Due to the unusually high pressures and hazardous gasses used in refrigeration and air conditioning, only TRAINED refrigeration and air conditioning technicians should use this equipment. Proper procedures must be used.
Section 608 of the Federal Clean Air Act requires that all persons who maintain, service, repair, or dispose of appliances must be certified since November 14, 1994. Failure to comply can cost you and/or your company as much as $25,000 per day, per violation. The EPA also offers a reward up to $10,000 for providing information concerning violations to the Act.

PROCEDURES

The various service and testing procedures below can be performed after the manifold gauge set has been installed as shown in the following diagrams.

Key:

YELLOW JACKET 500750 TITAN Test and Charging Manifold -
Key

| |
---|---|---
TO PURGE HOSES BEFORE HOOKING UP
1 & 2 Connect hoses at
E & F; Do not tighten
C & D Close valves
4 Connect hose G to refrigerant
A & B Open valves
D & G Crack D & G valve to begin purge
E & F Tighten hose| II. TO OBSERVE OPERATING PRESSURES
A & B C & D 1 & 2
E & F Close valves
Close valves
Connect hoses as illustrated
Crack open back seat
III. TO CHARGE REFRIGERA-
TION SUCTION (VAPOR)
SIDE WITH SCHRADERS
Purge as in I
Charge as in IV| IV. TO CHARGE REFRIGERATION SUCTION (VAPOR) SIDE
Purge as in I
4 Connect hose G to refrigerant A Open valve B & C Close valves D Open valve and throttle
F Crack front seat

V. TO PULL VACUUM
D Close valve
H Connect hose 3 to pump
C Open valve
A&B Open valves
E&F Mid position valves
Note: To improve pull down time, use core removal tool (to minimize restrictions), and use minimum 3/8” or larger hose

VI. TO SET LOW SIDE CONTROL BUILD UP PRESSURE
Disconnect pressure control line. Using flare union, screw union into control line and other end of hose 1.
B, C & D Close valves
A Open valve
E Back seat then crack open
F Back seat F
B Open to regulate pressure; set control

REMOVING THE MANIFOLD FROM THE SYSTEM

After completing service operations, you must remove the manifold from the system without losing refrigerant or admitting air.

  • Close valves E & C.
  • Then open manifold valves A, B and D, 1/2 turn.
  • Close valve F.

This arrangement will move all the high-pressure refrigerant from the line and the high-pressure gauge and put it into the low side. Close all manifold valves and remove hoses.

PARTS LIST

YELLOW JACKET 500750 TITAN Test and Charging Manifold - Figure
7

YELLOW JACKET!® Products Div.
Ritchie Engineering Company, Inc.
10950 Hampshire Avenue South
Bloomington, MN 55438-2623
E.E.U.U.
Telephone: 952-943-1333
Fax: 1-800-322-8684
Fax international : 952-943-1605
Email: custserv@yellowjacket.com
Internet: www.yellowjacket.com
P/N 500750 RevF
America

Read User Manual Online (PDF format)

Read User Manual Online (PDF format)  >>

Download This Manual (PDF format)

Download this manual  >>

YELLOW JACKET User Manuals

Related Manuals