CHERY LIFE 0171 Retractable Pergola
Specifications
- Dimensions: L=90x90x1760mm
- Material: Steel
- Weight: Varies based on configuration
Product Usage Instructions
Pre-assembly:
- Ensure you have at least two people for assembly.
- Prepare one or more stepladders for access.
- Wear protective gloves during assembly.
- Consider using a safety hat for added protection.
- Have a Phillips screwdriver ready for use.
- If needed, use a drill for easier construction.
- Consider using safety goggles for eye protection.
- Do not fully tighten screws until complete assembly.
Assembly Instructions:
-
Step 1:
Connect part A1 and part A, part A2 and part A on the side of the wall using screws 1# and part B1 as shown in the diagram. Then, connect part A2 and part A, A1 and part A on the other side using screws 1# and part B. -
Step 2:
Use screws 1# to connect part C and C1, and also connect part C2 and C3 together. At the same time, connect five sliders (part S2) on each side as shown in the figure. -
Step 3:
Link part D and part D1, part D and part D2 using screws 1#. Also, link part E and part E1, part E and part E2 using screws 1#. -
Step 4:
Link part F and F1, part G and G1 using screws 1#. Connect the sliders (part S1 and part S) and then hang part R on the outside slider of part G1. -
Step 5:
Connect part D2 with A1, D1 with A2 using screws 2#. Also, connect part E1 with A2, E2 with A1 using screws 2#. -
Step 6:
Connect part C2 with A1, C3 with A2 using screws 2#. Also, connect part C with A2, C1 with A1 using screws 2#. -
Step 7:
Use screws 5# to connect part F with beams (part D1 & D2), and also connect part F1 with beams (part E1 & E2). Connect part G and G1 with beams (part D & E) in the same way. -
Step 8:
Insert part J & J1 into the pocket of top roof (part M) and then insert part H & H1 into the pocket of top roof in turn. -
Step 9:
Insert part L & K, L1 & K1 into the part M1 using part N. -
Step 10:
Secure the part M1 to the top using appropriate screws. -
Step 11:
Connect part J and part D1 according to the diagram provided in the manual.
Warning & Attention:
- Try to assemble on flat ground for ease of assembly.
- Consider assembling with three or more people for efficiency.
- After assembly, ensure all screws are tightened to prevent parts from falling apart.
Frequently Asked Questions (FAQ)
-
How many people are recommended for assembly?
Two or more people are required for assembly. -
What tools are recommended for assembly?
You will need a Phillips screwdriver, possibly a drill for ease, and safety equipment like gloves and goggles. -
Should I fully tighten screws before complete assembly?
No, do not fully tighten screws until complete assembly to allow for adjustments.
Pre-assembly
- Two or more people are required for assembly.
- You will need one or more stepladders.
- Wearing protective gloves is recommended.
- You may need a safety hat.
- Please use a Phillips screw driver.
- For ease of construction, you may need a drill.
- You may need a safety goggle.
- Do not fully tighten screws prior to complete assembly.
Warning & Attention
- Try to assemble this product on the flat ground, otherwise it is difficult to carry out;
- It would be much easier to assemble the product with three or more people;
- After assembly, please check whether all screws are tightened, to prevent parts from falling apart.
Part list
ASEEMBLY INSTRUCTION
-
Step 1: Connect part A1 and part A, part A2 and part A on the side of the wall using screws 1# and part B1 as shown in diagram.
Then connect part A2 and part A, A1 and part A on the other side using screws 1# and part B. -
Step 2: As shown in the figure, use screws 1# to connect part C and C1, and also connect part C2 and C3 together. At the same time, connect five sliders (part S2) on each side.
-
Step 3: Link part D and part D1, part D and part D2 using screws 1# as shown in diagram1# as shown in diagram. And link part E and part E1, part E and part E2 using screws 1# as shown in diagram.
-
Step 4: Link part F and F1, part G and G1 using screws 1# as shown in diagram. And connect the sliders(part S1 and part S). Then hang part R on the outside slider of part G1.
-
Step 5: Connect part D2 with A1, D1 with A2 using screws 2# as shown in diagram. Also, connect part E1 with A2, E2 with A1 using screws 2# as shown in diagram.
-
Step 6: Connect part C2 with A1, C3 with A2 using screws 2# as shown in diagram. Also, connect part C with A2, C1 with A1 using screws 2# as shown in diagram.
-
Step 7: As shown in the figure, use screws 5# to connect part F with beams (part D1&D2), and also connect part F1 with beams (part E1&E2). Then connect part G and G1 with beams (part D&E) in the same way.
-
Step 8: Insert part J&J1 into the pocket of top roof(part M) as shown in diagram, then insert part H&H1 into the of top roof in turn.
-
Step 9: Insert part L&K, L1&K1 into the part M1 using part N.
-
Step 10: Secure the part M1 to the top.
-
Step 11: Connect part J and part D1 and connect part H and part H1.
-
Step 12: When the canopy is folded, hang the other end of string (part R) into the hole on the inside of beam (part E) to secure the top roof.
-