RICE LAKE WEIGHING SYSTEMS iDimension LTL Mounting Frame System Installation Guide

August 2, 2024
RICE LAKE WEIGHING SYSTEMS

iDimension LTL Mounting Frame System

“`html

Specifications:

  • Product Name: iDimension 80/20 Mounting Frame System

  • Compatibility: iDimension LTL, iDimension LTL-XL, iDimension
    Flex systems

  • Installation: Suspended from a steel roof structure

Product Usage Instructions:

1. Introduction

The iDimension 80/20 Mounting Frame System is designed to be
attached to a steel roof structure. Follow the steps below for
proper installation:

1.1 80/20 Mounting Frame Preparation

  1. Determine the mounting surface and frame configuration.
  2. Calculate dimensions and cut the required 80/20 bars for the
    frame.

1.4 Roll-in T-nut

Follow these steps to insert the T-nut into the 80/20
channel:

  1. Insert the T-nut into the 80/20 channel at an angle.

  2. Rotate the nut into the channel.

  3. Seat the T-nut into the channel.

  4. Fasten the screw into the T-nut to secure the accessory to the
    bar.

  5. Apply medium strength thread locking compound and tighten
    screws to 6 ft-lb (8.1301 Nm).

2. Configurations

The iDimension 80/20 Mounting Frame can be attached to either a
primary I-beam rafter or secondary Z-channel roof purlins. See
Figure 2 for configuration options.

3. Calculate Frame Dimensions

The dimensions of vertical and horizontal 80/20 bars may vary.
Refer to Table 1 for specific distances for each iDimension
model.

3.1 I-Beam Rafter Configuration Dimensions

For I-beam rafter configuration, use Figure 4 and Figure 5 for
cut length calculations and vertical 80/20 bar dimensions.

3.2 Z-Channel Roof Perlin Configuration Dimensions

Z-Channel roof perlin configuration is compatible with 80/20
bars spanning between at least two Z-channel roof perlins. Refer to
Figure 6 for more details.

FAQ:

Q: Can the iDimension 80/20 Mounting Frame be used with any

other systems?

A: The frame is specifically designed for use with iDimension
LTL, iDimension LTL-XL, and iDimension Flex systems. Consult with
Rice Lake Weighing Systems for more information on compatibility
with other systems.

“`

iDimension® LTL/LTL-XL/Flex
80/20 Mounting Frame Installation
The iDimension 80/20 Mounting Frame System is designed to be suspended from a steel roof structure. iDimension LTL, iDimension LTL-XL and iDimension Flex systems can be attached to the iDimension 80/20 Mounting Frame. Consult with Rice Lake Weighing Systems for more information.
1.0 Introduction
The iDimension 80/20 mounting frame can be installed directly onto the roof structure in pieces or it can be assembled on the ground and attached to the roof structure. Start all installations by completing steps in Section 1.1. If installing the mounting frame directly onto the structure of the roof follow the steps in Section 1.2. If assembling the mounting frame at floor level and attaching it to the roof structure, follow the steps in Section 1.3. See Section 12.0 on page 12 for a parts list.
1.1 80/20 Mounting Frame Preparation Use the following steps to ensure that the frame is ready to assemble and install:
1. Determine mounting surface and frame configuration (Section 2.0 on page 2). 2. Calculate dimensions and cut 80/20 bars needed for the frame:
· Primary I-beam rafter configuration (Section 3.1 on page 4) · Secondary Z-channel roof perlin configuration (Section 3.2 on page 5) 3. Cap 80/20 ends and form arm assemblies (Section 4.0 on page 7).
1.2 Direct Roof Assembly 1. Attach spans to structure: · Primary I-beam rafter configuration (Section 5.1 on page 7) · Secondary Z-channel roof perlin configuration (Section 5.2 on page 8) 2. Install vertical arms (Section 6.0 on page 8). 3. Install lower horizontal bars (Section 7.0 on page 9). 4. Attach iDimension assembly to mounting frame (Section 8.0 on page 9).
1.3 Floor Assembly 1. Assemble and square the frame (Section 9.0 on page 10). 2. Attach spans to structure: · Primary I-beam rafter configuration (Section 5.1 on page 7) · Secondary Z-channel roof perlin configuration (Section 5.2 on page 8) 3. Attach frames to roof structure (Section 10.0 on page 11). 4. Attach iDimension assembly to mounting frame (Section 8.0 on page 9).

July 22, 2024

PN 221406 Rev B

iDimension 80/20 Mounting Frame Installation

1.4 Roll-in T-nut Roll-in T-nuts are used to screw accessories into the bar. They can be inserted by sliding them in from the end of the 80/20 bar or they can be inserted into the channel of the 80/20 bar.
1. Insert the T-nut into 80/20 channel at an angle.
2. Rotate nut into the 80/20 channel.
3. Seat T-nut into channel.
4. Fasten screw into T-nut to secure accessory to the bar.
5. Apply medium strength thread locking compound and tighten screws to 6 ft- lb (8.1301 Nm).

NOTE: Over-tightening the screw may cause the screw to strip out of the T-nut. If screw spins freely, replace the T-nut

1

2

3

4

Figure 1. Roll-in T-Nuts
2.0 Configurations
The iDimension 80/20 Mounting Frame is attached either to a primary I-beam rafter or the secondary Z-channel roof purlins.
Secondary Z-Channel Roof Perlins

Primary I-Beam Roof Rafter
Primary I-Beam Rafter Configuration

Secondary Z-Channel Roof Perlin Configuration

Figure 2. Mounting Frame Configuration Options

2

Visit our website www.RiceLake.com

iDimension 80/20 Mounting Frame Installation
3.0 Calculate Frame Dimensions
The dimensions of the frame’s horizontal 80/20 span bars depend on the structure they are secured to. The dimensions of the frame’s hanging vertical 80/20 bars depend on the height of the structure. The distance from the frame’s lower horizontal 80/20 bars to the floor depends on the iDimension model. (Table 1) The final height of the iDimension sensors must be 132 in ± 1 in (3.352 m) from the floor. The following sections show how to calculate dimensions.

Vertical 80/20 Bars Vary

Hoizontal 80/20 Span Bars Vary

Distance from lower horizontal 80/20 mounting frame See Table 1

Distance from Sensors to floor must be 132 in ± 1 in (3.352 m)

Figure 3. Attach iDimension to Frame

Model

Distance

iDimension LTL iDimension LTL-XL iDimension Flex

142 in (3.607 m) 142 in (3.607 m) 139 in (3.531 m)

Table 1. Distance From Mounting Frame to Floor

© Rice Lake Weighing Systems All Rights Reserved

3

iDimension 80/20 Mounting Frame Installation
3.1 I-Beam Rafter Configuration Dimensions The I-beam rafter configuration is supported by 80/20 bars that are attached to the bottom flange of a roof structural I-beam.

35.5 in (.901 m)

35(..590in1 m)

(15.219.050min)

Top View
H1 LL31

51.00 in (1.295 m)

Center I-Beam on Frame

(.93051.5min)

See Figure 5

(15.219.050min) Figure 4. I-Beam Rafter Configuration 80/20 Bar Cut Length Calculations

L1
H1
F1 Distance from bottom of mounting frame to floor

Calculate length for each vertical 80/20 (L1) bar from height of structural I-beam.
L1 = H1 – F1 – 5 in (.127 m)
· H1 = Distance from floor to base flange of structural I-beam
· F1 = Distance from bottom of mounting frame to floor. See Table 1 on page 3.
NOTE: Distance from Sensors to floor must be 132 in ± 1 in (3.352 m)

Measure To Floor
Figure 5. Vertical 80/20 Bar Dimensions

4

Visit our website www.RiceLake.com

iDimension 80/20 Mounting Frame Installation

3.2 Z-Channel Roof Perlin Configuration Dimensions The Z-channel roof perlin configuration is compatible with 80/20 bars that span between at least two Z-channel roof perlins.

Z-Channel Perlins

Varies See Figure 9 on page 6

35.5 in (.901 m)

Top View Figure 6. Z-Channel Roof Perlin Configuration Top View

Z-Channel Perlins

35(..590in1 m)

L3 W1

80/20 Span Bar

(.93051.5min)

See Figure 8 on page 6

(15.219.050min) Figure 7. Z-Channel Perlin Configuration 80/20 Bar Cut Lengths

© Rice Lake Weighing Systems All Rights Reserved

5

iDimension 80/20 Mounting Frame Installation
Z-Channel Perlin Configuration Vertical 80/20 Bar Length Calculate length for each vertical 80/20 bar (L2) from the height of the top of the 80/20 span at the hanging point. L2 = H2 – F2 – 5 in (.127 m)
· H2 = Distance from floor to the top of the 80/20 span at the hanging point. · F2 = Distance from bottom of mounting frame to floor. See Table 1 on page 3.

H LL4

L
Distance from bottom of mounting frame to floor
H F
Distance from Sensors to floor must be 132 in ± 1 in (3.352 m)

Measure To Floor

Figure 8. Vertical 80/20 Bar Dimensions

Z-Channel Perlin Configuration 80/20 Span Bar Length Calculate length of each horizontal 80/20 bar (L3) that spans from Z-channel to Z-channel. L3 = W1 + 6 in (152.4 mm)
· W1 = Distance between Z-channel as shown

Z-Channel Perlins

WW21

C

Flange Clamp

80/20 Span Bar

LL 32
Figure 9. Z-Channel Perlin Configuration 80/20 Span Bar Length

6

Visit our website www.RiceLake.com

iDimension 80/20 Mounting Frame Installation
4.0 80/20 Arm Assemblies
Form arm assemblies with hangers and end caps before attaching to spans and systems. All 80/20 bars must have an end cap attached. Apply meduim strength thread locking compound and tighten screws to 6 ft-lb (8.1301 Nm).
End Cap
Upper Hanger

Figure 10. End Caps and Upper Arm Assemblies
5.0 Attach 80/20 Span to Structure
5.1 I-Beam Flange Clamp 80/20 Installation Install two upper spans onto the bottom flange of the I-beam using four flange clamps.
1. Loosely screw flange clamps onto the 80/20 span and slide flange clamps into contact with flange of beam. 2. Apply medium strength thread locking compound and tighten all four screws to 6 ft-lb (8.1301 Nm). 3. Tighten set screw to 25 ft-lb (33.9 Nm). 4. Tighten jam nut.

Upper Spans

I-Beam Rafter

1. Flange of Beam

80/20 Span Flange Clamps

Side View
80/20 Span Below

2. I-Beam Rafter Figure 11. I-Beam Flange Clamp

Top View

© Rice Lake Weighing Systems All Rights Reserved

7

iDimension 80/20 Mounting Frame Installation

5.2 Z-Channel Flange Clamp 80/20 Span Installation Install two upper spans onto the bottom flange of the Z-channels using four flange clamps.

1. Loosely screw flange clamps onto the 80/20 span and slide clamps into contact with bottom flange of the Z-channel.

2. Apply medium strength thread locking compound and tighten all four screws to 6 ft-lb (8.1301 Nm).

3. Tighten set screw to 25 ft-lb (33.9 Nm).

4. Tighten jam nut.

Upper Spans

Z-Channel

80/20 Span Flange Clamps

Side View

2. Z-Channel

Top View

Figure 12. Z-Channel Flange Clamp
6.0 Install Vertical Arms
Install vertical arms by four upper hangers into the upper span 35.5 in (.901 m) apart. Tighten top screw to 6 ft-lb (8.1301 Nm).

Upper Hangers

(.93051.5min)

Tighten Screws

Vertical Arms Figure 13. Install Vertical Arms

8

Visit our website www.RiceLake.com

Upper Hanger

iDimension 80/20 Mounting Frame Installation

7.0 Install Lower Horizontal Bars
Install two lower horizontal spans onto the bottom of the vertical arms 35.5 in (.901 m) apart. Tighten screws to 6 ft-lb (8.1301 Nm).
Upper Spans

Tighten Screws

(.93051.5min)
Lower Horizontal Spans
Figure 14. Install Lower Horizontal Bars
8.0 Attach iDimension Assembly to Mounting Frame
Attach arms of the iDimension assembly to mounting frame with four U-bolts. Tighten nuts to secure.

Lower Hanger

U-Bolts

Figure 15. Attach iDimension to Frame

© Rice Lake Weighing Systems All Rights Reserved

9

iDimension 80/20 Mounting Frame Installation
9.0 Assemble and Square the Frame
To assemble and square frame: 1. Lay the legs of the frame on the ground 35.5 in (.901 m) apart. 2. Connect bottom span to the legs of the frame. 3. Tighten Screw 1 on the two lower hangers so that the location is fixed, but the leg can still rotate around the point. 4. Loosely attach screw 2 to the lower hangers of the 80/20 frame. 5. Square the legs of the frame to the bottom span of the frame. 6. Tighten screws to 6 ft-lb (8.1301 Nm). 7. Flip the frame over and tighten screws on the opposite side of the frame to 6 ft-lb (8.1301 Nm). 8. Repeat to assemble two u shaped frames.

Vertical Legs Square Frame

(.93051.5min)

Screw 2 Screw 1

Hanger

Bottom Span Figure 16. Assemble and Square Frame

10

Visit our website www.RiceLake.com

iDimension 80/20 Mounting Frame Installation
10.0 Attach Frames to Roof Structure
1. Attach two top 80/20 spans of frame to roof structure 35.5 in (.901 m) apart. · Refer to Section 5.1 on page 7 for I-beam installation. Refer to Section 5.2 on page 8 for Z-channel installation.
2. Lift assembled frames to fit the upper hangers into the channels of the top spans 3. Tighten screws to 6 ft-lb (8.1301 Nm).
Top Spans
35(..590in1 m)

Angle Varies
Figure 17. Assemble and Square Frame NOTE: Angle of the legs to the top span varies with slope of the roof structure.
11.0 Adjust Height
Adjust bottom span height to accomodate iDimension Product. See Table 1 on page 3 for more information.
Loosen screws to adjust bottom span height
Bottom span height

Figure 18. Adjust Bottom Span Height

© Rice Lake Weighing Systems All Rights Reserved

11

iDimension 80/20 Mounting Frame Installation
12.0 Parts List

9
Flange Clamp Configuration Varies
7 8
1 6 1

45

3

2

6

Figure 19. Mounting Frame Parts

12

Visit our website www.RiceLake.com

iDimension 80/20 Mounting Frame Installation

2.00 in

1

(50.8 mm)

2.00 in (50.8 mm)

80/20 Bar (PN188308)

3.50 in

188310 (88.9 mm)

9

2.00 in (50.8 mm)

188331

1.50 in (38.1 mm)

14649
7

6

9
.38
1.90 in (48.26 mm)

188316

7.00 in (177.8 mm)

2.00 in (50.8 mm)

1.00 in (25.4 mm)
Flange Clamp (PN 188363)

1.90 in (48.26 mm)

0.11 in (2.79 mm)

End Cap (PN 189488)

Upper Hanger (PN 188366)

Figure 20. Mounting Frame Parts

No. Part

Description

Qty

1 188308 80/20 Extrusion, 2 X 2 X 12 ft Nominal Length Slotted Aluminum Black

Varies

2 209480 U-Bolt, 3/8-16 Thread 3 in X 6 5/8 in High Square

4

3 209481 Plate, U-Bolt Mounting for 3/8-16 X 3 in Wide Hole Spacing

4

4 21938 Washer, Plain 3/8 Type A Series N Steel Zinc Plated; ID = .401-.421; OD = .805-.827 Thickness = .051-.080 8

5 22072 Nut, Nyloc 3/8-16 UNC Steel Zinc Plated

8

6 188366 Upper Mount Assembly

16

7 189488 End Cap

16

8 189496 Screw, 1/4 – 14 x 3/4 TEKS Hex Washer Head Steel Climaseal Finish #3 Point

64

9 188363 Flange Clamp Assembly

4

Table 2. Mounting Frame Parts List

© Rice Lake Weighing Systems All Rights Reserved

13

© Rice Lake Weighing Systems Content subject to change without notice.

230 W. Coleman St. · Rice Lake, WI 54868 · USA USA: 800-472-6703 · International: +1-715-234-9171

July 22, 2024

www.ricelake.com

PN 221406 Rev B

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

RICE LAKE WEIGHING SYSTEMS User Manuals

Related Manuals