Schier Products SV24-O Wastewater Sampling Port Installation Guide
- June 15, 2024
- Schier Products
Table of Contents
INSTALLATION GUIDE SV24-O Wastewater Sampling Port Lifetime Guaranteed Grease Interceptors
SPECIAL PRECAUTIONS
For Schier SV24 Sampling Port Installations – Failure to follow this guidance
voids your warranty
WARNING DO NOT AIR TEST UNIT OR RISER SYSTEM!
Doing so may result in property damage, personal injury or death.
CAUTION Do not install this unit in any manner except as described in
these instructions.
Installation Instructions
Installation instructions and additional components are included with the
interceptor.
Read all instructions prior to installation. This interceptor is intended to
be installed by a licensed plumber in conformance with all local codes.
Install sampling port as close as possible to and downstream from interceptor
being served
Provide at least 16″ clearance above unit for routine maintenance. Above Grade
Installation Additional Support
To prevent connection failure or damage to fittings, ensure heavy inlet and
outlet piping (such as cast iron or long runs) is properly supported or
suspended during entire installation process.
Above grade installations must be supported by a platform or trapeze (not
included) that contacts the entire footprint of the unit. Composite cover
C24BC is recommended for use in above grade installations.
DO NOT USE CAST IRON COVERS IN ABOVE GRADE OR INDOOR INSTALLATIONS Use
composite cover C24BC only for above grade installations ODOR ALERT!
Sampling port is not a sewer gas trap. All upstream fixtures must be trapped
Below Grade Installation Slab Requirements
A concrete slab to finished grade with rebar is required when installing
sampling port below grade.
GETTING TO KNOW THE SV24-O
1. Pickable Cast Iron Cover (standard)
2. Cover Gasket
3. Safety Star
4. Safety Star Tether
5. Cover Adapter
6. Cover Adapter Gasket Assembly with Upper and Lower Stainless Steel Band
Clamps
7. Flow Distributor Body| 8. Bulkhead Connection Retaining Nut
9. Bulkhead Connection Gasket
10. Inlet Bulkhead Connection
4″ FPT (x2)
11. 4″ Plain End Fitting (x3)
12. Outlet Bulkhead Connection 4″ FPT
13. Composite Cover Bolts and Washers (x4)
14. Bolted Composite Cover (optional)
15. 7/16″ Nut Driver Bit
---|---
-
Excavate Burial Pit Excavate hole at least 12″ larger than sampling port on all sides and 6″ deeper than port bottom. Lay a level bed of well-packed, crushed aggregate (approximately 3/4″ size rock or sand, with no fines) in the base of hole.
-
Connect Piping
2a Install plain end fittings
Screw plain end fittings (included) into bulkhead fittings using pipe thread sealant or tape approved for use with plastics. 2b Connect sampling port to drain lines Place unit into final position and set level. Mechanically couple inlet and outlet drainage lines to unit. Do not solvent weld. Ensure all upstream fixtures are trapped. Vent per local code. -
Install Above Grade Support (by others)
To prevent damage to drain line connections, SV24-O above grade installations must be supported by a structure (not included) built on-site. The support structure may be a platform or trapeze that contacts the entire footprint of the sampling port and is able to hold the weight of the unit. -
Bring Covers Flush-to-Grade
The SV24-O is ready for burial depth of 22″ from finished grade to bottom of unit (or 12-1/4″ to centerline of inlet).
Deeper burials will require extending the Cover Adapter and possibly adding risers.
Loosen the Cover Adapter Upper Band Clamp using 7/16″ Nut Driver Bit. Adjust Cover Adapter heights as needed. Maintain a minimum 2-1/2″ insertion depth. Tighten Upper Band Clamp to 5 -8 ft. lbs. of torque using 7/16″ Nut Driver Bit. If required, Cover Adapters may now be tilted up to 10º in any direction using gasket flexibility. -
Backfill and Finished Grade Backfill evenly around tank using crushed aggregate (approximately 3/4″ size rock or sand with no fines)or flowable fill. Do not compact backfill around unit.
5b Pour concrete slab to finished grade
Vehicular Traffic Areas:
Minimum 8″ thick concrete slab with rebar required. Thickness of concrete
around covers to be determined by specifying engineer. If traffic loading is
required the concrete slab dimensions shown are for guideline purposes only.
Concrete to be 28 day compressive strength to 4,000 PSI. Use No. 4 rebar (ø
1/2″) grade 60 steel per ASTM A615: connected with tie wire. Rebar to be
2-1/2″ from edge of concrete and spaced in a 12″ grid with 4″ spacing around
access openings.
Pedestrian Traffic or Greenspace Areas:
Minimum 4″ thick concrete slab with rebar required.
SV24-O Installation Guide
MODEL NUMBER:
DESCRIPTION: Wastewarer Sampling Port
SV24-O
PART #: 8062-003-03
DATE: 01/01/2023
REV:
ECO:
6455 Woodland Dr.
Shawnee, KS 66218 913-951-3300
schierproducts.com
© Copyright 2023 Schier
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>