DISASSEMBLY DRAWING OF BADGE MOLD

  1. Red badge machine
  2. Tripod badge machine
  3. Rotary badge machineVEVOR-Red-Button-Badge-Maker-Machine-fig- \(3\)
  4. Slide rail mold· New moldVEVOR-Red-Button-Badge-Maker-Machine-fig- \(4\)

BADGE MACHINE INSTALLATION PROCESS

  1. With a hexagonal wrench Fix the machine to the base
  2. Install the handle on the machine
  3. The convex points of the upper die are aligned with the grooves of the head and pushed up, and the head will automatically absorb the upper die VEVOR-Red-Button-Badge-Maker-Machine-fig- \(5\)
  4. Installation complete Place the pattern and badge on the mold to form the finished product
  5. Effectively prevent the slide rail from falling off and the mold from being misaligned
  6. Align the slide rail mold with the groove and push it forwardVEVOR-Red-Button-Badge-Maker-Machine-fig- \(6\)

INSTALLATION PROCESS OF ROTATING BADGE MACHINE

  1. Press the handle down, Align the bumps of the upper mold with the grooves, and Push it up
  2. The raised part of the left mold L with the Align mounting hole of the base, Put it in flatVEVOR-Red-Button-Badge-Maker-Machine-fig- \(7\)
  3. Put the pattern and badge material on the mold to start making
  4. The convex part of the right mold R with the Align mounting hole of the base, Put it in flatVEVOR-Red-Button-Badge-Maker-Machine-fig- \(8\)

BADGE MAKING PROCESS

  1. With a circle cutter Cut out the printed picture
  2. Put the upper cover of the tinplate badge into the left mold
  3. Drawings and Transparent protective film Put them on the tinplate in turnVEVOR-Red-Button-Badge-Maker-Machine-fig- \(9\)
  4. After pressing, Push the slide rail to Hie’s right, is complete
  5. Put the bottom cover into the mold on the right,Push the slide rail to the left until Align the upper and lower die, Press down the handle Press the mold to the bottom
  6. Push the slide mold to the right and align the upper and lower dies, Press the handle to push the mold to the bottomVEVOR-Red-Button-Badge-Maker-Machine-fig- \(10\)

DESIGN STANDARD OF BACKGROUND PAPER

VEVOR-Red-Button-Badge-Maker-Machine-fig- \(11\)

  • finished product Size of
  • Image specifications
  • Cutting sizeVEVOR-Red-Button-Badge-Maker-Machine-fig- \(12\)

Batch printing:
157g coated paper, Double-sided coated with oily light film;

Home printing:
115-135g photo paper, Membranes matched with consumables

Digital developing photo paper:
The thickness is less than 0.2mm All kinds of brand photo paper

Skill: How to make the pattern correct?
Put the drawings at exactly 12 o’clock with the mold stopper as a reference, and put the bottom cover at about 11 o’clock in mold R, make several comparison positions of finished products and make marks on the mold.

VEVOR-Red-Button-Badge-Maker-Machine-fig- \(14\)

Figure 1: When the upper die is loose, the inner hexagon wrench can be used to tighten the mold. The standard is 1.2.3 three points in a line.

VEVOR-Red-Button-Badge-Maker-Machine-fig- \(15\)

Figure 2: loosen the screw of the mold slightly with a hexagon wrench, rotate the whole die to an angle, and then conduct a pressure test until the upper and lower dies are aligned, and then tighten the screws.

SOLUTIONS TO COMMON PROBLEMS

Fault phenomenon Possible reasons Exclusion method
The iron cover won’t suck up 1. Improper operation method

2. The upper mold

There is too much lubricating oil on

| 1. When pressing the first step, The upper mold must be separated
2.  lubricating oil on the upper mold, There is too much Dry with a towel or paper
| 3. When the upper mold and the lower mold are closed, Must be on the same vertical line
Part of the the membrane is not covered| 1. Improper operation method 2.The friction of mold is large 3. Paper thickness is not suitable 4. Loose upper mold| 1. When the upper mold and the lower mold are closed,

Must be on the same vertical line 2.Apply lubricating oil to upper and lower die the inner circle of the

3.Use paper of a specified 4. Putthe mold on the machine body and tighten the loose screws of the upper mold ( As shown in Figure 1 )

 |  | Need to press in place
Compaction is not tight| 1. Not pressed to the end 2.Paperisthin

3.No gasket is placed

| 2. Use thicker paper instead 3.Refrigerator magnet,

Iron bottom badge, When making,

put2mm thick gasket in the right mold core

| 4. Loose upper mold| 4. Tighten the loose screws of the upper mold
There is noise when pressing| The friction between dies is large| Apply lubricating oil to upper mold and the lower mold the inner circles of the
It is necessary to manually adjust of the upper and lower dies the separation and closing

2. The upper mold can rotate 360 degrees

| Loose upper mold| 1. The convex point of the die head is broken and can be replaced

2.  Tighten the upper die screws

The upper mold is stuck together| 1. Deviation of upper and lower dies 2. Foreign matters such as paper is stuck in the mold| With sharp objects, such as screwdrivers, Align the gap between the upper and lower dies Knock on objects with the help of a hammer, etc. Make it drill open
The upper mold and the lower mold is not in the same vertical line| 1. Wrong mold position

2. Reverse installation of the mold slide rail

| 1. The pushed die position has passed or is not in place

2. The slide rail of the mold

is reversely loaded into the machine Change the position of L and R dies

3. with a hexagonal wrench Loosen the die screws

turn the die at an angle as a whole, and conduct a pressure test until the upper and lower dies are aligned, and then tighten the screws

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

VEVOR User Manuals

Related Manuals