GivEnergy HY 3.6 Hybrid Inverter Gen 1 Instruction Manual

June 13, 2024
GivEnergy

GivEnergy HY 3.6 Hybrid Inverter Gen 1

GivEnergy-HY-36-Hybrid-Inverter-Gen-1-product

SPECIFICATIONS

  • Dimensions
    440H x 260D x 480W (mm)

  • Weight
    24 Kg

  • Warranty
    12 years

  • Operational temperature
    25ºC – 55ºC

  • Max. DC Input Power
    15kW

  • Start-Up Voltage
    3.6kW -140V 5.0kW -140V

A TRUE MULTI-TASKER
Battery Inverter and Solar Inverter in One

GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(1\)

The first-generation hybrid inverter can be coupled directly with solar panels to generate electricity in the property during daylight hours, as well as store any excess energy for later use in our batteries to minimize export. Additionally, it will minimize import by discharging to meet demand in the property. The Hybrid Inverter Gen 1 is connected to our Gen 1 batteries using a ring terminal to ring terminal cable, and ring terminal to all-in-one plug for our Gen 2 batteries.

BOX CONTENTS

GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(2\)

Item Item Name Qty
A Inverter 1
B Mounting Bracket 1
C WiFi or 4G (additional) 1
D Battery Terminal Cover 1
E BMS, RS485 Communications Port Cover 1
F AC Supply Terminal Cover 1
G Cover Screw 14
H Inverter Security Pin 2
I Mounting Frame Fixings 4
J Battery Input Terminations 2

COMPONENTS

GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- 21GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(3\)

GENERAL INFORMATION

Introduction

All information contained in this booklet refers to the assembly, installation, commissioning, and maintenance of the Generation 1 Hybrid Inverter. Please retain this manual for future reference. Legal Disclaimer: This document is the property of GivEnergy, reproduction is prohibited.

Installation Requirements
Installation of all GivEnergy equipment must be carried out by a GivEnergy Approved Installer.

GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(4\)

Unit Information
The Hybrid Inverter is a battery inverter and solar inverter in one. It is bi- directional, meaning it can charge from the grid (AC coupled) and from solar (DC coupled).

Storing the Inverter
The unit must be stored in its original packaging at temperatures between 5ºC – 60ºC. Do not stack more than 4 units on top of each other.

Packaging Contents
When unpacking, please check the following:

  • There are no missing accessories from the packaging list
  • The model and specification of the inverter’s nameplate match the order specifications

If any damaged or missing parts are found, please contact GivEnergy on 01377 252 874 or email [email protected] immediately. Returns must be provided in original or equivalent packaging. The cardboard packaging is recyclable.

SAFETY AND INSTALLATION

Safety Instructions
Extra care and attention must be taken when installing and maintaining any GivEnergy equipment. The system is capable of retaining a high voltage, even when disconnected.

  • If you suspect something is wrong with the inverter, contact GivEnergy on 01377 252 874 or email [email protected]
  • If any damaged or missing parts are found, please contact GivEnergy on 01377 252 874 or email [email protected] immediately. Returns must be provided in original or equivalent packaging
  • All electrical installations must be carried out by a qualified and registered Electrician and in accordance with the IEE Wiring Regulations
  • During operation, the heat sink may become hot. Do not touch the heat sink at the sides, or the top of the inverter when in operation
  • The inverter is designed to be connected to the grid; connecting your inverter to a generator or other power source can result in damage to the inverter or external devices
  • All GivEnergy equipment must be installed by a GivEnergy Approved Installer

Precautions

  • It is very important for system safety and efficient operation to use appropriate cables for battery connections. 16mm2 (minimum) tri-rated cables must be used for DC battery connections
  • The voltage of the battery connected must not exceed 60V (or it will damage the inverter and void any warranty)
  • Only GivEnergy batteries should be connected to our inverters
  • Reversed polarity will damage the inverter
  • The battery must be installed in accordance with the Battery Installation Guide

STEP-BY-STEP INSTALLATION

  1. The wall thickness for mounting the inverter must be no less than 100mm. Remove the wall mounting bracket from the back of the inverter place horizontally onto the wall and mark the position of the bracket holes.

  2. Drill 4 holes at the marked positions, at least 75mm deep. Fix the mounting bracket to the wall using 4 x M6x50 expansion bolts.GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(6\)
    Please note : If fitting the inverter to a non-masonry wall, different fixings will be required.

  3. Mount the inverter onto the mounting bracket.

  4. Insert the 2 x M4 safety locking screws on the left and right sides to prevent the inverter from being lifted off the bracket.

CLEARANCE AND MAINTENANCE

Space Clearance
There must be adequate clearance around the inverter to allow for heat dissipation. The diagram below illustrates the space required around the inverter.

Maintenance
When maintaining and cleaning the inverter, the whole system must be powered down. Please refrain from using cleaning products on the surface of the inverter. To ensure your inverter operates optimally at all times, annual maintenance checks need to be carried out. Check for visible damage or discoloration of the switch, and that the cables are intact. Please ensure that the top of the inverter is not obstructed in any way. Whilst the inverter is powered down, we recommend operating the PV rotary isolator from ON to OFF 2-3 times, this cleans the contacts of the rotary switch.
Please note: do not carry out this maintenance while the inverter is switched on.

CONNECTIONS OVERVIEW

Item Item Name

  • APV Isolation Switch
  • B Battery DC Terminals
  • C PV Input
  • E USB Port
  • D Communication/DRM Ports
  • F EPS Supply Terminals
  • G AC Supply Terminals

GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(10\)

AC UTILITY GRID CONNECTION

Cable size requirements for the Hybrid Inverter are dependent on the model:

  • HY 5.0 – minimum 4mm² – 6mm²
  • HY 3.6 – minimum 2.5mm² – 4mm²

The recommended maximum cable length should not exceed 50m as the resistance of the cable will consume inverter output power and reduce the inverter efficiency. You must install a separate AC circuit breaker per inverter in order to ensure that it is adequately protected and can be safely disconnected under load.

CONNECTING TO THE EPS
The Emergency Power Supply (EPS) can provide a maximum output power of 5000W (dependent on the inverter model, see table below) during a grid failure. This output must be protected as close to the inverter as possible, with a double pole 30mA RCD rated at up to 20A. There are four approved methods to connect to the EPS, please refer to the EPS Connection Guide on our Knowledge Base for more information.

Maximum Power Output

Hybrid Gen 1 2.6
Max. Power Output (Battery & Solar)

Max. Power Output from Battery

| 5000W

2600W

Hybrid Gen 1 5.0
Max. Power Output (Battery & Solar)

Max. Power Output from Battery

| 3600W

2600W

If the backup terminals are used, please ensure the following
An earth rod must be installed and connected to the main earthing terminal, as close to the origin of the supply as possible, and adequate overload / short circuit protection must be installed in accordance with the IEE wiring regulations. The EPS MAX output power is 5000W (dependent on the inverter model, see table above). If the load is greater than 5000W the inverter will stop outputting and go into fault. The EPS output will only operate when the battery(s) have capacity available. Any other grid-tied generation must be supplied from the grid side of the changeover switch to avoid damage to the inverter, and voiding any warranty (see the following diagrams for reference).

  • Incorrect wiring of full property backup with manual or automatic change-over switch:
  • Correct wiring of full property backup with manual or automatic change-over switch:

GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(13\)

CONNECTING THE BATTERY TO THE INVERTER

  1. A DC MCB must be installed between the master battery and the inverter of Gen 1 batteries (not less than 100A), this will ensure the inverter can be safely disconnected during maintenance. Please note that a separate DC MCB is not required with Gen 2 batteries as they have one integrated unless Gen 1 batteries are installed after a Gen 2 battery pack.GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(14\)
  2. Generation 1 battery only Check the battery nominal voltage and polarity. When connecting a Gen 1 inverter to a Gen 1 battery (2.6kWh, 5.2kWh, 8.2kWh), a ring terminal to ring terminal cable must be used.GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(15\)
  3. Generation 2 battery only When connecting a Gen 1 inverter to a Gen 2 battery (9.5kWh), a ring terminal to an all-in-one cable must be used. Connect the ring terminal cable to the battery terminal connection on the inverter. The other end can then be connected to the A-socket on the Gen 2 battery (ensure that the red clip is facing away from the inverter, and is pushed in securely).
  4. Installation of additional batteries If connecting additional Gen 1 batteries after a Gen 2 battery, you must install a DC MCB in between the Gen 2 and the Gen 1 battery to ensure that the Gen 1 battery can be safely isolated, as it has no in-built isolation.GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(17\)

CONNECTING MID-APPROVED METER TO INVERTER In the system, a mid-approved meter must be installed to ensure correct monitoring of the grid power. The inverter uses this information to decide whether to charge or discharge the battery. The CT clamp that is connected to the mid-approved meter must be installed around the live incoming supply to the property, with the arrow pointing in the direction of grid import, in order to monitor the complete consumption of the building.
GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(18\)

Communication/network ports

COMMUNICATION CONNECTIONS

START-UP AND SHUT-DOWN OF THE INVERTER

  1. Connect the AC circuit breaker, and ensure that the system is powered and commissioned using the portal/App.
  2. Ensure that the grid power is reading identical to that of the mid-approved meter (this can be found on the screen of the meter).
  3. Turn on the PV switch
  4. Turn on the battery breaker
  5. Turn on the battery
  6. The inverter will start automatically when the PV voltage is higher than 150V, and the battery voltage is higher than 46.4V

Shutdown Procedure

  1. Turn off the battery
  2. Disconnect the AC circuit breaker to prevent it from being reactivated
  3. Disconnect the battery breaker to prevent it from being reactivated
  4. Turn off the PV switch
  5. Check the inverter operating status
  6. Wait until all LEDs have gone out. The inverter is now shut down

COMMISSIONING & DECOMMISSIONING A SYSTEM
All systems must be commissioned to ensure correct battery and meter communications, as well as connection to the online portal.
Note: Without commissioning, the system may not operate correctly. Check that all the wires are securely connected before the battery breaker and the AC isolator is switched on. You MUST set the parameters of the battery according to your battery system.

Accessing the Commissioning Portal
Sign into the online portal at https://portal.givenergy.cloud with your GivEnergy Engineer login. If you are a first-time user, and you do not have an account or Engineer login, please consult your supplier to get this set up. To download a fully illustrated guide, please visit our Knowledge Base at www.givenergy.co.uk

Uninstalling the Inverter

  1. Remove all connections and cables from the inverter
  2. Remove the locking pins which are securing the inverter to the bracket
  3. Lift the inverter off the bracket
  4. Remove the wall bracket

Packaging the Inverter
If possible, always pack the inverter in its original packaging and secure it with tension belts. If this is not available, you may also use an equivalent- sized box. The box must be capable of being closed completely and be strong enough to support both the weight and the size of the inverter.

Storing the Inverter
Store the inverter in a dry place where ambient temperatures are always between -25ºC and +60ºC

WORK MODES

Eco Mode
The system optimizes the delivery of generated PV power and battery power to prioritize the home load. Grid power is used as a last resort if solar and battery power are unavailable.

Peak Charging / Peak Discharging
This is prioritized to charge the battery during off-peak times when energy is cheaper, greener, and cleaner. The battery will start to discharge outside of the off-peak time when energy is more expensive to support the home, otherwise, the battery can be discharged at full power to support a variable export tariff.

Back-Up / Island Mode
The system has the ability to be used in the event of a power cut. To utilize this feature, circuits must be connected to the inverter’s EPS terminals. To download a fully illustrated guide on connecting the inverter to the EPS, please visit our Knowledge Base at www.givenergy.co.uk.

This inverter is covered by a 12-year warranty.

Products Covered

GivEnergy-HY-36-Hybrid-Inverter-Gen-1-fig- \(20\)

www.givenergy.co.uk

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

GivEnergy User Manuals

Related Manuals