Green Motion chargers
Installation guide: Green Motion ™
Fleet Green Motion ™ Building
Installation Guide
Product introduction
Eaton Green Motion chargers (AC Level 2) deliver fast and cost-effective
charging for passenger vehicles and medium-duty trucks used for last mile
delivery. Combining breakout capabilities for metering, control, integrated
communications and access control with flexible installation options.
Product Family | SKU | Description |
---|---|---|
Green Motion Building | GMEV40CME1B-XXY | 96 kW AC Level 2, 40 A at 240 Vac, Wi- |
Fi, Ethernet
GMEV40CMC1B-XXY| 96 kW AC Level 2, 40 A at 240 Vac, Ethernet, cellular
Green Motion Fleet| GMEV80CME1B-XXY| 192 kW AC Level 2, 80 A at 240 Vac, Wi-
Fi, Ethernet
GMEV80CMC1B-XXY| 192 kW AC Level 2, 80 A at 240 Vac, Ethernet,
Note: Additional SKUs are offered for the above products (example: GMEV40CME1B-WCX) where ‘X’ is the identifier of CPO provider
Package contents
[A] Charger unit with 1” conduit fitting-preinstalled with 36” 3 wires and adapter plate attached 1
- 9.6 kW: L1/L2 – 8 AWG, GND – 10AWG
- 19.2 kW: L1/L2 – 6AWG, GND – 8AWG
[B] Premium cord holster
[C] Twist-resistant anchor
[D] Steel hex head screw
[E] Stainless steel hex head screw
[F] Polaris lug
[G] Custom ethernet adapter
[H] 1/2” trade size flexible conduit
[J] 1/2” trade size 90-degree sweep conduit fitting
[K] O-ring for 1/2” fitting
[L] 1/2” trade size conduit fitting locknut
[M] 1” trade size conduit
[N] 1” Trade Size 90-degree conduit fitting
[P] O-ring for 1” fitting
[R] 1” Trade Size conduit fitting locknut
[S] T25 Torx wrench
Routine operation
State| Color| Blink Type|
---|---|---|---
Idle / Ready| Green| No Blink|
Vehicle connected| Blue| Medium|
Vehicle connected, EVSE ready| Blue| Long|
Vehicle charging state, EVSE not ready (1)| Blue| Short|
Charging| Blue| No Blink|
Fault (2)| Red| Long|
- Not a valid J1772 state. EV charger will commence charging once EV is ready.
- Refer to the troubleshooting section for help on various faults.
Installation
Important safety instructions
DANGER
FAILURE TO FOLLOW THESE INSTRUCTIONS COULD RESULT IN DEATH, PERSONAL INJURY,
OR PROPERTY DAMAGE. CIRCUIT BREAKERS MUST BE INSTALLED AND SERVICED BY A
QUALIFIED ELECTRICIAN. REMOVE ALL POWER SOURCES TO THE PANEL BEFORE STARTING
INSTALLATION OR MAINTENANCE.
WARNING
THIS EQUIPMENT SHOULD BE INSTALLED, ADJUSTED, AND SERVICED BY QUALIFIED
ELECTRICAL PERSONNEL FAMILIAR WITH THE CONSTRUCTION AND OPERATION OF THIS TYPE
OF EQUIPMENT AND THE HAZARDS INVOLVED. FAILURE TO OBSERVE THIS PRECAUTION
COULD RESULT IN DEATH OR SEVERE INJURY.
READ THIS MANUAL THOROUGHLY AND MAKE SURE YOU UNDERSTAND THE PROCEDURES BEFORE
YOU ATTEMPT TO OPERATE THIS EQUIPMENT. THE PURPOSE OF THIS MANUAL IS TO
PROVIDE YOU WITH INFORMATION NECESSARY TO SAFELY OPERATE, MAINTAIN, AND
TROUBLESHOOT THIS EQUIPMENT. KEEP THIS MANUAL FOR FUTURE REFERENCE.
DO NOT USE THIS PRODUCT IF THE EV CONNECTOR CORD IS FRAYED, HAS DAMAGED
INSULATION, OR HAS ANY OTHER INDICATION OF DAMAGE.
DO NOT USE THIS PRODUCT IF THE EV SMART BREAKER CHARGER, THE EV CONNECTOR, OR
THE LOADCENTER IS BROKEN, CRACKED, OPEN, OR SHOWS ANY OTHER INDICATION OF
DAMAGE.
INTENDED FOR USE WITH PLUG-IN ELECTRIC VEHICLES ONLY. PREMISE VENTILATION NOT
REQUIRED.
THIS DEVICE SHOULD BE SUPERVISED WHEN USED AROUND CHILDREN.
**WARNING
TURN OFF OR DISCONNECT THE POWER SUPPLYING THIS EQUIPMENT BEFORE BEGINNING
WORK. THIS MAY REQUIRE THAT YOU CONTACT YOUR ELECTRIC UTILITY TO DISCONNECT
POWER TO AN EXISTING LOADCENTER. THE LINE SIDE OF THE MAIN BREAKER IS
ENERGIZED UNLESS POWER IS DISCONNECTED UPSTREAM.
EATON WILL NOT ASSUME RESPONSIBILITY FOR PROPERTY DAMAGE OR PERSONAL INJURY
RESULTING FROM MISUSE OF THE INFORMATION IN THIS PUBLICATION.
NOTICE INSTALL EQUIPMENT IN CONFORMANCE WITH CODES.
Grounding instructions
WARNING
IMPROPER CONNECTION OF THE EQUIPMENT-GROUNDING CONDUCTOR IS ABLE TO RESULT IN
A RISK OF ELECTRIC SHOCK. CHECK WITH A QUALIFIED ELECTRICIAN OR SERVICEMAN IF
YOU ARE IN DOUBT AS TO WHETHER THE PRODUCT IS PROPERLY GROUNDED.
For a permanently connected product
This product must be connected to a grounded, metal, permanent wiring system,
or an equipment-grounding conductor must be run with the circuit conductors
and connected to the equipment grounding terminal or lead on the product.
This product must be installed in accordance with the National Electrical Code
® (NEC ® ) and any applicable local codes. Before installing equipment, check
with your local electrical inspector for requirements and information. If you
have questions or need assistance, contact a qualified electrical contractor.
SAVE THESE INSTRUCTIONS.
Definitions
EVSE—Electric Vehicle Supply Equipment. EVSE is a general term used for all of
the equipment used to supply electricity to the car.
J1772—SAE Recommended Practice for conductive charging of hybrid and electric
vehicles.
This standard spells out the hysical dimensions of the J1772 connector and
the pilot communication between the plug-in vehicle and the
EVSE. Pilot—The communication signal through the J1772 connector. This signal
tells both the vehicle and the EVSE when both are ready to charge and how much
current is permitted in the circuit. This signal is part of the SAE J1772
standard.
SAE—Society of Automotive Engineers. The group that organizes and leads
committees of transportation experts to create standards, such as J1772, for
the transportation industry.
ADA—Americans with Disabilities Act. UL ®
—Underwriters Laboratories. UL is an accredited standards developer in the
U.S. and Canada.
Moving, transporting, and storage instructions
Store the equipment indoors and in its original packaging until it is ready to
be installed. Storage temperature should be between –40 °C and +70 °C. Never
attempt to lift, move, or carry the equipment by the EV connector cord or
power cord. Improper storage or handling may cause damage to the equipment.
WARNING
ONLY QUALIFIED PERSONNEL FAMILIAR WITH THE OPERATION AND CONSTRUCTION OF THIS
EQUIPMENT SHOULD INSTALL, ADJUST, MODIFY, AND SERVICE THIS EQUIPMENT. FAILURE
TO FOLLOW THE INSTRUCTIONS COULD RESULT IN SEVERE BODILY INJURY OR DEATH.
NOTICE
THE USER IS RESPONSIBLE FOR CONFORMING TO ALL LOCAL AND NATIONAL ELECTRICAL
CODES AND STANDARDS APPLICABLE IN THE JURISDICTION IN WHICH THIS EQUIPMENT IS
INSTALLED.
NEC Article 625 requires that the coupling means of the electric vehicle
supply equipment shall be stored or located at a height of not less than 18
inches (450 mm) and not more than 4 ft (1.2 m) above the floor level for
indoor locations and 24 inches (600 mm)
above the grade level for outdoor locations.
WARNING** – Risk of Explosion. This equipment has arcing or sparking parts
that should not be exposed to flammable vapors. This equipment should be
located at least 18 inches (460 mm) above the floor.
Americans with Disabilities Act requirements to consider for workplace
charging installation
The ADA and workplace charging
The Americans with Disabilities Act (ADA) is a federal civil rights law that
prohibits discrimination in public places against individuals with
disabilities. As an employer installing plug-in electric vehicle (PEV)
charging stations, also known as electric vehicle supply equipment (EVSE), you
need to follow special design guidelines to accommodate people with
disabilities, as required by the ADA. Although the ADA does not provide design
standards for charging stationequipped parking spots, several industry
studies and PEV planning guides do. In addition, several plans developed under
the U.S. Department of Energy’s (DOE) Clean Cities EV Community Readiness
projects describe best practices for installing ADA-compliant charging
stations.
Best practices for designing ADA-compliant PEV charging stations
When designing ADA-compliant PEV charging stations, consider accessibility,
ease of use, and safety for disabled drivers, including those using
wheelchairs or other assistive equipment. Key considerations include ensuring
adequate space for exiting and entering the vehicle, unobstructed access to
the EVSE, free movement around the EVSE and connection point on the vehicle,
as well as clear paths and close proximity to any building entrances.
For information about the ADA, including the revised 2010 ADA regulations,
please visit the Department’s website:
http://www.ada.gov; or, for answers to specific
questions, call the toll-free ADA information line at 800-5140301 (voice) or
800-514-0383 (TTY).
A Prepare the EV charger(s)
STEP A-1
Unscrew the two bolts (1) on the side of the adapter plate and remove the
plate (2). Set the bolts aside for now.
Reference:
- Bolts – x2
- Adapter plate
If a SIM card is not needed, then skip this step and go to:
- Section B if mounting to a wall
- Section C if mounting to a pedestal
STEP A-2
Loosen 13 screws (1) on the rear of the charger [A], and then remove the
front cover (2) Reference:
- Fixed screws – x13
- EV charger front cover
STEP A-3
Insert the SIM card.
STEP A-4
Replace the front cover (1) and tighten the screws. Recommended screw
torque is 1.0 N.m (9.6 lbf.in)
Reference:
- EV charger front cover
Repeat Steps A-1 through A-4 if you plan to install a second charger onto a
pedestal
Section B is instructions for mounting an EV charger to a wall. For mounting
to a pedestal, skip to Section C.
This section details the instructions for various installation options.
Failure to follow these instructions may result in nonfunctional and/or
unprotected equipment
Eaton suggests following the appropriate ADA installation guidelines for
commercial applications
CAUTION: Ensure the EV charger’s dedicated upstream breaker handle is in
the OFF position.
B Mount an EV charger to a wall
STEP B-1
Use the adapter plate (1) as a template, mark the hole pattern on the wall.
Make sure two of the mounting holes are on a stud.
Use the four M6 screws [D] (2) provided to mount the adapter plate.
Reference:
- Adapter plate
- M6 screws [D] – x4
- Anchor [C] – x4
STEP B-2
Hang the EV charger [A] (1) on the adapter plate (2). Using the bolts set
aside earlier (3), secure the EV charger to the adapter plate.
Reference:
- EV charger [A]
- Adapter plate
- Bolts – x2
STEP B-3
A junction box is not included in the package.
Eaton recommends following local code in selecting an appropriate junction
box, suitable for the installation, to complete the line side connections.
Mount the junction box within 20 inches of the EV charger.
STEP B-4
Feed the lineside conductors (1) from the EV charger [A] (2) through a 1”
trade size conduit (not included) (3).
Reference:
- Lineside conductors
- EV charger [A]
- 1” trade size conduit
STEP B-5
Insert the lineside conductors (1) into the junction box (2).
Run conductors (3) from the circuit breaker to the junction box and connect
inside the junction box. Suggest using the Polaris lugs [F] provided in the
kit for wiring inside the junction box. Secure the cover of the junction box
(4).
** Follow local guidelines to secure the cover and knock-out holes of the
junction box.
Reference:**
- Lineside conductors
- Junction box
- Conductors from circuit breakers
- Junction box cover
** Steps B-6 and B-7 are optional: RJ45 (Ethernet) cable wiring
STEP B-6** Optional Remove the cap (1) of the Ethernet port on the EV
charger [A] (2).
Reference:
- Cap
- EV charger [A]
STEP B-7 Optional
Thread the Ethernet cable through the 1/2” trade size flexible conduit [H] (1)
and and the custom Ethernet adapter (2).
Plug the Ethernet cable into the port (3) on the EVcharger [A] (4).
Screw the custom Ethernet adapter [G] (2) to the EV charger [A] (4). Push the
conduit [H] (1) into the custom Ethernet adapter [G] (2).
Reference:
- 1/2” trade size flexible conduit [H]
- Custom Ethernet adapter [G]
- Ethernet port
- EV charger [A]
STEP B-8
Mount the premium cord holster [B] (1) using the steel hex head screws [D]
(2).
Please refer to the ADA website for additional accessibility requirements.
Reference:
- Premium cord holster [B]
- Steel hex head screws [D] – x3
- Anchors [C] – x3
Use anchors [C] (3) for screws not on a stud
STEP B-9
BEFORE ENERGIZING WALL CHARGER, RE-CHECK ALL ELECTRICAL CONNECTIONS AFTER ALL
WIRING HAS BEEN COMPLETED
Reconnect power to the upstream circuit by switching circuit breaker to the ON
position.
Energize the loadcenter or the panelboard. The EV charger electronics should
power immediately, and the LCD will indicate the status of the charger.
Installation is complete. Turn to page 17 to commission the EV charger.
C Mount an EV charger to a pedestal
STEP C-1
Remove the middle rear cover panel (1).
If you have a dual pedestal, remove the hex head screw, neoprene washer, and
locknut (2).
For all pedestals, remove the top (3) and bottom cover panels (4).
Reference:
- Middle rear cover panel
- Hex head screw assembly
- Top rear cover panel
- Bottom rear cover panel
STEP C-2
On the front of the pedestal, remove the four hex head screws, neoprene
washers, and locknuts (1).
Remove NEMA plug (2). Only remove second NEMA plug (3) if you intend to
connect to Ethernet.
Reference:
- Hex head screw assembly – x4
- Front NEMA plug
- Front NEMA plug
STEP C-3
Remove the serrated flange nuts and neoprene washers (1) from the cord hook (2)
that came with the EV pedestal. With that hardware, install the premium cord
holster [B] (3) onto the pedestal using 1/4-20 hex head bolts, washers, and
serrated flange nuts. (4).
Install the adapter plate (5) onto the front of the pedestal (6) using four
1/4-20 hex head bolts, washers, and serrated flange nuts (7).
Reference:
- Serrated flange nuts/washers – x2
- Cord hook
- Premium cord holster [B]
- 1/4-20 hex head bolts, washers, serrated flange nuts – x2
- Adapter plate
- EV pedestal
- 1/4-20 hex head bolts, washers, serrated flange nuts – x4
STEP C-4
Hang the EV charger [A] (1) on the adapter plate (2) and install the two
retention screws (3).
Reference:
- EV charger [A]
- Adapter plate
- Retention screws – x2
STEP C-5
Construct the pedestal mount conduit assembly by pressing the 1” trade size
conduit (3” length) M into the 1-inch trade size 90-degree conduit fitting
[N] (2).
Place an o-ring [P] (3) on the 90-degree fitting [N] (2) Slide the pedestal
mount conduit assembly (4) onto the lineside conductors (5) and up into the EV
charger [A] (6), where it press-fits.
Reference:
- 1” trade size conduit [M]
- 90° conduit fitting [N]
- O-ring [P]
- Conduit assembly
- Lineside conductors
- EV charger [A]
STEP C-6
Feed the lineside conductors (1) through the opening in the pedestal and
through the 1″ conduit locknut [R] (2). Insert the conduit assembly (3) into
the pedestal and connect the locknut [R] (2) to it.
Reference:
- Lineside conductors
- 1” conduit locknut [R]
- Conduit assembly
Steps C-7 through C-9 are optional: RJ45 (Ethernet) cable wiring
STEP C-7 Optional
Place a 1/2” o-ring [K] (1) onto the threaded end of the trade size 90-degree
sweep conduit fitting [J] (2). Remove the Ethernet port cap (3) on the EV
charger [A] (4).
Reference:
- O-ring for 1/2” fitting [K]
- 1/2” trade size 90-degree sweep fitting [J]
- Cap
- EV charger [A]
STEP C-8
Optional
Feed an Ethernet cable (1) through the 1/2” plastic nut [L] (2), and the small
opening in the EV pedestal (3).
Feed the Ethernet cable through the 90-degree sweep conduit fitting [J] (4),
1/2” flexible conduit [H] (5), and custom Ethernet adapter [G] (6). Plug the
Ethernet cable into the port (7) on the EV charger [A].
Screw the custom Ethernet adapter [G] (6) to the EV charger [A].
Push the conduit [J] (5) into the custom Ethernet adapter [G] (6).
Reference:
- Ethernet cable
- 1/2” plastic nut [L]
- Small opening in EV pedestal
- 1/2” trade size 90-degree sweep conduit fitting [J]
- 1/2” trade size flexible conduit [H]
- Custom Ethernet adapter [G]
- Ethernet port
STEP C-9
Optional
Push the conduit [H] (1) into the 1/2” trade size 90-degree sweep conduit
fitting [J] (2)
Feed the conductors and the threads of the 90-degree conduit fitting [J] (2)
through the small cutout on the pedestal (3). Use the plastic nut [L] (4) to
secure the fitting in place.
Reference:
- 1/2” trade size flexible conduit [H]
- 1/2” trade size 90-degree sweep conduit fitting [J]
- Small opening in pedestal
- 1/2” plastic nut [L]
STEP C-10
Cut the L1 and L2 charger conductor to the desired lengths and connect them
with their respective power cables using two Polaris lugs [F] (1).
Reference:
- Polaris lugs [F]
STEP C-11
Install a ring terminal on the EV charger ground conductor and connect it to
the pedestal ground stud (1). Secure the ring terminal to the pedestal ground
stud using a 1/4-20 serrated flange nut.
Reference:
- EV charger ground conductor
If you are installing a second EV charger onto the same EV pedestal, then
skip to Section D.
STEP C-12
Replace the three access panels starting with the top panel.
STEP C-13
BEFORE ENERGIZING WALL CHARGER, RE-CHECK ALL ELECTRICAL CONNECTIONS AFTER ALL
WIRING HAS BEEN COMPLETED
Reconnect power to the upstream circuit by switching circuit breaker to the ON
position
Energize the loadcenter or the panelboard. The EV charger electronics should
power immediately, and the LCD will indicate the status of the charger.
Installation is complete.
Turn to page 17 to commission the EV charger.
D Mount a second EV charger to a pedestal
STEP D-1
Remove the bracket (1) and NEMA plug (2) from theupper access panel (4). Only
remove NEMA plug (3) if you intend to connect the EV charger to Ethernet.
Reference:
- Bracket
- NEMA plug
- NEMA plug (Ethernet)
- Upper access panel
- Adapter plate
- Hex bolts, washers, nuts – x3
Install adapter plate (5) to upper access panel (4) using the top three holes with hex bolts, washers, nuts (6).
STEP D-2
Install the adapter plate/access panel assembly (1) onto the pedestal (2)
using the ten speed screws (3).
Reference:
- Adapter plate
- Pedestal
- Speed screws – x10
- Hex bolts, washers, nut
STEP D-3
**** Repeat Steps C-3 through C-11 to mount the second EV charger.
STEP D-4
Attach the premium cord holster [B] (1) to the middle access cover (2) using
the 1/4-20 hex head bolts, washers, and locknuts (3).
Install the middle access panel (with the premium hook installed) (4) and the
lower access panel (5) to the EV pedestal (6) using speed screws (7).
Reference:
- Premium cord holster [B]
- Middle access panel
- 1/4-20 hex head bolts, 1/4” washers, 1/4-20 locknuts
- Mid-panel assembly
- Lower access panel
- EV pedestal
- #10 speed screws
STEP D-5
BEFORE ENERGIZING WALL CHARGER, RE-CHECK ALL ELECTRICAL CONNECTIONS AFTER ALL
WIRING HAS BEEN COMPLETE
Reconnect power to the upstream circuit by switching circuit breaker to the ON
position
Energize the loadcenter or the panelboard. The EV charger electronics should
power immediately, and the LCD will indicate the status of the charger.
Installation is complete.
Turn to page 17 to commission the EV charger.
FCC
FCC ID
This device complies with part 15 of the FCC rules.
Operation is subject to the following two conditions:
- This device may not cause harmful interference, and
- This device must accept any interference received, including interference that may cause undesired operation.
RF radiation exposure statement
This equipment complies with FCC RF radiation exposure limits set forth for an
uncontrolled environment. This equipment should be installed and operated with
a inimum distance of 20 centimeters between the radiatorand your body.
Canada low-power license exempt radio communication devices (RSS-210)
Common information operation is subject to the following two conditions:
- This device may not cause interference, and
- This device must accept any interference, including interference that may cause undesired operation of the device.
SKU | FCC ID |
---|---|
GMEV40CME1B-XXY | UH2-GMEV40B |
GMEV40CMC1B-XXY | UH2-GMEV40B |
GMEV80CME1B-XXY | UH2-GMEV80B |
GMEV80CMC1B-XXY | UH2-GMEV80B |
Wi-Fi commissioning and operation .
Refer to the product webpage below for detailed instructions on commissioning
the charger using Wi-Fi, Ethernet or cellular and connect to a CPO provider
WIFI module: Contians FCC ID:2AC7Z-ESPWROOM32UE
44G commissioning and operation
4G module: Contians FCC ID: XMR201909EC25AFX
https://www.eaton.com/us/en-us/catalog/emobility/green-motion- fleet.resources.html
Maintenance
Your Green Motion EV charger contains no user serviceable parts. Do not
attempt to repair or service any other part of the unit yourself. If the unit
requires servicing, please contact Eaton customer service. The installation,
maintenance, and servicing of your EV charger must only be performed by
qualified personnel in accordance with applicable local regulations.
Protect your EV charger from any external impact. Take appropriate precautions
with electronic medical implants.
Disconnect the main service power to your charger before cleaning the unit. Do
not use cleaning solvents to clean any part of your charger. Use a clean, dry
cloth to remove accumulated dust and dirt.
Ensure that the EV charging cable is positioned in such a way so that it will
not be stepped on, tripped over, or subjected to damage or stress. Do not
close your garage door on the charging cord. Best practice for EV charging
cable storage when not in use is to wrap the cord around the premium cord hook
and holster provided.
Green Motion Fleet & Green Motion Building
Technical specifications
Description ption| Specification|
---|---|---
number| GMEV80CME1B-XXY| GMEV80CMC1B-XXY| GMEV40CME1B-XXY
GMEV40CMC1B-WCXXY
Electrical input| |
Input power| 19.2kW at 240Vac; 16.6kW at 208Vac| 9.6kW at 240Vac; 8.3kW at
208Vac
Input voltage| 208-240 Vac| 208-240 Vac
Input (amperage) current| 80 A| 40 A
Input OCPD (Breaker) rating| 100 A| 50 A
Electrical output| |
Power output| 19.2kW at 240Vac; 16.6 kW at 208Vac| 9.6kW at 240Vac: 8.3kW at
208Vac
Output voltage| 208/240 Vac| 208/240 Vac
Output amperage| 80 A| 40 A
Connectivity| Wi-fi, Ethernet Cellular, Ethernet| Wi-fi, Ethernet Cellular,
Ethernet
Other specifications|
Connector| SAE J1772
Wiring| Hardwire
RFID| Yes
Overvoltage protection| Yes
Mounting options| Wall and pedestal mount
LED indications| R/G/B LEDs to indicate charger status
Cable length (in feet)| 25
Safety| ETL
Ground fault protection| 20 mA
Overcurrent protection| Yes
Frequency rating| 50/60 Hz
Ambient operating temperature| —30 °C to +50 °C
Storage temperature| —40 °C to +70 °C
Humidity| 0% to 95%, noncondensing
Warranty| 3 years
Enclosure| NEMA-3R rated for outdoor installation
Certifications| ETL, SAE, NFPA, FCC Part 15, Energy Star, OCPP 1.6J
Warranty statement
Warranty for Products. Seller warrants that the Products manufactured by it
will conform to Seller’s applicable specifications and be free from failure
due to defects in workmanship and material for three (3) year from the date of
original purchase. In the event any Product fails to comply with the foregoing
warranty Seller will, at its option, either (a) repair or replace the
defective Product, or defective part or component thereof, with an equivalent
Product or component, F.O.B. Seller’s facility freight prepaid, or (b) credit
Buyer for the purchase price of the Product. All warranty claims shall be made
in writing. Seller requires all non-conforming equipment and material be
returned for evaluation unless specifically stated otherwise in writing by
Seller. This warranty does not cover failure or damage due to storage,
installation, operation, or maintenance not in conformance with Seller’s
recommendations, including as set forth in these Terms and Conditions of Sale,
and industry standard practice or due to accident, misuse, abuse, or
negligence. This warranty does not cover breach of data or system security,
including that of information technology infrastructure, computers, software,
hardware, databases, electronic systems (including database management
systems), and networks. This warranty does not cover reimbursement for labor,
gaining access, removal, installation, temporary power, or any other expenses,
which may be incurred in connection with repair or replacement. This warranty
does not apply to equipment not manufactured
by Seller. Seller limits itself to extending the same warranty it receives
from the third-party supplier, to the extent such third party permits
assignment of its warranty. For all other Terms and Conditions of Sale, please
refer to Eaton’s Selling Policy 25-000.
Troubleshooting
Condkion | TroubleshootingTip |
---|---|
Why is my EV charger not charging my EV? | Check to see if the EV charger is |
powered and the LCD screen is showing the home screen. If not, check if the EV
charger is wired properly and the circuit breaker is closed. If the problem
persists, contact and certified electrician. If the EV charger continues to
show ‘Plug in your vehicle’ screen, then make sure the J1772 connector is
properly plugged into the EV.
If the EV charger is displaying an authentication screen (Scan QR or Swipe
Card to Start), then it is networked charger managed by a CPO. You will need
the CPO subscription and authorization credentials to use this charger.
I see a blinking BLUE LED but my
EV charger and my EV Is not charging.| Blinking BLUE LED indicates that EV
charger is plugged into an EV but either the EV charger or the EV are not
ready to start the charging. Refer to the ‘Routine Operation’ section of the
Instruction Leaflet for more details.
If the EV is not ready, check if its battery is fully charged or if there is a
fault on the EV that is preventing it from initiating a charge.
Why do I see the ‘authorization failed’ message on the EV charger?| If an RFID
is used for authentication, please make sure that RFID card used is issued by
the authorized CPO. Swipe the card over the RFID module properly and make sure
that you hear a beep from the charger.
Note that the authentication screen is timed. If authentication process does
not start within the stipulated time, the EV charger will timeout and
‘authentication failed’ messgae is displayed.
Contact a certified electrician to make sure the RFID module is not
disconnected from the main EV charger electronics
Why Is the LCD screen on my EV charger blank?| Check if the EV charger is
wired properly and the circuit breaker is closed. Restore the EV connector
back to the charger and try to reset the circuit breaker powering the charger.
If the problem still persists, contact and certified electrician.
I see a blinking RED LED on my EV charger. What does this mean and how can I
resume normal operation?| RED LED on the EV charger blinks for various fault
conditions. Some of those conditions are discussed below:
1.Over-voltage fault: RED LED flashes one every 3 seconds.
2.Under-voltage fault: RED LED flashes twice every 3 seconds.
3.Ground Fault: RED LED flashes six times every 3 seconds.
To resolve these conditions, contact a certified electrician to check Voltage
levels feeding the charger. Check for any obvious grounding issues in wiring.
Also check if L1, L2 and GND wires are connected per guidelines.
I unplugged EV connector In the middle of a charge and now the EV charger
Is not charging.| If you were using a networked charger that is controlled by
a CPO, then removing the EV connector in the middle of a charge session will
end that session. A new session needs to be initiated. For a non-networked
charger, a new charging session will automatically start once the EV connector
is plugged back into the EV.
Have trouble connecting the EV charger to the CPO| Refer to the EV charger
product page for instructions on commissioning the EV charger using Wi-Fi,
Ethernet, or cellular and connecting to a CPO provider.
Scan for more troubleshooting tips on various error codes.|
https://www.eaton.com/us/en-us/catalog/emobili|y/green-motion- fleet.resources.html
FCC Statement:
This device complies with part 15 of the FCC Rules. Operation is subject to
the following two conditions: (1) This device may not cause harmful
interference, and (2) this device must accept any interference received,
including interference that may cause undesired operation.
This equipment has been tested and found to comply with the limits for aClass
B digital device, pursuant to part 15 ofthe FCCRules. Theselimits aredesigned
to provide reasonable protection against harmful interference in a residential
installation. This equipmentgenerates,
usesandcanradiateradiofrequencyenergyand,ifnotinstalled andused inaccordance
withthe instructions, may causeharmfulinterferencetoradio
communications.However,there isno guaranteethatinterferencewill notoccur ina
particularinstallation.Ifthisequipmentdoescauseharmfulinterferencetoradioor
television reception, which can be determined by turning the equipment off and
on, the user is encouraged to try to correct the interference by one or more
of the following measures:
—Reorient or relocate the receiving antenna.
—lIncrease the separation between the equipment and receiver.
—Connect the equipment into an outlet on a circuit different from that to
which the receiver is connected.
—Consult the dealer or an experienced radio/TV technician for help.
Caution: Any changes or modifications not expressly approved by the party
responsible for compliance could void the user’s authority to operate the
equipment.
Thisequipment complies withFCC radiation exposure limits setforth for an
uncontrolled environment. This transmitter must not be co-located or operating
in conjunction with any other antenna or transmitter. This equipment should be
installed and operated
with minimum distance 20cm between the radiator&your body.
Eaton
1000 Eaton Boulevard
Cleveland, OH 44122
United States
Eaton.com
Eaton is a registered trademark. © 2023 Eaton
All Rights Reserved Printed in USA
Publication No. IL191012EN (Rev.04) February 2023
All trademarks are property of their respective owners.
Scan here for Spanish translations
Documents / Resources
|
EATON GMEV40CME1B-XXY Green Motion
Charger
[pdf] Instruction Manual
GMEV80CME1B-XXY, GMEV80CMC1B-XXY, GMEV40CME1B-XXY, GMEV40CMC1B-XXY,
GMEV40CME1B-XXY Green Motion Charger, Green Motion Charger, Charger
---|---
References
- Select your location | Eaton
- lbf – Learn by fun
- The Americans with Disabilities Act | ADA.gov
- Select your location | Eaton
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>