Installation Testing Process

  1. Safe Isolation: Ensure the electrical supply is safely disconnected before proceeding with any testing.
  2. Inspection: Visually inspect the installation for any visible issues or irregularities.
  3. Dead Testing: Perform testing on the installation while the electrical supply is disconnected to ensure safety.
  4. Live Testing: Once the electrical supply is connected, conduct live testing to check the functionality.
  5. Functional Testing: Verify the proper functioning of the installation under normal operating conditions.

How to carry out Installation Testing?

The subject of this article ‘Installation testing’ is one half of the Inspection and Testing process. Inspection involves using your senses; sight, touch, hearing, etc. to inspect an electrical installation. Testing is the process of using a meter to take measurements. The aim of the inspection and testing process is to establish the safety and correct functioning of the electrical installation, without posing a danger to the inspector or other persons and without damaging the electrical installation under test.

Electrical testing generally falls into two categories, ‘dead testing’ and ‘live testing’. Dead tests, as the name suggests, are tests carried out on installations, circuits, or equipment that have been safely isolated from the electricity supply, following the correct safe isolation procedure. Some tests, however, cannot be performed on a ‘dead’ installation, and therefore some degree of ‘live’ testing is always necessary. Naturally ‘live’ testing introduces inherent hazards, so all precautions for safety must be taken to prevent danger or injury to the inspector and to others during testing.

To meet this basic and essential aim, the inspection and testing process for new installations usually follows the format detailed below: –

Electrical Supply Safely Disconnected
  • Safe Isolation
  • Inspection
  • Dead Testing
Electrical Supply Connected
  • Live Testing
  • Functional Testing

The aim of the above process is to gradually, step-by-step, prove the safety of the electrical installation in the safest way possible. Only when the installation successfully passes one stage within the process, is it then safe to proceed to the next step. It is essential that inspection and testing are carried out throughout the installation process and on completion. It is not possible to carry out full inspection and testing on a completed installation, as much of the installation may be hidden within the fabric of the building and we may not be able to carry out a full range of tests with all circuit loads connected.

There are two main types of inspection and testing referred to in the wiring regulations (BS 7671). The first is initial verification, the inspection and testing of new installations, alterations or additions. The second is periodic inspection, performed on existing installations.
If you require more help, please contact us at https://www.seaward.com/gb/enquiry/.

15-15-18 Bracken Hill, South West Industrial Estate, Peterlee, County Durham, SR8 2SW, United Kingdom18 Bracken Hill, South West Industrial Estate, Peterlee, County Durham, SR8 2SW, United Kingdom t : +44 (0) 191 586 3511 | f : +44 (0) 191 586 0227 | e : sales@seaward.comt: +44 (0) 191 586 3511 | f : +44 (0) 191 586 0227 | e : sales@seaward.com seaward.comseaward.com

Frequently Asked Questions

Q: How do I ensure safety during live testing?
A: Always follow proper safety procedures, wear appropriate protective gear, and use insulated tools when conducting live testing. Make sure to have qualified professionals supervise the process.

Q: What should I do if I encounter abnormalities during dead testing?
A: If you notice any irregularities during dead testing, do not proceed with live testing. Contact a licensed electrician to address and rectify the issues before continuing.