SCHIER GB-500 100 GPM Grease Interceptor Instruction Manual

June 16, 2024
SCHIER

**SCHIER GB-500 100 GPM Grease Interceptor Instruction Manual

**

SPECIAL PRECAUTIONS

For Schier Grease Interceptor Installations – Failure to follow this guidance voids your warranty
WARNING! DO NOT AIR TEST UNIT OR RISER SYSTEM! Doing so may result in property damage, personal injury or death.
CAUTION! Do not install this unit in any manner except as described in these instructions.

Installation Instructions

Installation instructions and additional components are included with the interceptor. Read all instructions prior to installation. This interceptor is intended to be installed by a licensed plumber in conformance with all local codes.

**When Installing Interceptor Inside

** If your dishwashing sink(s) discharges into a floor drain/sink (drain), you must regulate the flow into the drain to avoid an overflow of water onto the kitchen floor. This can be done by installing a valve or flow restriction cap on the sink piping that discharges into the drain.
See drawing for guidance. For detailed guidance on indirect connections, go to : webtools.schierproducts.com/Technical_Data/Indirect_Connections.pdf

Hydrostatic Slabs (or Pressure Slabs)
When installed under a hydrostatic slab (slab designed to withstand upward lift, usually caused by hydrostatic pressure) interceptor must be enclosed in a watertight concrete vault.

**High Temperature Kitchen Water

** If water is entering the interceptor at excessive temperature (over 150º F), a drain water tempering valve (DTV) and approved backflow prevention assembly must be installed. Most state and local plumbing codes prohibit water above 150º F being discharged into the sanitary sewer. Water above 150º F will weaken or deform PVC Schedule 40 pipe, poly drainage fixtures like interceptors and erode the coating of cast iron (leading to eventual failure).

Below Grade Installation Slab Requirements
A concrete slab to finished grade with rebar is required when installing interceptor below grade.

High Water Table Installations

Interceptors and risers are not designed to withstand water table height in excess of the top of the unit when buried (see figure). If it is possible for this to occur, install the interceptor and risers in a water-tight concrete vault or backfill with concrete or flowable fill (wet concrete and flowable backfill should be poured in stages to avoid crushing the interceptor).
At risk areas include but are not limited to tidal surge areas, floodplains and areas that receive storm water. Great Basin™ models that are direct buried in high water table scenarios must be installed with an anchor kit. Model GB-500 uses model AK1 anchor kit

**Above Grade Installation Support (for Model GB-500 Only

** The wet weight of the interceptor combined with high temperature kitchen water creates the potential for tank deformation when installed above grade. Model GB-500 installed above grade must be installed with Above Grade Support Kit model AGS2 to maintain structural integrity

Fully Support Base of Unit

Install unit on solid, level surface in contact with the entire footprint of unit base; for suspended installations design trapeze to support the wet weight of the unit.
Do not partially support unit or suspend unit using metal U-channel to create a trapeze.

**Support Inlet and Outlet Piping

** For above grade installations ensure heavy inlet and outlet piping (such as cast iron or long runs) is properly supported or suspended during the entire installation process to prevent connection failure or damage to bulkhead fittings.

DO NOT COMPACT BACKFILL

GETTING TO KNOW THE GB-500

  1. Pickable Cast Iron Cover (standard)
  2. Cover Gasket
  3. Safety Star (x2)
  4. Safety Star Tether (x2)
  5. Cover Adapter (x2)
  6. Cover Adapter Gasket Assembly(x2) with Upper and Lower Stainless
  7. Steel Band Clamps
  8. Bulkhead Connection Retaining Nut
  9. Bulkhead Connection Gasket
  10. 4″ Cleanout Plug (x2)
  11. Flow Control Cartridge (>13′ below kitchen only)
  12. Inlet Diffuser
  13. Inlet Diffuser Retaining Nut
  14. Inlet Diffuser Foot Retaining Nut
  15. Inlet Diffuser (Foot)
  16. Inlet Bulkhead Connection (standard) 4″ FPT
  17. 4″ Plain End Fitting (x2)
  18. 3″ Plain End Fitting (x2) (optional)
  19. Composite Cover Bolts and Washers (x8)
  20. Bolted Composite Cover (optional)
  21. Air Relief/Visual Access
  22. Outlet Diffuser Retaining Nut
  23. Outlet Diffuser
  24. Outlet Bulkhead Connection (optional) 4″ FPT (x2)
  25. Outlet Bulkhead Connection (standard) 4″ FPT
  26. 7/16″ Nut Driver Bit

BURIED INSTALLATION

Special Precautions

  1. Install interceptor as close as possible to fixtures being served

  2. Provide at least 16″ clearance above unit for routine maintenance.

      1. Max Water Level
        Risers are not designed to retain water

Test tank for water tightness

Cap all connection points with 4″ cleanout plugs using pipe thread sealant or tape approved for use with plastics.

Remove covers. For base unit testing fill with water to just above the highest connection.
Inspect unit, connections and gaskets for leaks. Check water level at specific time intervals per local code.

Leak?
Call customer care at 913-951-3300 8a – 5p M – F CST

Set Up Outlet Diffuser and Install Cleanout Plugs

Remove safety star insert, leave tethered to unit.

Unscrew diffuser retaining nut and remove outlet diffuser.

Rotate diffuser toward chosen outlet, insert and hand tighten retaining nut.

Cap all unused connection points with 4″ cleanout plugs using pipe thread sealant or tape approved for use with plastics.

Install Flow Control

Note to Plumbing Inspector
This interceptor includes certified internal flow control and does not require a dedicated “Flow Control Vent” (air intake).
Flow control is not pre-installed on this unit.

  • If dimension “A” is 13 feet or less no flow control is needed, go to Step 5, Excavate Burial Pit.
  • If dimension “A” in Figure 1 is more than 13 feet, or a high flow/increased head pressure condition exists, follow Steps below.

UNITS WITH 4″ DIFFUSERS

Remove safety star insert and remove flow control cartridge from the parts bag

200 GPM Installation Only: Cut off bottom of flow control cartridge at marked line.

Slide flow control cartridge into top of inlet diffuser and rotate clockwise until cartridge drops onto flow control retainer pins.
Continue rotating clockwise until pins are fully seated.

OPTIONAL: For easy flow control removal in deep burial installations, 1-1/2″ PVC SCH. 40 pipe may used as an extension handle. Before risers have been installed, cut pipe to length and attach to top of flow control cartridge using PVC primer/cement.

OR 35 UNITS WITH 6″ DIFFUSERS
Install flow control plate on the inlet bulkhead fitting prior to connecting piping and burial. Fasten plate to bulkhead fitting using supplied screws. Holes in plate must line up with pre-drilled holes in bulkhead fitting and grooved side of plate must face the unit.

Excavate Burial Pit

Excavate hole at least 18″ larger than interceptor on all sides and 12″ deeper than tank bottom.

Lay a level bed of well-packed, crushed aggregate (approximately 3/4″ size rock or sand, with no fines) in the base of hole.

Connect Piping

Screw plain end fittings (included) into bulkhead fittings using pipe thread sealant or tape approved for use with plastics. 6″ connection types come pre- installed from the factory.

Lower unit into pit and set level. Mechanically couple inlet and outlet drainage lines to unit. Do not solvent weld. Ensure all upstream fixtures are trapped. Vent per local code. Installation of 2-way cleanout tees to grade (by others) is recommended.

Wet or Air Test Piping Per Local Code

WARNING! DO NOT AIR TEST UNIT OR RISER SYSTEM! Doing so may result in property damage, personal injury or death. Leak? Call customer care at 913-951-3300 8a5p M-F CST

Bring Covers Flush-to-Grade

The GB-500 is ready for burial depth of 49-1/2″ from finished grade to bottom of tank (or 10-1/2″ to centerline of inlet).
Deeper burials will require extending the Cover Adapters and possibly adding risers.Measure dimension X to determine riser height needed.

Riser Height Needed Risers Required
0″ – 4″ None (use adapter
>4″ – 34″ FCR2 (x2)
>34″ – 64″ FCR2 (x4)
>64″ – 94″ FCR2 (x6)

Install risers if required (see instructions included with FCR2).

Loosen the Cover Adapter Upper Band Clamp using 7/16″ Nut Driver Bit.

Adjust Cover Adapter heights as needed.
Maintain a minimum 2-1/2″ insertion depth.

Tighten Upper Band Clamp to 5 -8 ft. lbs. of torque using 7/16″ Nut Driver Bit.
If required, Cover Adapters may now be tilted up to 10º in any direction using gasket flexibility

Backfill and Finished Grade

Fill unit with water for stabilization and float-out prevention.
Backfill evenly around tank using crushed aggregate (approximately 3/4″ size rock or sand with no fines)or flowable fill. Do not compact backfill around unit.

Pour concrete slab to finished grade

8c1

Vehicular Traffic Areas:
Minimum 8″ thick concrete slab with rebar required. Thickness of concrete around covers to be determined by specifying engineer. If traffic loading is required the concrete slab dimensions shown are for guideline purposes only. Concrete to be 28 day compressive strength to 4,000 PSI. Use No. 4 rebar (ø 1/2″) grade 60 steel per ASTM A615: connected with tie wire. Rebar to be 2-1/2″ from edge of concrete and spaced in a 12″ grid with 4″ spacing around access openings.

Pedestrian Traffic or Greenspace Areas:
Minimum 4″ thick concrete slab with rebar required.

ON THE FLOOR INSTALLATION

Special Precautions

  1. ODOR ALERT!
    Do not install air gap on outlet side of interceptor

  2. ODOR ALERT!
    Interceptor is not a sewer gas trap.
    All upstream fixtures must be trapped

  3. Install interceptor as close as possible to fixtures being served

  4. Provide at least 16″ clearance above unit for routine maintenance.

Test tank for water tightness

Cap all connection points with 4″ cleanout plugs using pipe thread sealant or tape approved for use with plastics.

Remove covers. For base unit testing fill with water to just above the highest connection.
Inspect unit, connections and gaskets for leaks. Check water level at specific time intervals per local code.

Leak?
Call customer care at 913-951-3300 8a – 5p M – F CST

Set Up Outlet Diffuser and Install Cleanout Plugs

Choose outlet location.

Remove safety star insert, leave tethered to unit.

Unscrew diffuser retaining nut and remove outlet diffuser.

Rotate diffuser toward chosen outlet, insert and hand tighten retaining nut

Cap all unused connection points with 4″ cleanout plugs using pipe thread sealant or tape approved for use with plastics.

Install Flow Control

Note to Plumbing Inspector
This interceptor includes certified internal flow control and does not require a dedicated “Flow Control Vent” (air intake).
Flow control is not pre-installed on this unit.

  • If dimension “A” is 13 feet or less no flow control is needed, go to Step 5, Connect Piping.
  • If dimension “A” in Figure 1 is greater than 13 feet, or a high flow/increased head pressure condition exists, follow Steps below.

UNITS WITH 4″ DIFFUSERS

Remove safety star insert and remove flow control cartridge from the parts bag

200 GPM Installation Only: Cut off bottom of flow control cartridge at marked line.
Slide flow control cartridge into top of inlet diffuser and rotate clockwise until cartridge drops onto flow control retainer pins.
Continue rotating clockwise until pins are fully seated.

UNITS WITH 6″ DIFFUSERS

Install flow control plate on the inlet bulkhead fitting prior to connecting piping and burial. Fasten plate to bulkhead fitting using supplied screws. Holes in plate must line up with pre-drilled holes in bulkhead fitting and grooved side of plate must face the unit.

Connect Piping

4″ Plain End
Screw plain end fittings (included) into bulkhead fittings using pipe thread sealant or tape approved for use with plastics. 6″ connection types come pre- installed from the factory.

Floor Below Installation Detail
Mechanically couple inlet and outlet drainage lines to unit. Do not solvent weld. Ensure all upstream fixtures are trapped. Vent per local code.

Install AGS2 Above Grade Support Kit (sold separately)

The wet weight of the interceptor combined with high temperature kitchen water creates the potential for tank deformation when installed above grade. Model GB-500 installed above grade must be installed with Above Grade Support Kit model AGS2 to maintain structural integrity. Refer to installation instructions included with AGS2.

Wet or Air Test Piping Per Local Code

WARNING! DO NOT AIR TEST UNIT OR RISER SYSTEM!
Doing so may result in property damage, personal injury or death. Leak? Call customer care at 913-951-3300
8a – 5p M – F CST

INSTALLATION OPTIONS

High Water Table Installations, See Anchor Kit Model AK2

Deadmen Anchoring:
If the installation location is in a high water table area or at risk are (including but not limited to tidal surge areas, floodplains and areas that receive storm water) the GB-500 must be secured to concrete deaden anchors (by others) using Schier model AK2 anchor kit.

Series Installations

For lower flow rates and higher grease storage requirements. Piping between units and two-way cleanout tees by others.
Below grade installations: All units must be level in the excavation pit. Note that downstream units must be buried 2″ deeper than the adjacent, upstream fixture. Two-way cleanout tees extended to finished grade should be installed before the first unit inlet, after the last unit outlet and in between units (if there is a long run of pipe between units) for line cleaning purposes.
NOTE: When the flow control cartridge is required, it should only be installed on the first unit in the series.
Top View of 4 GB-500 Units Piped in Series
Side View of 3 GB-500 Units Piped in Series

No. of Units in Series Removal Efficiency

100 GPM
95.3%
2| 6,096 lbs
3| 9,144 lbs.
4| 12,192 lbs.

References

Read User Manual Online (PDF format)

Read User Manual Online (PDF format)  >>

Download This Manual (PDF format)

Download this manual  >>

Related Manuals