RAB SWISH34 2×2 Watt Economy Center Basket LED Troffer Installation Guide

June 4, 2024
RAB

RAB SWISH34 2×2 Watt Economy Center Basket LED Troffer Installation Guide
RAB SWISH34 2x2 Watt Economy Center Basket LED
Troffer

IMPORTANT

READ CAREFULLY BEFORE INSTALLING FIXTURE. RETAIN THESE INSTRUCTIONS FOR FUTURE REFERENCE.
RAB fixtures must be wired in accordance with the National Electrical Code and all applicable local codes. Proper grounding is required for safety. THIS PRODUCT MUST BE INSTALLED IN ACCORDANCE WITH THE APPLICABLE INSTALLATION CODE BY A PERSON FAMILIAR WITH THE CONSTRUCTION AND OPERATION OF THE PRODUCT AND THE HAZARDS INVOLVED.

WARNING: Make certain power is OFF before installing or maintaining fixture. No user serviceable parts inside.

RECESSED CEILING MOUNTING

The fixture is suitable only for indoor recessed ceiling application. Above ceiling access required.

To mount in an insulated or non-insulated ceiling – 9/16” or 15/16” exposed flat tee grid ceiling follow the steps below.

  1. Firmly bend the pre-installed Grid Clips (up and out as shown in Fig. 1).
    RECESSED CEILING MOUNTING

  2. Rotate and slide the Fixture as required to fit through the Tee-Grid Bar and place it as indicated by the directional arrow as shown in Fig. 2. Secure the Fixture to the Tee-Grid Bar.
    RECESSED CEILING MOUNTING

  3. Support wires are required by installation Codes. Support the Fixture to the building structure by Support Wires (supplied by others) through the Grid Clip Hole as shown in Fig. 2.

  4. Make sure that the orientation of the Splice Box and Access Plate faces an accessible tile to make electrical splices.

  5. Loosen Access Plate Screw and remove the Access Plate.
    Knock out appropriate Conduit Knockouts on the Access Plate to route input conduit. Use appropriate conduit connectors as required by code (Fig. 3).
    RECESSED CEILING MOUNTING

  6. Connect wires as shown in wiring diagram (Fig. 4). Push all wires back into the Splice Box. Use appropriate UL approved wire connectors as required by code to complete wiring.
    Be careful not to pinch wires. WARNING: To prevent wiring damage or abrasion, do not expose wiring to edges of sheet metal or other sharp objects.

  7. Replace Access Plate and tighten Access Plate Screw.

SAFETY INSTRUCTIONS

WARNING: Risk of fire or electric shock. Suitable for Damp locations.

WARNING: Suitable for 9/16” or 15/16” Flat Tee Grid in both Insulated Ceilings and Non-Insulated Ceilings. Access above ceiling required.

WARNING: Do not handle energized fixture when hands are wet, when standing on wet or damp surfaces, or in water.

WARNING: Vapor barrier must be suitable for 90° C.

WARNING: Fixture to be independently supported to building structure.

0-10V DIMMABLE WIRING

Universal voltage driver permits operation at 120V thru 277V, 50 or 60 Hz. For 0-10V Dimming, follow the wiring directions as shown in below (Fig. 4).
0-10V DIMMABLE WIRING

Do not use any supply voltage other than 120V-277V.

  1. Insert the LINE supply lead into the black push connector.
  2. Insert the COMMON supply lead into the white push connector.
  3. Insert the GROUND supply lead into the green push connector.
  4. Insert Dim+ supply lead into the purple push connector.
  5. Insert Dim- supply lead into the pink (or gray) push connector.

CLEANING

CAUTION: Be sure fixture temperature is cool enough to touch. Do not clean or maintain while fixture is energized.

  1. Clean polystyrene lens & fixture with non-abrasive cleaning solution.
  2. Do not open fixture to clean the LEDs. Do not touch the LEDs.

TROUBLESHOOTING

  1. Check the line voltage at fixture. Refer to wiring directions.
  2. Is the fixture grounded properly?

BATTERY BACKUP MODELS

WIRING

CAUTION: FOR BATTERY BACKUP FIXTURE. Voltage can be present in BATTERY. To prevent high voltage from being present on output leads, Inverter Connector must be open. Do not join

BATTERY connector until installation is complete and AC power is supplied to the emergency driver. (Fig. 5)
BATTERY BACKUP MODELS

NOTE: Make sure that the necessary branch circuit wiring is available. An UNSWITCHED AC source of power is required.
The emergency driver must be fed from the same branch circuit as the LED driver.

CAUTION: Do not use any supply voltage other than 120-277V 50/60 HZ.

  1. Connect UNSWITCHED HOT fixture lead to HOT AC supply line.
  2. If using an UNSWITCHED circuit, connect UNSWITCHED and SWITCHED lines together.
  3. If using a SWITCHED circuit, connect SWITCHED HOT AC fixture lead to the external.
  4. Connect the pink (or gray) fixture lead to the (V-) DIM lead.
  5. For 0-10V Dimming, connect DIM (+) and DIM (-) to the supply ground. Do not connect GROUND to the output leads.
  6. All unused leads must be capped and insulated.
  7. After installation is complete, supply AC power to the fixture and connect the BATTERY.
  8. When power is on, the fixture should be on and the Charging Indicator Light should illuminate to indicate the battery is charging.
  9. Once the BATTERY has charged for at least one hour, a short duration test may be performed by pressing the test button.
  10. After the battery has charged for 24 hours, a long duration test can be performed by shutting power to the fixture.

OPERATION

  1. When AC power is applied, the charging indicator light is illuminated, indicating that the BATTERY is being charged.
  2. When power fails, the standby power automatically switches to emergency power (internal battery), operating at reduced illumination. The emergency driver supplies 8W of power for SWISH 2X2 and 16W of power for SWISH 2X4 in standby power for a minimum of 90 minutes.
  3. When AC power is restored, the emergency driver automatically returns to charging mode.

MAINTENANCE

Although no routine maintenance is required to keep the emergency driver functional, it should be checked periodically to ensure that it is working. The following schedule is recommended:

  1. Visually inspect the charging indicator light monthly. It should be illuminated.
  2. Test the emergency operation of the fixture at 30-day intervals for a minimum of 30 seconds.
  3. Conduct a 90-minute discharge test once a year. Fixture will operate at reduced illumination for a minimum of 90 minutes.

TROUBLESHOOTING

  1. Is the fixture grounded properly?
  2. If the charging indicator light does not illuminate after pressing the test button, check if battery is connected properly.

INSIDE FIXTURE

Note: These instructions do not cover all details or variations in equipment nor do they provide for every possible situation during installation, operation or maintenance.

Easy Answers

rablighting.com
Visit our website for product info

Tech Help Line
Call our experts: 888 722-1000

e-mail
Answered promptly – sales@rablighting.com

Free Lighting Layouts
Answered online or by request

SWISH34 2X2, 2X4 – 1221
73696-RAB

RAB WARRANTY: RAB’S Warranty is subject to all terms and conditions found at rablighting.com/warranty.

RAB Lighting is committed to creating high-quality, affordable, well- designed and energy-efficient LED lighting and controls that make it easy for electricians to install and end users to save energy. We’d love to hear your comments. Please call the Marketing Department at 888-RAB-1000 or email:marketing@rablighting.com

Logo

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

Related Manuals