Installation Instructions
Installation Notes
Professional installation by a licensed plumber required. Adhere to all local
building and plumbing codes.
Measure the actual tub prior to any construction or installation to ensure
accuracy for rough-in.
Be sure that the floor is structurally sound and able to support the full
weight of a tub with water and an occupant.
Sub floor must be correctly leveled.
Support the bottom of the tub only by the feet or base of the tub.
Do not use the rim as a supporting area.
Ensure that the tub is perfectly levelled for proper draining.
The base area should be set in 1” to 2” of mortar cement.
Access should be given to all plumbing connections.
Verify that the bottom of the apron is at the same height as the floor
covering.
100%Silicone sealant is recommended.
Prior to commencing installation
Remove packaging carefully without damaging and store until installation is
completed.
Inspect all areas of the tub prior to installation– the two year limited
warranty does not cover any visible defects if the tub has been installed.
Contact your retailer within one calendar week after receipt if any defect is
found.
Post-Installation
To clean without scratching use a moist soft cloth and a mild liquid
detergent.
Do not use abrasive cleaners, scraping tools, or any item that could damage or
dull the acrylic surface.
ALCOVE TUB INSTALLATION
Note: If you purchased a trim finish other than Polished Chrome, it must
be installed before installing the bathtub (other trim finishes not available
on all models).
Polished Chrome is included at no additional cost.
Warning: Due to rough handling during shipping or on the job site, do not
install this product until a thorough inspection and water test has been
completed.
Check bathtub for correct model and size. Carefully inspect the tub for any
damage (i.e., chips, scratches, cracks).
If at any point during the pre-installation inspection and water test, you
discover a problem with the bathtub or piping system, DO NOT INSTALL the unit
and contact us immediately.
All pre installed parts must be checked and retightened before installation.
TOOLS and ITEMS REQUIRED
Tape measure| Pencil| Silicone sealant| Electric Drill|
Gloves| Ruler| Spirit Level| Protective Eyewear
---|---|---|---|---|---|---|---
| | | | | | |
PREPARATION
-
Construct a plumb stud pocket. Refer to the specification sheet. (figure 1)
-
Install the rough plumbing. (figure 2)
-
Place the drain into the bathtub. Apply silicone to the drain. (figure 3)
Note: Your tub will be delivered with the overflow installed and drain in its location but not tightened.
Make sure you properly seal and tighten the drain assembly prior to connection and ensure that the silicone has cured.
The overflow drain is integrated into the inner body of the tub so no additional drain or installation is required.
Test drain for leaks prior to Final installation.
Drain, waste locations and trim options vary by model. -
Apply mortar to the floor surface. (figure 4)
-
Lift the tub into position. Make sure to align the drain with the pipe. (figure 5)
-
Level all sides of the bathtub. Apply 100% silicone sealant around the bath along the finished walls and deck. (figure 6)