Storage Area: 27 Sq. Ft. 167 Cu. Ft. 2,5 m 2 4,7 m 3
BUILDING DIMENSIONS Size rounded off to the nearest foot
CAUTION: SOME PARTS HAVE SHARP EDGES. CARE MUST BE TAKEN WHEN HANDLING
THE VARIOUS PIECES TO AVOID A MISHAP. FOR SAFETY SAKE, PLEASE READ SAFETY
INFORMATION PROVIDED IN THIS MANUAL BEFORE BEGINNING CONSTRUCTION. WEAR GLOVES
WHEN HANDLING METAL PARTS.
Exterior Dimensions Interior Dimensions Door
Approx. Base (Roof Edge to Roof Edge) (Wall to Wall) Opening
Size Size Width Depth Height Width Depth Height Width Height 6′ x 5′ 74″ x 57″
76 1/4″ 59 1/2″ 79 1/8″ 71 1/4″ 54 1/4″ 77 7/8″ 32″ 69 1/4″ 1,8 m x 1,4 m
188,0 cm x 144,8 cm 193,7 cm 151,1 cm 201,0 cm 181,0 cm 137,8 cm 197,8 cm 81,3
cm 175,9 cm
BEFORE YOU BEGIN
Owner’s Manual
Before beginning construction, check local building codes regarding footings,
location and other requirements. Study and understand this owner’s manual.
Important information and helpful tips will make your construction easier and
more enjoyable.
Assembly Instructions: Instructions are supplied in this manual and contain
all appropriate information for your building model. Review all instructions
before you begin, and during assembly, follow the step sequence carefully for
successful results.
Flooring and Anchoring: Your storage building must be anchored to prevent wind
damage. A base is necessary to construct a square and level building.
Anchoring and base materials are not included with your building. We recommend
the combined use of an Arrow Floor Frame Kit and an Arrow Anchoring Kit as an
effective method of securing your building to the ground (Available at your
local dealer, Arrow’s website arrowsheds.com or call Arrow’s Customer Service
department 1-800-851-1085) or you may
construct a base and anchoring system of your choice. Your assembly
instructions provide information on a few methods commonly used to secure and
level a storage building.
Parts and Parts List: Check to be sure that you have all the necessary parts
for your building.
-
All part numbers can be found on the parts. All of these numbers (before the -) must agree with the numbers on the Parts List page.
-
If you find that a part is missing, include the model number of your building and contact:
Arrow Shed, LLC Customer Service Department 1101 North 4th Street Breese, Illinois 62230 -
Separate contents of the carton by the part number while reviewing parts list. The fi rst few steps show how to join related parts to make larger sub assemblies which will be used later.
-
Familiarize yourself with the hardware and fasteners for easier use during construction. These are packaged within the carton. Note that extra fasteners have been supplied for your convenience. 1-800-851-1085 or assist@arrowsheds.com
PLAN AHEAD
Watch the Weather: Be sure the day you select to install your building is
dry and calm.
Do not attempt to assemble your building on a windy day. Be careful on wet or
muddy ground.
Teamwork: Whenever possible, two or more people should work together to
assemble your building. One person can position parts or panels while the
other is able to handle the fasteners and the tools.
Tools and Materials : These are some basic tools and materials you will
need for the construction of your building. Decide which method of anchoring
and the type of base you wish to use in order to form a complete list of the
materials you will need.
-
Eye Goggles
-
No. 2 Phillips Screwdriver (With Hardened Magnetic Tip)
Note: A power screwdriver or variable speed drill with Phillips-tip attachment can speed assembly by as much as 40%. -
Work Gloves
-
Step Ladder
-
Utility Knife / Scissors
-
Pliers
-
Carpenter’s Level
-
Tape Measure
Optional Time-Savers -
Wrench / Nut Driver
-
Electric / Cordless Drill
-
Square
-
String (for squaring frame)
Base Preparation -
Hammer and Nails
-
Spade or Shovel
-
Hand Saw / Power Saw
-
Lumber and/or Concrete
Selecting and Preparing Your Site: Before assembly, you will want to decide on a location for your building. The best location is a level area with good drainage.
- Allow enough working space for ease of moving parts into position during assembly. Be sure there will be enough space at entrance for doors to open fully and enough space around the building to be able to fasten the panel screws from the outside.
- Before you begin the fi rst steps in assembling your parts, a base should be constructed and an anchoring system should be ready to use.
SAFETY FIRST
Safety precautions are important to follow throughout the construction of your building.
- Care must be taken when handling various pieces of your building since some contain sharp edges. Please wear work gloves, eye protection and long sleeves when assembling or performing any maintenance on your building.
- Keep children and pets away from worksite to avoid distractions and any accidents which may occur.
- Never concentrate your total weight on the roof of the building. When using a step ladder make sure that it is fully open and on even ground before climbing on it.
- Practice caution with the tools being used in the assembly of this building. Be familiar with the operation of all power tools.
- Do not attempt to assemble the building if parts are missing because any building left partially assembled may be seriously damaged by light winds. Call 1-800-851-1085 or assist@arrowsheds.com
- Do not attempt to assemble the building on a windy day, because the large panels acting as a “sail”, can be whipped about by the wind making construction difficult and unsafe.
CARE & MAINTENANCE
Finish: For long lasting fi nish, periodically clean and wax the exterior
surface. Touch-up scratches as soon as you notice them on your unit.
Immediately clean the area with a wire brush; wash it and apply touch-up paint
per manufacturer’s recommendation.
Roof: Keep roof clear of leaves and snow with long handled, soft-bristled
broom. Heavy amounts of snow on roof can damage building making it unsafe to
enter. In snow country, Roof Strengthening Kits are available for most Arrow
Buildings for added protection against heavy snow accumulation. Contact Arrow
as outlined on the Ordering Accessories page to place an order.
Doors: Always keep the door tracks clear of dirt and other debris that
prevent them from sliding easily. Lubricate door track annually with furniture
polish or silicone spray. Keep doors closed and locked to prevent wind damage.
Fasteners: Use all washers supplied to protect against weather
infiltration and to protect the metal from being scratched by screws. Regularly
check your building for loose screws, bolts, nuts, etc. and retighten them as
necessary.
Moisture: A plastic sheet (vapor barrier) placed under the entire floor
area with good ventilation will reduce condensation.
Other Tips….
- Wash off inked part numbers on coated panels with soap and water.
- Silicone caulking may be used for watertight seals throughout the building.
Do not store swimming pool chemicals in your building. Combustibles and
corrosives must be stored in air tight approved containers.
Keep this Owner’s Manual and Assembly Instructions for future reference.
ACCESSORIES
ROOF STRENGTHENING (heavy snow load) KITS
Extra roof beams and gable braces designed for added protection against heavy
snow accumulation. Increases the strength of your roof.
ANCHOR KITS Model No. AK4
Anchor Kit contains heavy-duty steel augers, 60′ (18 m) of steel cable and 4
cable clamps. No digging or concrete pouring, just insert cable under roof,
over roof beams, into augers and twist augers into the ground. For buildings
larger than 10’x9′ (3,0 m x 2,6 m), use 2 kits. Model No. AK100
New concrete anchor system permits anchoring any size Arrow building directly
to a concrete slab. Each kit contains heavy-duty, hot-dipped galvanized steel
corner gussets and perimeter clips which fi t over the floor frame and lag bolt
into a concrete slab. Full assembly instructions and a 1/4″ masonary drill bit
are included.
Model No. AK600
Earth Anchor Kit anchors any size Arrow building to the ground. Each kit
contains heavy duty, hot-dipped galvanized steel corner gussets and 4 earth
anchors.
TOOL HANGING RACK
Model No. TH100
The perfect tool organizer. Twin 25 1/2″ (64,8 cm) steel channels plus fi ve
heavy-duty snap-in hangers and a small tool holder for screwdrivers, pliers,
etc. Holders slide along channel for fully adjustable spacing. Great for
garage, basement, or the back of any door. Fits all Arrow storage buildings.
FLOOR FRAME KITS
MODELS FB47410, FB5465, FB106-A
FB109-A and FB1014-A
A simple new floor frame system made of heavy-duty, hot-dipped galvanized
steel. Use as base for plywood, sand or stone.
ATTIC KIT / WORKBENCH KIT
Model No. AT101
Heavy-duty galvanized steel bars that fi t all 10′ (3,0 m) wide Arrow
buildings. They install quickly and easily to help organize space and create
more useable space as an attic or workbench. Will hold up to 250 lbs.
(113 kg) evenly distributed.
Some drilling required to fi t buildings without mid-wall bracing.
SHELF UNITS
Heavy-duty, galvanized steel shelf units help organize storage space. They
easily mount on the wall or sit on the floor. Fits all Arrow buildings.*
Model No. SS404
- Makes 8″ to 12″ (20,3-30,5 cm) wide shelves in any length.
- Brackets, braces, hardware included. Lumber is not included.
- Some drilling required to fi t buildings without mid-wall bracing.
Model No. SS900-B
- Grey color
- 3 shelves
- Holds up to 85 lbs. (38 kg) (even weight distribution)
ORDERING ACCESSORIES….
We recommend that you purchase accessory items from your local storage
building dealer whenever possible; however, because the full line of
accessories is not always available from all dealers, Arrow is offering them
to you on a direct basis. There are two ways to order Arrow Storage Building
Accessories:
Option 1
Accessories can be purchased through arrowsheds.com
Option 2
Order accessories by telephone using your MasterCard or Visa credit card.
Call toll free 1-800-851-1085
(Customer Service).
Allow 2 weeks for delivery.
SPECIAL NOTE:
If your accessory is shipped via truck line a day time phone number is
required to arrange delivery. If no one is available to sign for the delivery,
you may be subject to a re-delivery charge assessed by the carrier.
Base
The Base For Your Building
No matter which of the options below you choose for a base, an ARROW ANCHORING
KIT is recommended as an effective method of properly securing your building
after assembly is complete.
OPTION 1: Directly on ground (earth)
Assemble your building directly on level ground (grass, dirt, rock, sand,
etc.). If you choose this option Arrow has a simple kit available to provide a
floor inside the shed to keep stored items off the ground. This kit can be used
to support a plywood floor (wood not included) or be filled with sand/rock to
provide a solid surface. (Order No. FB5465) Allow 1 – 2 hours for
construction.
OPTION 2: Wood Platform
If you decide to build your own base, be sure to select the appropriate
materials.
These are the recommended materials for your base:
-
2 x 4’s (38 mm x 89 mm) Pressure Treated Lumber
-
5/8″ (15,5 mm) 4 x 8 (1220 mm x 2440 mm) Plywood-exterior grade NOTE: Pressure Treated Lumber must not be used where it will make contact with your storage building. The properties of Pressure Treated Lumber will cause accelerated corrosion.
If Pressure Treated Lumber comes in contact with your storage building your warranty will be voided. -
10 & 4 penny Galvanized Nails Concrete Blocks (optional)
The platform should be level and fl at (free of bumps, ridges etc.) to provide
good support for the building. The necessary materials may be obtained from
your local lumber yard.
To construct the base follow instructions and diagram.
Construct frame (using 10 penny galvanized nails)
Measure 16″/24″ (40,6 cm/61,0 cm) sections to construct inside frame (see
diagram)
Secure plywood to frame (using 4 penny galvanized nails) Allow 6 – 7 hours for
construction.
Note: Platform/Slab will extend 9/16″ (1,4 cm) beyond floor frame on all
four sides. Seal this 9/16″ (1,4 cm) of wood with a roofing cement (not
included), or bevel this 9/16″ (1,4 cm) of concrete when pouring, for good
water drainage.
OPTION 3: Concrete Slab
The slab should be at least 4″ (10,2 cm) thick. It must be level and fl at to
provide good support for the frame.
The following are the recommended materials for your base.
- 1 x 4’s (19 mm x 89 mm) (will be removed once the concrete cures)
- Concrete Sheet of 6 mil plastic
- We recommend for a proper strength concrete to use a mix of:
1 part cement 3 parts pea sized gravel 2 1/2 parts clean sand
Prepare the Site/Construct a Base
- Dig a square, 6″ (15,2 cm) deep into the ground (remove grass).
- Fill up to 4″ (10,2 cm) in the square with gravel and tamp fi rm.
- Cover gravel with a sheet of 6 mil plastic.
- Construct a wood frame using four planks of 1×4 (19 mm x 89 mm) lumber.
- Pour in concrete to fi ll in the hole and the frame giving a total of 4″ (10,2 cm) thick concrete. Be sure surface is level.
Note: Finished Slab dimensions, with lumber removed.
Allow 3 – 5 hours for construction and a week for concrete curing time.
Anchoring
Anchoring Down The Building
It is important that the entire fl oor frame be anchored after the building is
erected.
Below are recommended ways of anchoring.
Arrow Anchoring Kit: (Model No. AK4 or 60298) Recommended for use with any
suggested base.
Contains: 4 Anchors with Cable, Clamps and installation instruction.
Arrow Anchoring Kit: (Model No. AK100 or 68383)
Recommended for use with the concrete base.
Contains: Corner gussets, perimeter clips, hardware, 1/4″ masonary drill
bit and installation instruction. Anchoring into Wood/Post:
Use 1/4″ (6 mm) Wood Screws. There are 1/4″ (6 mm) dia. holes provided in the
frames for proper anchoring.
Anchoring into Concrete:
-
For poured concrete slab or footing or patio blocks:
Use 1/4″ x 2″ (6 mm x 51 mm) Lag Screws. -
For Anchor Post of Concrete poured after building is erected: Use 1/4″ x 6″ (6 mm x 152 mm) Lag Screws.
Hardware
Remove from bag of screws and save for the last step
Parts List
Assembly Key No.| Assembly Part Part Number| Part Quantity
Description| Quantity in Carton| Quantity Check List
---|---|---|---|---
1| 9403| Front Floor Frame| 1|
2| 9914| Rear Floor Frame| 1|
3| 9907| Rear Wall Angle| 1|
4| 9396| Door Track| 1|
5| 5997| Left Gable| 2|
6| 5996| Right Gable| 2|
7| 9402| Side Floor Frame| 2|
8| 5288| Corner Post| 4|
9| 9912| Side Wall Angle| 2|
10| 7311| Door Jamb| 2|
11| 9344| Siding Stud| 4|
12| 9911| Side Siding| 6|
13| 6658| Gable Brace| 2|
14| 9910| Rear Siding| 3|
15| 9913| Front Siding| 6|
16| 5964| Roof Beam| 1|
17| 5982| Roof Angle| 1|
18| 6442| Right Roof Panel| 2|
19| 6443| Left Roof Panel| 2|
20| 6869| Ridge Cap| 1|
21| 6015| Side Roof Trim| 2|
22| 10482| Right Door| 1|
23| 10482| Left Door| 1|
24| 10499| Horizontal Door Brace| 4|
25| 6657| Door Handle Brace| 2|
Assembly by Key No.
Step 1
Parts Needed For
9396 Door Track (1)
Door Track Assembly
The door track assembly supports the sliding doors and reinforces the front
wall.
Hint: The holes in the top side of the door track are for fastening the
gable to the top of the front wall in a later step.
- Position door slides onto the legs, from the end of door track, as shown in the end view.
- Set this piece aside for later use.
Step 2
Parts Needed For
Floor Frame
- 9403 Front Floor Frame (1)
- 9914 Rear Floor Frame (1)
- 9402 Side Floor Frame (2)
- Assemble the four corners of the floor frame using two screws at each corner as shown. At the front corners fasten bolts through from the bottom with nuts on top.
- Measure the floor frame diagonally. When the diagonal measurements are equal, the floor frame is square. NOTE
If using a wood platform or concrete slab do not fasten the floor frames to your base at this time. You will anchor the building after it is erected. The floor frame must be square and level or holes will not align.
Step 3
BH16
NOTE
The remainder of the building assembly requires many hours and more than one
person. Do not continue beyond this point if you do not have enough time to
complete the assembly today. A partially assembled building can be severely
damaged by light winds. The top frame pieces give rigidity to the side walls
and provide a surface for attaching the gables which support the roof.
-
Position corner posts at the corners of the fl oor frame as shown. Fasten the corner post to the fl oor frame with 2 screws.
Support the corner posts with stakes or other devices until door jambs are attached. -
Fasten the door track assembly (holes on top) behind the top of the front corner posts using 1 screw in each corner. See the fi gure.
-
Fasten the rear wall angle behind the top of the rear posts using 2 screws in each post.
-
Fasten the side wall angles behind the top of the side posts using 2 screws in each corner. Side wall angles overlap rear wall angel in corners.
The floor frame must be square and level or holes will not align.
Step 4
BH17
Parts Needed For
Door Jambs/Studs
- 7311 Door Jamb (2)
- 9344 Siding Stud (4)
The door jambs reinforce the door opening and provide an attractive trim. The studs provide a surface for attaching the siding panels.
- Fasten the top of the door jambs to the door track with 2 screws. Do the same for the bottom into frame. Notched edge faces toward center of building. Fasten middle hole on inside edge of door jamb with a bolt inside building and a hex nut with an acorn nut outside, as shown.
- Place a stud between each corner post at the sides of building and 2 studs between corner posts at the rear. Position stud inside top angle and fasten with a screw at the lower hole.
- Rest bottom tab (large hole) outside floor frame. Do not fasten tab at this time. Repeat procedure for the remaining studs around the building.
Step 5
BH18
Parts Needed For
Side Siding
9911 Side Siding (6)
Each screw in the wall requires a washer.
- Slide side siding into channels of corner posts, flat edge upward, bottom edge down resting on fl oor frame. Always follow this pattern. Fasten bottom edge and tab of stud to floor frame using a screw. Fasten center to stud with screws. Do not fasten flat edge yet.
- Install side siding as before. Note how the slot in bottom edge must overlap flat edge of last siding. Fasten both siding panels to stud at this overlap.
- Install side siding to the top as before.
- From inside building, fasten sid- ing to corner posts using screws.
- Repeat steps 1 through 4 for opposite side of building.
NOTE
Be careful to install the correct panel in each position as shown. The floor frame must be square and level or holes will not align.
Step 6
BH19
Parts Needed For
Rear/Front Siding
- 9910 Rear Siding (3)
- 9913 Front Siding (6)
- Slide rear siding into channels of corner posts fastening to rear frame as shown in previous Step.
- Install rear siding to complete rear wall. Fasten top center of last siding to rear angle.
- Slide front siding into channels of corner post and door jamb. This siding is fastened from the inside, using screws into post and jamb.
- Install front siding to complete both front sections.
Step 7
BH20
Parts Needed For
Gables/Braces
- 5996 Right Gable (2)
- 5997 Left Gable (2)
- 6658 Gable Brace (2)
The gables go on top of the front and rear walls to support the roof beams.
NOTE
The gables are packed nested together and might be mistaken as one piece.
Carefully separate them before continuing.
- Lift and fasten a right and left gable, under angle at corner, to the door track with screws.
- Join the left and right gables together with a gable brace using a bolt in the bottom 2 holes.
Repeat Steps 1 & 2 for the opposite side of building.
Step 8
BH21
Parts Needed For
Roof Beam/Angle
-
5964 Roof Beam (1)
-
5982 Roof Angle (1)
- Fasten the roof beam, small holes on top, to the gable brace of the front gable.
- Fasten the other end of the roof beam to the gable brace of the rear gable.
- Fasten the roof angle to the roof beam as shown using screws.
Step 9
BH22
Parts Needed For
6442 Right Roof Panel (1)
Right Roof Panel
Installing the roof panels is best done with a step ladder. Begin
installing roof panels at the back right corner of the building. Each screw
and bolt in the roof requires a washer.
NOTE
Measure the building diagonally again and make adjustments to make sure the
building is square and level. This will make the roof panels fi t better, and
holes will align. Don’t anchor the floor frame.
NOTE
If a Roof Beef-Up Kit was purchased, assemble prior to attaching the roof
panels.
- Locate the roof panels by their numbers and place them on the ground alongside the building in their proper positions.
- Position the right roof panel at the back right corner and fasten to the gable and roof beam using screws and bolts as shown. Do not fasten the lower end of the panel to the side wall angle at this time.
Hint: Follow the fastener sequence shown, for proper alignment.
Step 10
BH23
- Parts Needed For
- 6443 Left Roof Panel (1)
Left Roof Panel
- Install a left roof panel at the left rear corner of the roof.
Step 11
BH24
- Parts Needed For Front of Roof
- 6443 Left Roof Panel (1)
- 6442 Right Roof Panel (1)
-
Cover the joint at the peak with weather stripping tape. Unroll the tape and press it down over the opening at the ridge as you install each roof panel. Do not cut the tape at this time.
-
Install a left and right roof panel in the sequence and positions shown in Step 9. Follow fastener sequence and instructions in Steps 9 thru 11 while fastening roof panels. Fasten overlap at center of roof panel rib using a bolt and nut.
NOTE
Narrow roof panel rib (with bead on it) is always overlapped by wide rib of adjacent panel -
Unroll the weather stripping tape, press it down fi rmly, and cut it.
-
Fasten the lower end of the panels to the side wall angles using screws and washers.
NOTE
If roof beam holes do not line up with the roof panel holes, shift the
building from left to right. If this does not help, your building may not be
level. Shim the corners until holes line up.
Step 12
BH25
Parts Needed For
Ridge Cap/Roof Trim
- 6869 Ridge Cap (1)
- 6015 Side Roof Trim (2)
- Install the ridge cap on the completed roof section using bolts and nuts.
- Fasten the roof panel rib, peak cap and ridge cap together using bolts and nuts. Fasten the remaining peak cap in the same manner.
- Attach the side roof trim to the lower end of the roof panels on each side of the building using screws at each panel overlap.
- Using your thumb and index finger, overbend the bottom flange of the side roof trim at the corner inward enough so the right and left roof trim caps fi t onto right and left corners.
- Fasten the roof trim caps to the side trim using a screw.
Step 13
BH26
Parts Needed For
Door Assembly
- 6657 Door Handle Brace (2)
- 10482 Right and Left Doors (2)
- 10499 Horizontal Door Brace (4)
The steps on this page tell how to assemble the right door. You will perform exactly the same procedures for the left door. Each screw and bolt in the door requires a washer. Proceed as follows:
- Attach the door handle brace and handle to the door with 1 bolt as shown. Don’t tighten the bolt yet.
- Swing the door handle brace up to the hole on the opposite side of the door and insert a bolt and nut.
- Insert a second bolt in the door handle and tighten both bolts.
- Put a horizontal door brace onto the top edge and bottom edge.
- Attach the lower door guides and bolts as shown.
- Repeat steps 1 through 5 for the left door.
Step 14
Parts Needed For
Door Installation & Adjustment
- Right Door Assembly (1)
- Left Door Assembly (1)
-
From inside the building, put the bottom of the right door assembly (on your left when you are inside the building) behind door jamb into the front frame track.
-
Position the top of the door so that that holes in the door line up with the holes in the door slides.
-
Fasten the door to the door slides using two #10Bx1/2″ (13 mm) screws per door slide.
NOTE
The holes in the door slides allow you to adjust the doors. Place the door in the middle holes. -
Repeat steps 1 through 3 for the left door.
Keep this Owner’s Manual and Assembly Instructions for future reference.
ED65 GD65-B WR65
Anchoring and Floor Frame
Anchoring
Anchor your building at this time.
Floor Frame
If you have purchased a Floor Frame Kit you need to install it at this time.
SOME FACTS ABOUT RUST
Rusting is a natural oxidizing process that occurs when bare metal is exposed
to moisture. Problem areas include screw holes, unfi nished edges, or where
scrapes and nicks occur in the protective coating through normal assembly,
handling and use. Identifying these natural rusting problem areas and taking
some simple rust protection precautions can help to stop rust from developing,
or stop it quickly as soon as it appears.
- Avoid nicking or scraping the coating surface, inside and out.
- Use all the washers supplied. In addition to protecting against weather infiltration, the washers protect the metal from being scraped by the screws.
- Keep roof, base perimeter and door tracks free of debris and leaves which may accumulate and retain moisture. These can do double damage since they give off acid as they decay.
- Touch up scrapes or nicks and any area of visible rust as soon as possible. Make sure the surface is free of moisture, oils, dirt or grime and then apply an even fi lm of high quality touch-up paint.
Documents / Resources
|
ARROW ED65 Woodridge Metal Shed
Kit
[pdf] Owner's Manual
ED65 Woodridge Metal Shed Kit, ED65, Woodridge Metal Shed Kit, Metal Shed Kit,
Shed Kit, Kit
---|---
|
ARROW ED65 Woodridge Metal Shed
Kit
[pdf] Owner's Manual
ED65 Woodridge Metal Shed Kit, ED65, Woodridge Metal Shed Kit, Metal Shed Kit,
Shed Kit, Kit
References
- Arrow Storage Products | Durable and Affordable Metal Sheds and Metal Carports
- Manual-Hub.com – Free PDF manuals!
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>