Installation Steps

  • Step 1 – Use a laser level to outline the position of the L tee.

  • Step 2 – Snap a chalk line.

  • Step 3 – Fix L tees in position with screws.

  • Step 4 – Mark positions for tensioners to hang main tees.(The spacing of the main tees is 60cm)

  • Step 5 – Fix the tensioner with the screw.

  • Step 6 – Screw the cover onto the tensioner.

  • Step 7 – Thread cables through brackets.

  • Step 8 – Fasten the cable to the tensioner.

  • Step 9 – Thread main tees through brackets.

  • Step 10 – Adjust the length of the cables until the main tees are level.

  • Step 11 – Install cross tees.

  • Step 12 – Install PVC panels.