SSW MOU 9 Chop Saw
Product Information
Product Name: Extruder One
Training Date: [Training Date]
Product Usage Instructions
-
Before operating the machine, ensure that a safety check has
been completed and signed off. If not, contact a Manager or setter
before switching the machine on. -
Before starting the change, make sure the heat temperatures are
running at the set value. Purge out a small amount of ABS before
extraction. -
Crack the 4, 16mm Allen bolts on the head and remove them. This
will release the ring and heater band attached to the head. Remove
the thermocouple and the plug attached to the heater band. Place
the ring on the floor to cool, being careful not to damage the
heater band or thermocouple. -
Loosen off the 4, 19mm bolts attached to the head using the
Allen key and bar supplied. This will release the die. Undo the
16mm Allen bolt on the inside of the core to release it from the
spider. Ensure gloves and arm bands are used. -
Remove the die and core from the spider and take them to the
workbench. Use the brass tools supplied to remove any existing ABS
from the die. Ensure gloves and arm bands are used. -
Insert the next core and attach it to the spider using the 16mm
Allen key and bar. Insert the next die into the head and attach it
using the heater band and the 4, 16mm bolts. Once tight, tighten
the 4, 19mm bolts on the head. Insert the plug into the heater band
and wait for 1.5 hours for the die/core to heat. Ensure gloves and
arm bands are used. -
Do not use the machine unless trained and authorized by a
Manager.
Confirmation
I have received the above training and fully understand every
point that was explained to me. I confirm that I will wear the
required PPE equipment when using the above machinery and take all
steps to ensure my own safety. I will ask for further training if
needed and will immediately inform the Supervisor or Manager if
there are any issues with the machinery.
Name: [Name]
Signed: [Signature] Date: [Date]
I confirm that I have trained the aforementioned person and that
they fully understand how to use the above machinery, have received
the required PPE equipment, and know to inform me immediately of
any issues with the machinery or if they require further training.
I authorize this person to use the machinery detailed above.
Name: [Authorized Trainer]
Signed: [Signature] Date: [Date]
SSW MOU 9 06.01.16
Safet System of Work OPERATING AND SAFETY INSTRUCTIONS FOR DIE AND CORE CHANGE
ON
EXTRUDER ONE
Name: ……………………………………………………….. Training Date:……………………………..
Instruction
1 Explain that safety equipment must be used at all times and why safety
boots must be used at all times when running machines
Understood or X
2 Before operating a machine clarify that safety check has been completed and
signed off, if not see a Manager or setter before switching the machine on.
3 Before starting the change make sure the heat temperatures are running at
set value, purge out small amount of ABS before extraction.
4 Crack the 4, 16mm Allen bolts on the head, remove these from the head, this
will release the ring and heater band attached to the head, remove the
thermocouple and the plug attached to the heater band, place the ring on the
floor to cool.be careful not to damage the heater band or thermocouple.
5 Loosen off the 4 , 19mm bolts attached to the head, using allen key and bar
supplied, this will release the die, undo the 16mm allen bolt on the inside of
the core , this will release the core from the spider. GLOVES AND ARM BANDS
MUST BE USED.
6 Remove die and core from spider take these to the work bench and remove any
existing ABS from the die using brass tools supplied. GLOVES AND ARM BANDS
MUST BE USED.
7 Insert next core and attach this to the spider using the 16mm allen key and
bar, insert next die into the head attach this using the heater band and the
4, 16mm bolts once tight, the 4, 19mm bolts on the head need to be tightened,
insert plug into heater band THEN WAIT 1.5 HOURS for the die/core to heat.
GLOVES AND ARM BANDS MUST BE USED.
8 Do not use any machine unless trained and authorised by Manager.
I have received the above training and fully understand every point that was
explained to me. I confirm that I will wear the required PPE equipment when
using the above machinery and take all steps to ensure my own safety. I will
ask for further training if I need to and will immediately inform the
Supervisor or Manager if there are any issues with the machinery.
Name: ………………………………………………………………………………………………………….
Signed: ……………………………………………………………….. Date:…………………………………
I confirm that I have trained the aforementioned person and that they fully
understand how to use the above machinery, have received the required PPE
equipment and know to inform me immediately of any issues with the machinery
or if they require further training. I authorise this person to use the
machinery detailed above.
Name: ………………………………………………………………………………….(Authorised Trainer)
Signed …………………………………………………………………… Date: ……………………………