multiLane V93000 CTH ATE Twinning Frame Site Preparation
productOverview

This document is used to prepare the customer site for the MultiLane High Speed I/O option used with either an Advantest V93000 CTH or STH. The only additional site resource required is the Site Utility Air Supply. All other resources and connections are made between the MultiLane option and the existing V93000 tester cell.

Figure 1: MultiLane System Connection OverviewmultiLane V93000 CTH ATE
Twinning Frame Site Preparation fig 1 Figure 2: MultiLane Utility Box Location (Service Positions taken from Advantest TDC)multiLane V93000 CTH ATE Twinning Frame
Site Preparation fig 2

Air Supply – Site Utility Requirement

MultiLane instruments are air cooled and require in customer site utility air supply

Specification Value Comments
CFM1 3 CFM min, continuous 6 CFM, max, continuous Need continuous CFM while

ML instruments are powered on
PSI| 60 PSI max| 4 bar equivalent
NPT “A” style coupler| Recommended

PUSH-TYPE: Sleeve release

| Feeds air cable from utility air supply to ML Utility Box
Distance from Site Utility Air supply to Utility Box| 3 meters (10 ft) max| Utility Box is assumed to be next to V93000 workstation

Figure 3: Site Air Supply Coupler TypemultiLane V93000 CTH ATE Twinning
Frame Site Preparation fig 3

Smartest Software

The following software must be installed before installing MultiLane Smartest API’s:

Specification Value Comments
RedHat Rev 7.4
V93000 Smartest 7.5 or higher Must be a Smartest “7.x”

version

Site must support fixed IP address assignments| Contact MultiLane for instrument pre-assigned values| For MultiLane instruments

Twinning Frame

Additional information available on the Advantest TDC website:
Twinning guide – Advantest Technical Documentation Center 5.3.0 BETA
A storage area at the customer site is recommended when twinning frame is not in use

Specification Value Comments
Dimensions 0.52 x 1.71 x 1.25 Height (Ft) x Width x Depth
Dimensions 0.16 x 0.52 x 0.38 Height (m) x Width x Depth
Weight 40 kg Doesn’t include customer DIB kg
Storage Container Not Provided Shipping Box only
ESD ESD sensitive devices
Docking personnel Recommend 2 people Docking to CTH or STH

Figure 4: Operator Holding MultiLane Card Cage (also called “Twinning Frame”)multiLane V93000 CTH ATE Twinning Frame Site Preparation fig
4

Ethernet Port

Specification Value Comments
Ethernet Port drop, customer site to V93000 workstation 1 drop Nothing extra

from standard V93000 ethernet drop
Bridge Network, V93000 workstation to MultiLane| 192.168.0.X| Not a site prep requirement.

Shown here for completeness

Figure 5: Ethernet ConnectionsmultiLane V93000 CTH ATE Twinning Frame
Site Preparation fig 5

MultiLane Power Supply – Supplied by V93000

MultiLane power is supplied by the Advantest V93000. It is not supplied directly from the customer site. V93000 power outlets are provided for both the CTH and STH cases. The MultiLane Power supply takes an AC voltage in (see table below) and creates 12 V out for the MultiLane instruments Connecting the mains cable and powering up – Advantest Technical Documentation Center 5.3.0 BETAmultiLane V93000 CTH ATE Twinning Frame Site Preparation fig
6

Figure 6: V93000 STH power switched outlets Figure 7: V93000 CTH power switched outletmultiLane V93000 CTH ATE Twinning Frame Site
Preparation fig 8

MultiLane Utility Box Interconnects

Figure 8: Multi Lane Utility Box Dimensions (mm)multiLane V93000 CTH
ATE Twinning Frame Site Preparation fig 9 Figure 9: MultiLane System Detailed Utility Box InterconnectsmultiLane V93000 CTH ATE Twinning Frame Site Preparation fig
10

Manipulator and Test head Upgrades – Contact Advantest

Consult with Advantest to make sure the manipulator can support the additional twinning frame weight. Consult with Advantest to make sure the onsite V93000 test head has all the upgrades required to hard dock with the MultiLane twinning framemultiLane V93000 CTH ATE Twinning Frame Site Preparation fig
11

Advantest Site Planning Information – Contact Advantest

Additional site planning information can be found in the Advantest CTH and STH site planning documentation. For example,

  • Facility environmental conditions: (Advantest TDC topic 128630)
  • ESD prevention: (Advantest TDC topic 128733)

Notices

Copyright © MultiLane Inc. All rights reserved. Licensed software products are owned by MultiLane Inc. or its suppliers and are protected by United States copyright laws and international treaty provisions.
Use, duplication, or disclosure by the Government is subject to restrictions as set forth in subparagraph (c)(1)(ii) of the Rights in Technical Data and Computer Software clause at DFARS 252.227-7013, or subparagraphs (c)(1) an d (2) of the Commercial Computer Software — Restricted Rights clause at FAR 52.227-19, as applicable.
MultiLane Inc. products are covered by U.S. and foreign patents, issued and pending. Information in this publication supersedes that in all previously published material. Specifications and price change privileges re served.

General Safety Summary
Re view the following safety precautions to avoid injury an d prevent damage to this product or any products connected to it. To avoid potential hazards, use this product only as specified.
Only qualified personnel should perform service procedures.
While using this product, you may need to access other parts of the system. Read the General Safety Summary in other system manuals for warnings and cautions related to operating the system.

To Avoid Fire or Personal Injury
Use Proper Power Cord. Only use the power cord specified for this product and certified for the country of use.
Observe All Terminal Ratings. To avoid fire or shock hazard, observe all ratings and markings on the product. Consult the product manual for further ratings information before making connections to the product.
Do not apply a potential to any terminal, including the common terminal that exceeds the maximum rating of that terminal.
Do Not Operate Without Covers.
Do not operate this product with covers or panels removed.
Avoid Exposed Circuitry. Do not touch exposed connections and components when power is present.
Do Not Operate with Suspected Failures.
If you suspect there is damage to this product, have it inspected by qualified service personnel.
Do Not Operate in Wet/Damp Conditions. Do Not Operate in an Explosive Atmosphere. Keep Product Surfaces Clean and Dry
Caution statements identify conditions or practices that could result in damage to this product or other property.

North America
48521 Warm Springs Blvd.
Suite 310
Fremont, CA 94539, USA
+1 510 573 6388
Worlwide
Houmal Technology Park
Askarieh Main Road
Houmal, Lebanon
+961 81 794 455
Asia
14F-5/ Rm.5, 14F., No 295
Sec.2, Guangfu Rd. East Dist.,
Hsinchu City 300, Taiwan (R.O.C)
+886 3 5744 591
UAE
Building 4WA, Office 420
Dubai Airport Freezone Authority,
UAE
Dubai,
+9714 5487 547

Read User Manual Online (PDF format)

Read User Manual Online (PDF format)  >>

Download This Manual (PDF format)

Download this manual  >>

Related Manuals