SUSSEX BLWBMS160RH Lever Wall Basin Mixer Outlet System Dress Kit Owner’s Manual

June 12, 2024
SUSSEX

Suba
Lever wall basin mixer outlet system Dress kit

Product code

BLWBMS160RH Lever wall basin mixer outlet system 160mm
BLWBMS210RH Lever wall basin mixer outlet system 210mm

SUSSEX BLWBMS160RH Lever Wall Basin Mixer Outlet System Dress Kit -
Parts

Mixer dress kit

  • Remove Mixer protective cover.
  • Using silicon, seal the wall surface around the Mixer.
  • Apply a small amount of silicon to the rear of the backplate prior to mounting onto the wall.
  • Fit the handle body onto the Mixer Cartridge Lever ensuring the Handle is fully engaged.
  • Secure the Handle Body by tightening the Set screw using the Allen Key provided (tighten well).

Outlet fit off

  • Apply a small amount of grease to the O-rings of the fitting.
  • Carefully fit the Outlet ensuring the locating pins align with the Backplate.
  • Secure the Outlet by tightening the Set Screw.
    To complete the installation, operate the Mixer(s) checking the flow of both hot and cold water from Outlet.
    Check all fittings and fixtures for water leaks.

SUSSEX BLWBMS160RH Lever Wall Basin Mixer Outlet System Dress Kit - Parts
2

Rough in plumbing

  • Prior to installing, calculate the finished wall thickness, maximum is 30mm thick, contact manufacturer for  further options.
  • If Wall thickness is greater than 30mm, contact manufacturer for further options.
  • Prepare a Nogging to be fixed parallel between the Wall Studs.
  • The Nogging must be fitted to enable the base of the Masterfit to be 30-32mm back from the Stud Face.
  • The Masterfit will be marked “This side Up” to indicate orientation.
  • Using the screws (x4) provided, mount the Masterfit to the Nogging. Ensure the Masterfit is level and square.

Pipe connections

  • The Hot and Cold ports are marked on the Masterfit. (Mixers have individual Hot/Cold inlet ports).
  • Flush all water feed lines. All lines must be free from any dirt and debris before connecting to the Masterfit.
  • Connect Hot and Cold lines to the corresponding 1/2” BSP ports of the Masterfit. (see Drawing)
  • Do not remove any factory fitted pressure plugs or Fixings.
  • Once all water connections are made, check Hot/Cold water flow by operating the Mixer Cartridge.
  • Check all fittings and fixtures for leaks.
  • Leave the Mixer(s) in the closed position and replace the Mixer protective cover.
  • Store the Dress Kit in a safe place until required (see Dress Finishing Guide)

Plumber note

  • On-site high pressure line testing must be conducted with the Mixer in the closed position. (STATIC TEST ONLY)
  • Under no circumstances is the Mixer to be opened when exceeding the maximum stated water pressure.
  • At the completion of the testing, do not relieve any high pressure by opening the Mixer.
  • Exposing the internals of the Mixer Cartridge to higher than specified water pressures, will void the manufacturer’s warranty.

Tapware is to be installed by a Licensed Plumber in accordance with AS/NZS 3500:2003
Recommended working water pressure 300-500 kpa. Maximum water temperature is 65 deg.c