Safety Precautions
General Disclaimer
- The information in this quick installation guide is subject to change due to product updates or other reasons. All descriptions here are for guidance only.
- Before installations, read through the quick installation guide.
- All operations should be performed by trained and knowledgeable technicians who are familiar with local standards and safety regulations.
- Check the deliverables for correct model, complete contents, and intact appearance.
- Contact the manufacturer if any damage is found or any component is missing.
- Strictly follow the installation, operation, and configuration instructions in this guide and user manual. The manufacturer shall not be liable for equipment damage or personal injury if you do not follow the instructions. For more warranty details, please visit https://en.goodwe.com/warranty.
Safety Disclaimer
WARINING
- Make sure that the device is powered off before any operations.
- Ensure the cables are connected tightly, securely, and correctly. Inappropriate wiring may cause poor contact or damage the device.
- Additional circuit breakers are recommended on the voltage input side to avoid personal injury or device damage.
- Specification of the protective fuse should be 0.5A.
- In areas at risk of lightning, if the input cable of the device exceeds 10m (33ft), you are recommended to use an external lightning protection device. If the communication cables are wired with grounded metal conduits, the lightning protection device is not necessary.
- Strictly follow the National Electrical Code, ANSI/NFPA 70, and Canadian Electrical Code C22.1 during operations.
Check before Power-on
No.
| Check Item
---|---
1
| The product is firmly installed at a clean place that is well-ventilated and easy- to-operate.
2
| The input power cables, CT Cables, and communication cables are connected correctly and securely.
3
| Cable ties are intact, routed properly and evenly.
Storage
If the equipment is not to be installed or used immediately, please ensure
that the storage environment meets the following requirements:
Do not unpack the outer package or throw the desiccant away.
Store the equipment in a clean place. Make sure the temperature and humidity
are appropriate and no condensation.
If the smart meter has been long term stored, it should be checked by
professionals before being put into use.
Federal Communications Commission (FCC) Interference Statement
This equipment has been tested and found to comply with the limits for a Class
B digital device, pursuant to Part 15 of the FCC Rules.
These limits are designed to provide reasonable protection against harmful
interference in a residential installation. This equipment generate, uses and
can radiate radio frequency energy and, if not installed and used in
accordance with the instructions, may cause harmful interference to radio
communications.
However, there is no guarantee that interference will not occur in a
particular installation. If this equipment does cause harmful interference to
radio or television reception, which can be determined by turning the
equipment off and on, the user is encouraged to try to correct the
interference by one of the following measures:
- Reorient or relocate the receiving antenna.
- Increase the separation between the equipment and receiver.
- Connect the equipment into an outlet on a circuit different from that to which the receiver is connected.
- Consult the dealer or an experienced radio/TV technician for help. This device complies with Part 15 of the FCC Rules. Operation is subject to the following two conditions:
- This device may not cause harmful interference.
- this device must accept any interference received, including interference that may cause undesired operation.
FCC Caution: Any changes or modifications not expressly approved by the party responsible for compliance could void the user’s authority to operate this equipment.
RF exposure warning
This equipment complies with FCC radiation exposure limits set forth for an
uncontrolled environment.
This equipment must be installed and operated in accordance with provided
instructions and the antenna(s) used for this transmitter must be installed to
provide a separation distance of at least 20 cm from all persons and must not
be collocated or operating in conjunction with any other antenna or
transmitter.
Product Introduction
GMK120
**
**
GMK140
GM330
**Waterproof box
**
CT
Wiring System
GMK120
NOTE
- Recommended cross-sectional area of the smart meter input power cable: 1mm2(18AWG).
- CT direction: House–>Grid.
- You are recommended to add fuses with a rated current of 0.5A to L1and L2 on the meter side.
- To ensure the correctness of the monitoring data, connect CT1 to L1, CT2 to L2. Also, the N wire, L1, and L2 need to be connected between the loads and the utility meter.
GMK140
NOTE
- Recommended cross-sectional area of the smart meter input power cable: 1mm2(18AWG).
- CT direction: House–>Grid.
- You are recommended to add fuses with a rated current of 0.5A to L1and L2 on the meter side.
- To ensure the correctness of the monitoring data, connect CT1, CT3 to L1, CT2, CT4 to
L2. Also, the N wire, L1, and L2 need to be connected between the loads and the utility meter.
GM330
NOTE
-
Recommended cross-sectional area of the smart meter input power cable: 1mm2(18AWG).
-
Customers need to prepare CT and CT cables. Certified CTs are recommended.
Recommended cross-sectional area of the CT cable: 1.6mm2(15AWG). -
CT direction: House–>Grid.
-
You are recommended to add fuses with a rated current of 0.5A to L1, L2, and L3 on the meter side.
-
To ensure the correctness of the monitoring data, connect CT1 to L1, CT2 to L2, and CT3
to L3. Also, the N wire, L1, L2,and L3 need to be connected between the loads and the utility meter. -
Short circuit N and L2 in the three-phase three-line system. Set the smart meter to Three
Phase Three Line mode via Solar Go app or PV Master app. Scan the QR code below to get more information.
|
---|---
Installation
Packing List
Installation and Cable Connection
DANGER
- • Pay attention to the silkscreens on the device when connecting the voltage input cables. Otherwise, the device may be damaged.
- Pay attention to the silkscreens on the device when connecting the CT and RS485 cables. Otherwise, the read-in data may be wrong.
NOTE
- The model of the smart meter differs, but the installation and cable connection steps are the same.In this guide, the GM330 is used as an example to illustrate the installation steps.
- Connect CT1+, CT1-, CT2+, and CT2- only when connecting cables of GMK120 or GMK140. CT3+ and CT3- are reserved.
Installing the rail
Model
| Tightening torque for RS485 terminals
---|---
GMK120|
0.2N·m
GMK140
| 0.2N·m
GM330|
0.5N·m
Installing the waterproof box
NOTE
- You are recommended to remove the cable hole cover using a screwdriver and a rubber hammer. Do not damage the smart meter when removing the cover.
- You are recommended to use the cable hole at the bottom of the box to ensure its waterproof performance. Customers need to prepare PG21 and PG16 waterproof connectors and tighten the connectors at the cable hole.
Commissioning
Power ON
Step 1 Connect the smart meter cables.
Step 2 Turn on the breaker on the voltage input side. Then the smart
meter is powered on.
Indicator
Type
| Status| Description
---|---|---
| Steady on| Power on, no RS485 communication.
Blinking| Power on, RS485 communication works properly.
Off| Power off.
| Off| Reserved.
| Steady on| Purchasing from the utility grid.
Blinking| Selling to the utility grid.
Off| No purchasing or selling.
(Only for GMK140)
| Steady on| Purchasing from the utility grid.
Blinking| Selling to the utility grid.
Off| No purchasing or selling.
Reset Button
Press Time | Description |
---|---|
³ 5s | Reset the smart meter. |
Maintenance
DANGER
Power off the smart meter before operations and maintenance. Otherwise, the smart meter may be damaged or electric shocks may occur.
Power OFF
Turn off the breaker on the voltage input side. Then the smart meter is powered off.
WARNING
- Make sure that the smart meter is powered off.
- Wear proper PPE before any operations.
Removing the Smart meter
Step1 Disconnect all the cables, including input power cable cables, CT
cables, RS485 communication cables.
Step2 Press the buckle at the bottom of the device to take it from the
rail.
Step3 Store the smart meter properly. If the smart meter needs to be used
later, ensure that the storage conditions meet the requirements.
Technical Parameters
Model
| GMK120| GMK140| GM330
---|---|---|---
Technical parameters
Input
| Grid| Single-phase(L/N £ 265Vac) Split-phase(L/N£ 265Vac) Three- phase(3-wire,L/L£ 265Vac) Three-phase(4-wire,L/N£ 265Vac)|
Three-phase(3- wire,L/L < 576Vac) Three phase(4- wire,L/N < 520Vac)
Frequency| 50/60Hz
Voltage| Rated voltage| 208V, 120V / 240V|
277V/480V
Voltage range
|
0.88Un-1.1Un
Current
| Rated current| 200A| 5A(MAX)
Current range| 0-200A|
0-5A
Communication
| RS485 interface, Modbus-RTU
Communication Distance|
RS485:1000m(Use shielded twisted-pair cables)
Display and button
|
4 LED (Power supply and network communication indicator, Wireless indicator(reserved),Energy consumption indicator1,Energy consumption indicator2), Reset button
Measurement precision
|
Voltage/Current: 0.5 level Active energy: 0.5 level
Reactive energy: 1 level
Power supply
|
Power consumption £5W
Structural parameters
| Dimension (L x W x H)| 85 x 72 x 72mm/33.5×28.3×28.3in
Weight
|
240g/0.53lb
Installation|
Rail installation
Environment paraments
|
Protection class
| IP20
Working temperature|
-30℃-+70℃/-22℉-+158℉
Storage temperature
| -30℃-+70℃/-22℉-+158℉
Relative humidity|
0%-95%, non-condensing
Altitude
|
< 3000m/9842ft
NOTE
The smart meters are not kilowatt-hour metering devices. They can only be used to calculate the element and energy in solar and hybrid systems. Please refer to the data measured by a standard kilowatt-hour meter when you need to calculate the electricity tariff.
**GoodWe Technologies Co., Ltd.
No. 90 Zijin Rd., New District, Suzhou, 215011, China
www.goodwe.com
service@goodwe.com
340-00732-01
Documents / Resources
|
GOODWE GMK120 Smart
Meter
[pdf] Installation Guide
SMARTMETER, 2AU7J-SMARTMETER, 2AU7JSMARTMETER, GMK120, GMK140, GM330, GMK120
Smart Meter, GMK120, Smart Meter, Meter
---|---
|
GOODWE GMK120 Smart
Meter
[pdf] Installation Guide
GMK120 Smart Meter, GMK120, Smart Meter, Meter
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>