.
https://www.cleanenergycouncil.org.au/industry/products/inverters/approved-
inverters
All Fronius Australia CEC listed inverters are compliant to the SAPN Dynamic
Export capable requirements.
To complete a compliant install, the system MUST have the following:
- Fronius Smart Meter MUST be installed & commissioned in the system
- Datamanager is loaded with a min. firmware version ≥ 3.27.1-3.
- “Cloud Control” activated on the Datamanager WebUI
- A PV System in Solarweb is active with the assigned inverter
- Selected “Grid Operator” is “SA Power Networks”
- “Only tick to register PV system for Dynamic/Flexible Export sites controlled by Fronius” is ticked.
NOTE: Due to the infancy of this emerging technology, there are steps in this guide that could change over time. The user is therefore advised to always use the latest version posted on the Fronius Australia website.
SYSTEM INSTALLATION & COMMISSIONING
Carry out the installation & commissioning process as per the standard
process, for more information please consult with our online manuals:
Datamanager Commissioning Guide
YouTube: https://www.youtube.com/watch?v=7G_pLLSl4UI
NOTE: After completion the Datamanager MUST be running the firmware
version 3.27.1-3 or greater.
If the firmware is lower than 3.27.1-3, please update the Datamanager via the
WebUI firmware update trigger OR via Solarweb.
ONSITE INVERTER SETUP
5.1 Set pre-commissioning Export Limit
/ Go to “Settings”
NOTE: A “service” password should have already been set when commissioning the Fronius Smart Meter.
- Then go to “DNO Editor”
- Scroll down to “Dynamic power reduction”
- Set “Limit Entire System”
- Enter the size of the PV array in W into the field “total DC power of the system”
- Tick “Export Limiting Control (Soft Limit)”
- Enter any value between 0 – 1000W in the field “Maximum Grid Feed-in Power”
- Then click on the “tick” symbol to save
NOTE: The Pre-Commissioning Export Limit is an additional fallback limit
which the inverter maintains before the Dynamic Export is in place. As soon as
the inverter has communication to the SAPN Utility Server the “local” export
limit will be overridden.
5.2 Activate Cloud Control function
- Scroll down to “Cloud Control” and tick “Allow cloud control for grid/utility compliance purposes”
- Then click on the “tick” symbol to save
IMPORTANT: If the Cloud Control “Allow cloud control for grid/utility compliance purposes” is NOT activated, the inverter will not be able to receive the export limit commands from SAPN.
SOLAR.WEB CLOUD SETUP
6.1 Create system in Solar.web
Create a new system in Solar.web as per the standard process, see how to
here:
https://www.youtube.com/watch?v=umE6-fTwRKA
6.2 Input correct site Address & Installation Date
For tracking of system performance, the correct site address and
installation date of the system is entered
6.3 Select & fill in Grid connection details
Under “Grid operator” choose “SA Power Networks”
Under “NMI – National Metering Identifier” enter site’s 11 x digit NMI number.
Tick the “Only tick to register PV system for Dynamic/Flexible Export sites
controlled by Fronius” box
IMPORTANT: Ticking the “Only tick to register PV system for
Dynamic/Flexible Export sites controlled by Fronius.” box registers the
inverter system with the SAPN Utility server and creates the LFDI in the
backgraound automatically. ONLY tick this box if the system is to be
controlled by the Fronius cloud. i.e. Fronius internal native solution.
DO NOT tick if controlled by Catch Relay, Zeco Marschall. The registration for
these devices MUST be done by them directly.
Also DO NOT tick this box for the SAPN Remote Disconnect functionality.
SAPN DEVICE REGISTRATION CHECK
7.1 Check “Device registration” in Smart Install
Access Smart Install and log in
Complete the required details and information up to “Device registration”
Check the “Device registration” tab for “Your device has been successfully
registered”
7.2 Run “Export Capability Test”
To run the “Export Capability Test” click on the “TEST EXPORT CAPABILITY”
button.
Progress will be shown of each test being performed.
IMPORTANT: the system MUST be exporting at least 500W for the test to
PASS. If the export is below 500W, you will have to perform a test at another
time OR turn loads off to enable the export to exceed 500W.
NOTE: this process can take up to 15mins depending on when the last data upload was executed.
When all GREEN ticks are present the test is finished and PASSED
END OF DOCUMENT
Fronius Australia Technical Support
Email: pv-support-australia@fronius.com
Hotline: +61 3 8340 2910
To access Technical articles, Quick guides, Whitepapers and other technical
documents, please visit the
Tech Support Area for Installers on our website
08/2023