Technical specifications

1.1 Overview
These instructions are for installation of MUTO COMFORT sliding door system L80 with Sidelites for Wood Doors for the following mounting and style versions:

  1. Ceiling mount
    1.1.1 General information
    • dormakaba requires use of tempered monolithic or tempered laminated glass.
    • dormakaba glass hardware is not suitable for application in rooms where chemicals (e.g. chlorine) are used as indoor swimming pools, saunas or salt- water pools.
    • Never move sliding panels faster than walking speed and always stop the door manually before it reaches end position.
    • Do not slide doors with excessive force. Install limiting stop to prevent door from opening too far.
    1.1.2 Intended use
    • For sliding door in dry indoor areas only
    • For manual slowly opening and closing only
    1.1.3 Glass requirements and fittings
    • The substructure/wall must be able to bear  permanent loads and be level (max. tolerance:
    1/16” [2] per 39” [1m]).
    • Fasteners must be sufficiently dimensioned for the substructure/wall and weight of the door.
    • When adjusting glass components, always stick to the required clearance for the respective hardware. Adjust clearance so glass does not come in contact with any hard surfaces such as glass, metal or concrete.
    • Do not use excessive force when installing the glass (avoid over tightening screws).
    1.1.4 Requirements for glass panel
    • dormakaba requires use of fully tempered glass, which complies with ASTM C 1036 and ASTM C 1048. Secondary heat soaking processes are recommended but not required. This applies to both tempered monolithic and tempered laminated glass.
    • Clamping area must be flat and uncoated (no self-cleaning coating!)
    • Never use glass with conchoidal fractures and/or damaged edges.
    1.1.5 Safety instructions
    • Installation requires two people.
    • Only properly qualified and specially trained staff are authorized to mount dormakaba glass hardware.
    • Due to crushing hazards and possible injury caused by breakage of glass during mounting, corresponding protective clothing (especially gloves and protective goggles) is required.
    • Never clamp metal fitting hardware directly to glass surface.

1.1.6 Symbols used – Safety/Installation
CAUTION
Mounting components must meet the  requirements of substructure/wall and door weight. Please read the technical information for fittings.
WARNING
Risk of breaking glass. When installing the door, support the door panel with a block of wood or similar object.
TIPS AND RECOMMENDATIONS
Information note
CLOSING EDGE
1.1.7 Maintenance, care, repair

  • Immediately replace damaged parts.
  • Always use original dormakaba parts.
  • Clean clamping area with alcohol-based standard commercial cleaning agent before mounting the glass hardware.
  • Use a damp clothe for occasional cleaning, especially the track.
  • Always use silicone – and oil-free cleaners (e.g. acetone).
  • Check glass hardware at regular intervals for proper positioning and smooth operation and correct adjustment.
  • High traffic door systems require inspection by properly qualified staff (specialized companies or installation firms.)

1.1.8 Disposal
Disposal in accordance with local, state and national regulations.
1.2 Specifications – technical data

| Single Door| Double Door
---|---|---
| L80| L80
Ceiling mount| Door leaf weight lbs [kg] *| 2 x ≤176lbs [2 x ≤80]

  • Including weight of auxiliary hardware.

Installation instructions

2.1 Overalldormakaba L80 Muto Comfort Ceiling Mount -
Overall 1.3 Track
1.4 Cover end c ap
1.1 Cover panel
1.2 Brush strip
1.5 Sidelite profile end c ap
1.8 End st op
1.9 Cover clips
1.6 F iller profile
1.7 Sidelite profile
1.10 Start / stop guide
1.13 F loor guide
1.14 U-channel
1.11 Roller carrier
1.12 Dormotion units
1.17 View protection clip
1.18 W ood door adaptor
1.15 Sidelite glass gasket
1.16 View protection profile
2.2 Door/wall dimentionsdormakaba L80 Muto Comfort Ceiling Mount - wall
dimentions NOTE:
Overhead Reinforcement:
The overhead reinforcement must be a minimum of ¼” [6] x 3” [76] steel angle, 16 gauge metal stud, or two pieces of 1 1/2” [38] thick wood blocking (double stacked), secured to studs or joists on a maximum 16” [406] centers for the length of the track. The overhead reinforcement may be flush on the overhead surface or on the interior of this surface.
Track mounting screws must fully penetrate the steel angle, metal stud, or at a minimum of 2” [51] into wood blocking, utilizing the predrilled holes in the MUTO track.
Consult with a structural engineer to determine if reinforcement is adequate for your specific application or to meet specific codes in your location.
2.3 Installing the end stopsdormakaba L80 Muto Comfort Ceiling Mount -
Installing the end stops 2.3.1 Slide bumper stops into each end of the trackNOTE: Loosen bottom section of end stop for easier install.
NOTE: Be sure set screw is flush with back of bumper.
NOTE: Exact location/adjustments will be determined in the Adjustment End Stop Location step.
2.4 Securing gasket to trackdormakaba L80 Muto Comfort Ceiling Mount -
Securing gasket to track 2.4.1 Ensure the track is cut to proper length.
NOTE: SEE DIMENSION INSTRUCTIONS ON PAGE 6.
2.4.2 Cut adhesive gasket equal to sidelite glass width.
2.4.3 Adhere gasket along bottom edge of back of track.
2.5 Securing track and sidelite section profile to mounting surfacedormakaba L80 Muto Comfort Ceiling Mount - Securing
track 2.5.1 Secure track to mounting surface.
2.5.2 Align predrilled holes in sidelite profile with track profile.
NOTE: Holes will be predrilled every 7-7/8″ [200].
2.5.3 Secure with proper fasteners.
NOTE: Be sure fasteners are flush with track to avoid rollers catching protruding fasteners.
2.6 Installing U-channel for sidelitedormakaba L80 Muto Comfort Ceiling
Mount - Installing U-channel 2.6.1 Install gaskets as shown. Trim to correct length.
2.6.2 Secure u-channel to floor using appropriate fasteners.
NOTE: Ensure u-channel is plumb and the back of the u-channel profile aligns with back of sidelite profile.
2.7 Installing sidelite glassdormakaba L80 Muto Comfort Ceiling Mount -
Installing sidelite glass 2.7.1 Place setting blocks into u-channel.
2.7.2 Spray inside of u-channel with glass cleaner.
2.7.3 Lift glass up and into sidelite profile.
2.7.4 Lower glass into u-channel.
2.7.5 Ensure there is 1/8″ [3] gap between wall and edge of sidelite glass.
2.7.6 If using tempered laminated glass, gently press glass panel against u-channel gasket and dispense silicone along full length of non-gasket side of U-channel
2.8 Installing sidelite glass filler paneldormakaba L80 Muto Comfort
Ceiling Mount - glass filler panel 2.8.1 Fit filler panel in to gap of door panel section in sidelite profile.
2.9 Installing sidelite glass gasketdormakaba L80 Muto Comfort Ceiling
Mount - glass gasket 2.9.1 Cut gasket to length per chart above.
2.9.2 Press gasket in between sidelite glass and sidelite profile.
2.10 Securing wood door adaptor
dormakaba L80 Muto Comfort Ceiling Mount - Securing
wood NOTE: Top of door must be reinforced to secure wood door adapter.
2.10.1 Prepare door properly for wood door adaptor.
NOTE: Seal top and bottom of door to minimize warping (use wood door manufacturer’s recommendations).
2.10.2 Cut wood door adapter to be equal width of door.
2.10.3 Secure the two wood door adaptor pieces to top of wood door with #10 x 3″ wood screws.
NOTE: Be sure screws are always secured in the first four and last four holes of the adaptor, along with every fourth hole in between.
2.11 Installing the roller carriersdormakaba L80 Muto Comfort Ceiling
Mount - roller carriers NOTE: FULLY CLEAN SURFACE OF ADAPTOR WITH AN ALCOHOL-BASED MILD GLASS AND SURFACE CLEANER.
ENSURE GASKET IS FREE OF DEBRIS.
ENSURE ROLLER CARRIER WHEELS ARE FREE OF DEBRIS.
2.11.1 Slide roller carriers onto wood door adaptor.
2.11.2 Slide gasket and metal shim between adaptor and roller carrier.
NOTE: Orient with gasket facing the adaptor.
2.11.3 Secure roller carriers to wood door adaptor using appropriate-size hex key at 10ft lbs (14 Nm).
**2.12 Install DORMOTION start/stop![dormakaba L80 Muto Comfort Ceiling Mount

  • Install DORMOTION start](https://manuals.plus/wp- content/uploads/2024/06/dormakaba-L80-Muto-Comfort-Ceiling-Mount-Install- DORMOTION-start.jpg) NOTE:** Determine a pin length based upon how square and plumb the opening is.
    2.12.1 If required, change pin in start/stop assembly.

    • Remove hex screws.

    • Remove existing pin and plate.

    • Swap in appropriate pin and plate.

    • Replace hex screws. Do not tighten
      2.12.2 Slide start/stop onto glass.

    • Center equally between the carriers.
      2.12.3 Slide glass gasket between start/stop and door.
      NOTE: Orient with gasket facing door.
      2.12.4 Secure start/stop via set screws.

2.13 Disengaging the anti-jump![dormakaba L80 Muto Comfort Ceiling Mount

  • Disengaging the anti-jump](https://manuals.plus/wp- content/uploads/2024/06/dormakaba-L80-Muto-Comfort-Ceiling-Mount-Disengaging- the-anti-jump.jpg) 2.13.1 Disengage the anti-jump on roller carrier.
    NOTE: Using the appropriate-size hex key, push antijump adjustment screw IN and turn COUNTERCLOCKWISE 90° to disengage anti-jump.
    2.14 Install door/rollers in trackdormakaba L80 Muto Comfort Ceiling
Mount - rollers in track

ENSURE ROLLERS AND TRACK ARE FREE OF DEBRIS
2.14.1 Tip wood door and rollers upward and rest rollers on track
2.15 Install floor guidedormakaba L80 Muto Comfort Ceiling Mount -
Install floor guide ANTI-JUMP IS DISENGAGED!
2.15.1 Align centerline of glass with centerline of floor guide.
2.15.2 Be sure the glass is plumb.
2.15.3 Mark appropriate floor guide measurements
2.15.4 TEMPORARILY REMOVE WOOD DOOR AND ROLLERS FROM TRACK.
2.15.5 Pre-drill into mounting surface using a 5/16″ drill bit.
2.15.6 Secure floor guide anchor with included fasteners.
2.16 Engaging anti-jumpdormakaba L80 Muto Comfort Ceiling Mount -
Engaging anti-jump 2.16.1 Engage anti-jump on roller carrier.
2.16.2 Using appropriate-size hex key, push anti-jump adjustment screw IN and turn CLOCKWISE 90° to engage anti-jump.
2.17 Adjustment door heightdormakaba L80 Muto Comfort Ceiling Mount -
door height 2.17.1 Set height of glass door.
2.17.2 Loosen height adjustment locking screws of carrier.
2.17.3 Using appropriate-size hex key, turn height adjustment screw CLOCKWISE or COUNTERCLOCKWISE to raise or lower wood door.
NOTE: Be sure glass is level during this adjustment.
2.18 Adjustment end stop location: LEADING end stopdormakaba L80 Muto
Comfort Ceiling Mount - Adjustment end stop location: TRAILING end stopdormakaba L80 Muto
Comfort Ceiling Mount - TRAILING end stop 2.19 Install DORMOTION unitsdormakaba L80 Muto Comfort Ceiling
Mount - DM unit installation RH Dormotion -door closed
2.19.1 Rotate RH DM fastening plates.

  • Using 4 mm hex key, loosen fastening plate hex screws.
  • Rotate fastening plates until they are parallel to the DM unit (Fig. 18.2)
  • Snug hex screws. 2.19.2 Move door to close position.
  • For installation of RH DM unit, door must be in the closed position against bumper.

2.19.3 Align DM unit in track, engage DM hook in DM trigger.

  • Align DM unit in track (Fig. 18.7).

  • Slide DM unit over the DM trigger block until the DM hook engages the DM trigger (Fig. 18.4)
    2.19.4 Use adjustment tool to set DM unit final position.

  • Place adjustment tool flat against DM unit with fork between DM hook and DM end stop (Fig. 18.5).

  • Slide DM unit over until hook and DM end stop are against the fork. This sets 5 mm gap (fork gap).

  • Trigger height: Adjust so trigger sets on top of adjustment tool (Para. 2.20). 2.19.5 Secure the DM unit in position.

  • NOTE: Insure door is fully closed against bumper before performing this step.

  • Using 4 mm hex key, tighten DM unit fastening plate socket head cap screws . Fastening plates must engage the track (Fig. 18.6 and .8).

Torque
Socket head cap screws 3 ft lbs [4 Nm]dormakaba L80 Muto Comfort Ceiling
Mount - DM unit installation 1LH Dormotion -door open
2.19.6 Rotate DM fastening plates.

  • Using 4 mm hex key, loosen fastening plate hex screws.
  • Rotate fastening plates until they are parallel to the DM unit (Fig. 18.10)
  • Snug hex screws. 2.19.7 Move door to open position.
  • For installation of LH DM unit, door must be in the open position against bumper.

2.19.8 Align DM unit in track, engage DM hook in DM trigger.

  • Align DM unit in track (Fig. 18.15).

  • Slide DM unit over the DM trigger block until the DM hook engages the DM trigger (Fig. 18.12)
    2.19.9 Set DM unit final position.

  • Place adjustment tool flat against DM unit with fork between DM hook and DM end stop (Fig. 18.13).

  • Slide DM unit over until hook and DM end stop are against the fork.
    This sets 5 mm gap (fork gap).

  • Trigger height: Adjust so trigger sets on top of adjustment tool (Para. 2.20).
    2.19.10 Secure the DM unit in position.

  • NOTE: Insure door is fully open against bumper before performing this step.

  • Using 4 mm hex key, tighten DM unit fastening plate socket head cap screws . Fastening plates must engage the track (Fig. 18.16).

Torque
Socket head cap screws 3 ft lbs [4 Nm] 2.20 Adjust start/stop pin height (if necessary)dormakaba L80 Muto Comfort Ceiling Mount - Adjust
start 2.21 Cover clipsdormakaba L80
Muto Comfort Ceiling Mount - Cover clips2.21.1 Insert cover clips into track. (One clip per foot)
2.21.2 Insert perpendicular to track, and turn CLOCKWISE to snap into place.
2.22 Cover spacersdormakaba L80 Muto Comfort Ceiling Mount - Cover
spacers 2.22.1 Tip cover spacers into outter most edge of track.
2.22.2 Place one at each end of track as shown.
2.22.3 Tighten at at 1 ft lbs [1Nm] or hand tighten.
2.23 Install brush profiledormakaba L80 Muto Comfort Ceiling Mount -
brush profile 2.23.1 Measure and cut brush to appropriate length.
2.23.2 Slide brush into cover
2.24 Install view protection clipsdormakaba L80 Muto Comfort Ceiling
Mount - protection clips 2.24.1 Slide door open until it meets the end stop.
2.24.2 Measure and cut view protection profile to fit into empty sliding portion of track – 3/16″ [5].
2.24.3 Snap view protection clips onto inside of cover as shown.
2.24.4 Use minimum 1 clip per foot of profile.
Exception: If profile is minimum of 1 foot in length, use 2 clips.
2.25 Install cover and view protection profiledormakaba L80 Muto
Comfort Ceiling Mount - view protection profile 2.25.1 Secure cover to clips and snap into place.
NOTE: Roll cover from the bottom upwards. Ensure the bottom of the cover is supported by the groove in the cover clip.
2.25.2 Tip view protection profile up into track and snap down into cover and onto track as shown.
2.26 Install end capsdormakaba L80 Muto Comfort Ceiling Mount - Install
end caps 2.26.1 Snap sidelite profile end caps into sidelite profile.
2.26.2 Snap end caps into cover

https://bit.ly/3v0h9lh?r=qr
Scan for product details and downloads.
Call 800-523-8483 or visit
glasstechserv.us@dormakaba.com
for assistance or warranty information
dormakaba USA, Inc.
1 Dorma Drive, Drawer AC
Reamstown, PA 17567

Read User Manual Online (PDF format)

Read User Manual Online (PDF format)  >>

Download This Manual (PDF format)

Download this manual  >>

dormakaba User Manuals

Related Manuals