Dextra Opus Column Small Sensor Installation Guide
- June 9, 2024
- Dextra
Table of Contents
Opus Column Installation
Opus Column Small Sensor
WARNING: Luminaire must be earthed. Risk of electric shock from LED
boards if operated with cover removed. Installation / operation outside of
luminaires intended scope invalidates warranty. Suitable only for domestic /
light industrial / industrial applications within the scope of EN55015. Tested
to compliance with BSEN 60598: specification for general requirements and
tests. Must be installed by a suitably qualified person in accordance with all
relevant legislation. Ambient operating temperature of 0°C to 25°C. If maximum
operating temperature is exceeded luminaire will automatically dim / switch
off. Terminal blocks are rated to 16A unless stated otherwise. The light
source is non replaceable. LUMINAIRES WITH EMERGENCY PACK:
When supply is isolated battery output terminals may be live if battery is
connected. Isolate mains and battery before servicing. Emergency luminaires
require unswitched live connection taken from same phase as switched supply.
When unswitched supply is connected status indicator illuminates green, when
unswitched supply is disconnected indicator extinguishes and luminaire
operates in emergency mode. 24 hour charge period required before undertaking
full discharge test. Emergency test sheets provided should be used to record
all emergency tests. Batteries should be replaced when 3 hour duration is not
met. Excessive switching of permanent live may result in premature battery
failure. Battery electrolyte can be harmful to eyes / open wounds, do not
puncture, if electrolyte touches skin / eyes flush with water. Do not
incinerate batteries.
1. Using a 4mm Allen Key, loosen all the grub screws sufficiently to allow
for the column diameter.| 2. Feed the mains cable into the column and offer
the spigot up to the column.
---|---
|
3. Using the 4mm Allen Key, tighten all the grub screws slightly so the
fitting can still rotate.| 4. Press the lid release button and lift the lid
to expose the internal spirit level.
Once the fitting is level, fully tighten the grub screws to 11Nm.
|
5. Spirit level to ensure the fitting is level| 6. To close the lid, apply
force to the centre and always check that the lid has been closed properly.
The release button should sit flush with the housing when closed.
|
7. To adjust the vertical mounting angle, loosen the M10 bolts on the spigot
using an 8mm hex key. DO NOT FULLY REMOVE.| 8. Raise or lower the Opus Column
Head as needed.
|
9. The spigot can be adjusted in 5° increments from -15° to +15°.| 10. To
change the spigot mount to a Post-Top orientation, remove the two M10 bolts
from the rear, rotate the spigot 90°.
|
11. Re-attach the bolts, tightening to a torque of 11Nm.| 12. Each marking
represents a 5° increment.
|
13. When 0° or neutral orientation of the luminaire (with both vertical and
horizontal spigot positioning) is required, the central mark on the spigot
must align with the mark on the body. DO NOT use any part of the body to
reference from.| 14. Follow steps 1-8 to install on a Column.
Commission sensor if appropriate using REA-AP controller according to customer
requirements.
|
Terminal Labelling:
Power
L1| Switched Live
E **| Earth
N| Neutral
Emergency
L2| Unswitched Live
DA/AT3| DALI Autotest
DA/AT3| DALI Autotest
Dimming**
-/D1/DA| Analogue/DSI/DALI
+/D2/DA| Analogue/DSI/DALI
L3| Switch Dim /Corridor Function
220-240V / 50-60Hz
IP65
IK09