invt 100kW 400V 3ph 9MMPT Solar On Grid Inverter Installation Guide

September 7, 2024
invt

invt 100kW 400V 3ph 9MMPT Solar On Grid Inverter

Product Information

Specifications

  • Product Name: XG8K Export Limitation
  • Model: SOP
  • Compatibility: Single and Multiple Inverter Systems

Product Usage Instructions

Single Inverter Export Limitation Installation
Follow these steps for installing the export limitation on a single inverter:

  1. Take the two red pin terminals and place them onto the CT wire ends.
  2. Thread the CT cable through the COM connector, connecting the white/black wire(CT+) to Pin 5 and the black wire(CT-) to Pin 6.
  3. Connect the COM connector to the inverter, clamp the CT on the L wire of the main power cables, ensuring the arrow logo of the CT points towards the load and inverter.

Multiple Inverter Export Limitation Installation
For installing export limitation on multiple inverters:

  1. Set different addresses for each inverter as per the user manual.
  2. Connect the CT only to the inverter with Address 1 (Master).
  3. Connect all inverters through RS485 cables to ensure communication with the master inverter.

FAQ

  • Q: Where should the CT be installed?
    A: The CT must be installed on the L wire of the main power cables before load and inverter(s).

  • Q: How should the pin terminals be connected?
    A: The white/black wire(CT+) should be connected to Pin 5, and the black wire(CT-) should be connected to Pin 6 of the COM connector.

  • Q: How to ensure safe installation?
    A: Disconnect both DC & AC connections before installing the CT to avoid any risk of electric shock.

System Diagrams

Warning: DISCONNECT both DC & AC connections before install the CT. Otherwise there will be risk of electric shock.

Notes:

  1. The CT must be installed on L wire of the main power cables before load and inverter(s).
  2. The arrow of the CT has to be pointing towards the load and the inverter(s).
  3. The CT has to be connected to Pin 5(CT+: White/Black or Red) and Pin 6(CT-: Black) on the COM connector of Inverter side.
  4. The Inverters have to be set to different addresses in FIG.2, and the CT only needs be connected to the inverter with Address 1(Master). Other inverters communicate with the Master via Pin 3(T/R+) and Pin 4(T/R-).

Bill of Materials

Installations

Installation of single inverter export limitation

  1. Take the two red pin terminals and placethem onto the CT wire ends as shown in the left picture below, and use pincer pliers to crimp the pin terminals.
  2. Thread the CT cable through the COM connector as shown in the left picture below, the white/black wire(CT+) is connected to Pin 5, and the black wire(CT-) is connected to Pin 6 of the connector. Then buckle the COM connector.
  3. The COM connector is connected to the inverter, the CT is clamped on theL wire of themain power cables before all of the loads and the inverter, and the internal arrow logo of the CT is targeted at the direction of the load and the inverter. At this point, the installation is completed.

Installation of mutiple inverter export limitation

  1. Set different addresses to the inverters, for example 1, 2, 3…n as per its user manual.
  2. The CT only needs to be connected to the inverter with Address 1(Master).
  3. All the inverters have to be connected through RS485 cables hand by hand to make sure they can communicate with the master inverter.

Parameter Settings

LCD Settings

  1. LCD basic operations

  2. Enable/Disable Export Limitation

  3. Step 1
    Long-press on “DOWN” to enter setting menu and choose “admin option”

  4. Step 2
    Input 00000 or 13156 to enter “admin option”

  5. Step 3
    Press “DOWN” and choose anti-current, then long press “DOWN” to enter this menu

  6. Step 4
    Choose Single or Multiple and long press “DOWN” to confirm

  7. Step 5
    In “anti current” menu, you may choose “input allow anti” which means the power that’s allowed to export to the grid. 0.0KW means zero export is allowed.

  8. Step 6
    In “anti current” menu, there is CT Ratio option in which you may set a value as per your CT Specification.

APP Settings

  • IMPORTER: Prima Group 2004 LTD, Bulgaria, 1784 Sofia, Mladost 1, bl. 144, Ground Floor; Phone: +359 2 988 45 72;