“`html
Product Specifications
- Model: LG4 Series LED Wall Mounts / Accessory
- Compatibility: TILD1X3LG4, TILD1X4LG4, TILD1X5LG4, TILVAB2
- Weight Capacity: 20 lbs (9.07 kg) per LED panel
Product Usage Instructions
Installation Instructions
The LG4 Series LED Wall Mounts are designed for use with LED
panels only. It is crucial to follow the below steps for safe and
proper installation:
Step 1: Identify Configuration
Determine the appropriate configuration based on your
application. Refer to the model numbers provided in the manual for
guidance.
Step 2: Mounting System Setup
Assemble the primary Chief product (Mounting System) following
the provided instructions.
Step 3: Attach Accessory
Attach the secondary Chief product (Accessory) to the Mounting
System. Ensure it is securely attached.
Step 4: Mount LED Panels
Mount LED panels on the LG4 Series Wall Mounts, making sure not
to exceed the weight capacity of 20 lbs per panel.
Step 5: Safety Precautions
Follow all safety instructions provided, including not using the
mounting system outdoors and returning damaged systems for
repair.
Frequently Asked Questions (FAQ)
Q: Can I use the LG4 Series Wall Mounts for non-LED
panels?
A: No, the LG4 Series Wall Mounts are specifically designed for
use with LED panels only. Using other types of panels may result in
damage or personal injury.
Q: What should I do if I exceed the weight capacity of the LED
panels?
A: Exceeding the weight capacity can result in serious injury or
equipment damage. Do not attach LED panels that exceed 20 lbs (9.07
kg) to the LG4 Series Wall Mounts.
Q: Are there any specific tools required for installation?
A: Yes, you will need a small level and drill bits of sizes
7/32, 3/8, and 1/2 for proper installation.
“`
INSTALLATION INSTRUCTIONS
(Standard three-upright configuration shown for each model. Configuration will
vary based on application)
TILD1X4LG4-L
TILD1X4LG4-M TILD1X4LG4-R
TILD1X3LG4-L
TILD1X3LG4-M TILD1X3LG4-R
TILD1X5LG4-M TILD1X5LG4-L TILD1X5LG4-R
TILVAB2 Accessory
LG4 Series LED Wall Mounts / Accessory
Spanish Product Description German Product Description Portuguese Product
Description
Italian Product Description Dutch Product Description French Product
Description
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
Installation Instructions
DISCLAIMER
Legrand | AV and its affiliated corporations and subsidiaries (collectively
“Legrand | AV”), intend to make this manual accurate and complete. However,
Legrand | AV makes no claim that the information contained herein covers all
details, conditions or variations, nor does it provide for every possible
contingency in connection with the installation or use of this product. The
information contained in this document is subject to change without notice or
obligation of any kind. Legrand | AV makes no representation of warranty,
expressed or implied, regarding the information contained herein. Legrand | AV
assumes no responsibility for accuracy, completeness or sufficiency of the
information contained in this document.
Chief® is a registered trademark of Legrand AV Inc.
DEFINITIONS
MOUNTING SYSTEM: A MOUNTING SYSTEM is the
primary Chief product to which an accessory and/or component is attached.
ACCESSORY: AN ACCESSORY is the secondary Chief
product which is attached to a primary Chief product, and may have a component
attached or setting on it.
COMPONENT: A COMPONENT is an audiovisual item
designed to be attached or resting on an accessory or mounting system such as
a video camera, CPU, screen, display, projector, etc.
WARNING: The TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 LED wall mounts are designed
for use with LED panels only. Exceeding the weight capacity (listed) can
result in serious personal injury or damage to equipment! Do NOT attach LED
panels to TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 LED video wall mounts that
exceed 20 lbs (9.07 kg) regardless of the size or design of the configuration.
See figure below for examples.
TILD1X3LG4 (example)
TILD1X4LG4 (example)
ONE LED PANEL 20 lbs (9.07 kg) maximum
WARNING: A WARNING alerts you to the possibility of serious injury or death if you do not follow the instructions.
CAUTION: A CAUTION alerts you to the possibility of damage or destruction of
equipment if you do not follow the
corresponding instructions.
ONE LED PANEL 20 lbs (9.07 kg) maximum
IMPORTANT SAFETY INSTRUCTIONS
WARNING: Failure to read, thoroughly understand, and follow all instructions
can result in serious personal injury, damage to equipment, or voiding of
factory warranty! It is the installer’s responsibility to make sure all
mounting systems are properly assembled and installed using the instructions
provided.
WARNING: Use this mounting system only for its intended use as described in
these instructions. Do not use attachments not recommended by the
manufacturer.
WARNING: Never operate this mounting system if it is damaged. Return the
mounting system to a service center for examination and repair.
WARNING: Failure to provide adequate structural strength for this mounting
system can result in serious personal injury or damage to equipment! It is the
installer’s responsibility to make sure the structure to which this mounting
system is attached can support five times the combined weight of all
equipment. Reinforce the structure as required before installing the mounting
system. The wall to which the mounting system is being attached may have a
maximum drywall thickness of 5/8″ (1.6cm). Do not install drywall anchors into
the seam between drywall pieces.
2
WARNING: Do not use this mounting system outdoors.
IMPORTANT ! : The TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 LED wall mounts are
designed to be mounted to:
· a bare 8″ concrete or 8″x8″x16″ concrete block wall; or · a 3/4″ thickness
plywood-backed, 2″ x 4″ wood studs
(16″ on center minimum) wall with a maximum drywall thickness of 5/8″; or · a
3/4″ thickness plywood-backed, steel stud wall covered with drywall having a
maximum thickness of 5/8″.
–SAVE THESE INSTRUCTIONS–
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
LEGEND
Tighten Fastener Apretar elemento de fijación Befestigungsteil festziehen
Apertar fixador Serrare il fissaggio Bevestiging vastdraaien Serrez les
fixations
Loosen Fastener Aflojar elemento de fijación Befestigungsteil lösen Desapertar
fixador Allentare il fissaggio Bevestiging losdraaien Desserrez les fixations
Phillips Screwdriver Destornillador Phillips Kreuzschlitzschraubendreher Chave
de fendas Phillips Cacciavite a stella Kruiskopschroevendraaier Tournevis à
pointe cruciforme
Open-Ended Wrench Llave de boca Gabelschlüssel Chave de bocas Chiave a punte
aperte Steeksleutel Clé à fourche
By Hand A mano Von Hand Com a mão A mano Met de hand À la main
Hex-Head Wrench Llave de cabeza hexagonal Sechskantschlüssel Chave de cabeça
sextavada Chiave esagonale Zeskantsleutel Clé à tête hexagonale
3
Installation Instructions
Pencil Mark Marcar con lápiz Stiftmarkierung Marcar com lápis Segno a matita
Potloodmerkteken Marquage au crayon
Drill Hole Perforar Bohrloch Fazer furo Praticare un foro Gat boren Percez un
trou
Adjust Ajustar Einstellen Ajustar Regolare Afstellen Ajuster
Remove Quitar Entfernen Remover Rimuovere Verwijderen Retirez
Optional Opcional Optional Opcional Opzionale Optie En option
Security Wrench Llave de seguridad Sicherheitsschlüssel Chave de segurança
Chiave di sicurezza Veiligheidssleutel Clé de sécurité
Installation Instructions
TOOLS REQUIRED FOR INSTALLATION
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
[Small level]
7/32″ 3/8″ 1/2″
[Laser level]
String M3
2
PARTS
3/4″ deep well socket
Ratchet or T-handle for use with deep well socket
Mounting Hardware Kit (Qty per bag) TiLDUS Hardware Kit (Qty per bag)
Level [4+ ft. long]
A – Left (1)
C (2) [UX10x60R anchor]
F (6) #10 x 1/2″
G (3) 1/4-20 x 1/2″
or
B – Right (1) [Adjustment washers]
D (2) 5/16 x 2-1/2″
H (1) [Keeper bracket] TILVAB2 Vertical Connector Kit [Sold separately]
E (2) 5/16″
J (8) 1/4-20 x 1/2″ K (2)
[Vertical connector] Spacer Plate Kit (Qty per bag) (not included
w/TILD1xXLG2-R or TILD1xXLG3-R)
P (2) [Spacer plate]
Q (8) #10-24 x 1/2″
L (1)
[Left upright –
M (1)
TILD1X3LG4-L-shown] [Middle upright –
N (1) [Right upright –
TILD1X3LG4-M shown] TILD1X3LG4-R-shown]
R (2) #8 x 2″
4
Installation Instructions
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
INSTALLATION
Preinstallation IMPORTANT ! : Reference the LED screen installation manual for
specific instructions regarding care, handling, cabling and installation of
the LED screens.
CAUTION: Handle the LED screens with care, being careful to not impact or drop
the LED screen.
CAUTION: There is a magnetic surface on the front of the LED screen. To
prevent damage ensure that no metallic object is pulled onto the LED screen.
NOTE: When planning the installation, remember the requirement to run power
and signal to the video wall.
Site Assessment
Before beginning any installation the site should be assessed in several areas
to help avoid any issues during the actual installation.
· Wall Structure – It is recommended that a 3/4″ furniture-grade plywood-
backed wall be used in most LED video walls. The use of a wood stud wall is
not appropriate since the studs won’t be in the proper location for an LED
video wall.
· Wall High/Low Points – Locate any high or low points on the wall that may
cause problems, and try to set up install so that these points can be avoided,
if possible.
· Flatness/Plumb of Wall – Learn how much depth adjustment will be needed
across the LED video wall mounting area.
· Power/Cable – Locate all power outlets and cable access holes that need to
be cleared by the installation. Plan appropriately for those holes.
· Installing in a Recess – Verify the level and squareness of the recessed
area. Since these areas are rarely perfect you may need to decide what to use
as a reference point. · The recess top or bottom may not be level so the video
wall may need to be installed to align with the recess, rather than being
level with the wall. · If the recess is not square the sides may make the
recess look crooked. If possible, the recess should be fixed. If repairing the
recess isn’t an option it may be best to “split the difference” between the
recess sides to make the video wall appear level.
· Where to Begin the Video Wall – The installer should make the decision
whether the video wall will be started at the top, bottom, left, right or
center. · If a lower bottom reference is given in the specifications, it may
make sense to start at the bottom of the video wall to ensure that this
specification is met from the start of installation. · If building inside of a
recess, it may be easier to start in the center of the space since the video
wall will most likely need to be centered within the recess.
· Vertical Connector Brackets – If creating a video wall with more than a
single row, you will be using the vertical connectors which are sold
separately. · Vertical Connector Brackets [sold separately] If the video wall
requires multiple rows, decide on whether the installation will start with the
top or
bottom row. This determines to which end (top or bottom) the vertical
connector brackets are attached.
Just a tip – For larger LED walls it is helpful to
check placement and alignment of the mounts by putting a few cabinets without
the LED’s in place in the bottom row of the installed mounts (referencing the
LED screen installation manual for specific instructions) during the mount
installation, verifying that everything is staying aligned and level, and then
continuing the mount installation.
Just a tip – The horizontal slots located along
the vertical mount pieces (and vertical slots located along the horizontal
mount pieces) are the center-of-screen indicators to illustrate where the
center of each LED screen will be located, and can be used to hold a tape
measure tab while measuring. (See Figure 1)
[TILD1X3LG4 shown as example]
Center of screen indicators
Tape
Measure
= Center-of-screen indicators = Slots to hold tape measure blade
Figure 1
5
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
Determining Installation Site
IMPORTANT ! : The top of the LED screen is 5.75″ above
the center line of the mounting lags in the upper mounting
(L)
slots. (See Figure 2)
IMPORTANT ! : The bottom of the LED screen is 6.25″
below the center line of the mounting lags in the lowest
mounting slots.
NOTE: Refer to dimensions drawings on pages 18-22 and in Figure 2 for further details on installation locations.
(TILD1X3LG4 shown as example)
BACK VIEW
Installation Instructions
2
(Q)
(M)
Figure 3 3. Hang spacer plates (P) onto screws loosely installed in Step
2. (See Figure 4) 4. Tighten Phillips undercut machine screws (Q) to secure
left
upright (L) to spacer plate (P). (See Figure 4) (L)
Figure 2
Installation to Wall
NOTE: If desired, the mount installation may be started in the middle of the
video wall, attaching mounts out from the center to the left and right ends.
Installation on smaller walls may be easier if started at the left side of the
video wall using the following instructions.
IMPORTANT ! : Installation of video wall should begin with installation of the
lowest row of mounts first. 1. Determine location for the bottom left corner
of the LED
wall. (See Figure 2) 2. Loosely install #10-24 x 1/2″ Phillips undercut
machine
screws (Q) into uprights (L, M or N) that will be attached to spacer plate
(P). (See Figure 3)
6
3
4 3
(Q) x 2 (P)
Figure 4
Installation Instructions
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
5. Hang middle upright (M) or right upright (N) onto side of spacer plate (P) using screws loosely installed in Step 2. (See Figure 5)
6. Tighten screws holding uprights (L, M or N) to spacer plate (P). (See Figure 5)
(M)
6
(Q) x 4
7
keyhole slot center line
(P) x 2
(P) 5
5
Figure 5 7. Make a mark at the centerline for the horizontal spacer
brackets based on the mount height. Refer to drawings on pages 18-20 for the
distance from the spacers to the bottom of the display. (See Figure 6) 8.
Using a level, mark horizontal lines across width of LED wall from the marks
made in Step 7. (See Figure 6) 9. Hold mount section up to wall, lining up
keyhole slot with line drawn in Step 8. (See Figure 6) NOTE: This line will
indicate the center line for the location of the
spacers used to mount the video wall uprights. 10. Use #8 x 2″ Phillips
drywall screw (R) to secure spacer
plates (P) to wall. Use a level to make sure spacers are level before
tightening screws. (See Figure 6)
9
(R) x 2
Figure 6
Adding Vertical Connector Kit (Sold Separately) NOTE: If more LED screens will
need to be added to the top or
bottom of the screen configuration, add TILVAB2 vertical connector kit to top
or bottom of wall mount using the following instructions. If you are NOT
adding the TILVAB2 connector kit, proceed to Installing First Mount section.
IMPORTANT ! : It is easier to install the vertical connector kit BEFORE the
mounts are attached to the wall. However, it can also be installed after the
mounts are attached to the wall. 1. Add the vertical connector (K) to the top
or bottom of the
mount, and fasten with four 1/4-20 x 1/2″ Phillips pan head screws (J) per
vertical connector (K). (See Figure 7)
2. Partially install two 1/4-20 x 1/2″ Phillips pan head screws (J) into top
or bottom screw holes on connectors (K). (See Figure 7)
2
(J) x 2
(K) x 2
1
(J) x 4
Figure 7 7
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
Installation Instructions
Installing First Mount to Wall
The TILD1X3LG4 / TILD1X4LG4 /TILD1X5LG4 LED wall mounts are designed to be
mounted to the following wall types:
Table 1: Fastener Information
WALL TYPE
Drywall attached to plywoodbacked walls Steel/Wood studs
Concrete or concrete block
PILOT FASTENERS (see PARTS HOLE drawing)
7/32″ x 3″
– 5/16 x 2-1/2″ flanged hex head lag (C)
– 5/16″ washer (D)
– Adjustment washer (A)
3/8″ x 3″
– 5/16 x 2-1/2″ flanged hex head lag (C)
– 5/16″ washer (D)
– Adjustment washer (A)
– Fischer Anchor UX10x60R (B)
4. Drill two pilot holes (see Table 1 for size) at each location marked in Step 2 (See Figure 8) and follow fastener information located in Table 1.
IMPORTANT ! : Refer to Fastener Installation Methods (located in Appendix at
end of Installation Instructions) for details on installing product into
various wall types. 5. Install two lag screws (C) into wall, but do NOT
completely
tighten to wall. (See Figure 9) NOTE: (OPTIONAL) If more LED screens need to
be added to
the top or bottom of the screen configuration, add TILVAB2 vertical connector
kit (not included) to top or bottom of wall mount following instructions in
the (OPTIONAL) Adding Vertical Connector Kit. If you are NOT adding the
TILVAB2 connector kit, proceed to Step 5.
(TILD1X3LG4 shown)
5
(C) x 2
1. Hold furthest left wall mount section against wall ensuring that mounting
slot is lined up with center line marked on the wall in Determining
Installation Site section. Doublecheck with a level. (See Figure 8)
2. Mark mounting holes near top or mounting slots along the horizontal line.
(See Figure 8)
3. The mounting holes are 17.48″ apart on-center for left and middle and
23.62″ for middle and middle and 22.64 for middle and right. (See Figure 8)
NOTE: Mark and drill pilot holes near top of mounting slots for maximum height
adjustment.
17.48 inches
Figure 9 6. Slide the left (A-Left) and right (A-Right) adjustment washers
into place behind and partially install lag screws. (See Figure 10)
2
3
Line showing center of
mounting slots
for mounts in LED
Figure 8
8
A (left)
A (right)
6 6
Figure 10
Installation Instructions
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
7. Place a level across front of the mount at bottom of leveling slots. (See
Figure 11)
8. Check the level of the mount at the bottom of the leveling slots. (See
Figure 11)
7 Level
Mount 8 leveling
slots
11. Check the level of the mount horizontally at the bottom of the leveling
slots and vertically on the side of the uprights. (See Figure 11) and (See
Figure 12)
12. If the mount is not level, slide or use a dead blow hammer to lightly tap
the spacer into place. This will lift the mount up as the lag screw rides in
the washer’s angled slot. (See Figure 12)
Just a tip – Tighten down the lag screw on the
side that does NOT need to be raised. This creates a pivot point for when the
opposite adjustment washer is tapped into place, and allows that correct side
of the mount to move up.
13. Tighten the bottom lag screws (C) to allow for leveling adjustment if needed later. (See Figure 13)
Vertical Level
11
13
(C) x 2
12 Dead blow hammer
Figure 11 9. Drill pilot holes near top of centerline of lower slots for
maximum height adjustment (see Table 1 for size) and follow fastener
information (appropriate for wall type) located in Table 1. (See Figure 12)
10. Loosely install 5/16 x 2-1/2″ lag screws (C) through the 5/16″ fender
washers (D) to secure to wall. (See Figure 12)
11 Level
11 Horizontal
Level
Figure 13 14. Remove #8 x 2″ Phillips drywall screws (R) from wall after
mount has been leveled. (See Figure 14)
(D) x 2
10
(C) x 2
9
x 2
Figure 12
14 Figure 14
(R) x 2
9
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
Adding Additional Uprights
1. Hang spacer plate (P) onto lower screws installed in previous section on
middle upright (M). (See Figure 15)
2. Tighten both screws (Q) to secure spacer plate (P) to middle upright (M).
(See Figure 15)
NOTE: Add uprights (M) or (N) one by one from left to right as the mounting
system is being built on the wall.
(TILD1X3LG4 shown) (M)
Installation Instructions
(M or N) 3
(Q) x 2 6
(TILD1X3LG4 shown) (M)
(P)
4
5
1 (P)
1
2 tighten Figure 15
3. Partially install two #10-24 x 1/2″ Phillips flathead screws (Q) into
middle two holes on middle upright (M) or right upright (N). (See Figure 16)
4. Insert two partially installed screws (Q) into holes on opposite side of
spacer plate (P). (See Figure 16)
5. Lower upright until screwed are properly seated in keyhole mounting holes.
(See Figure 16)
6. Tighten two screws to secure spacer plate to mounting upright (M) or (N).
(See Figure 16)
4 5
Figure 16
NOTE: (Optional) Drywall screws (R) may be used to keep the spacer (P) level
as the upright is being attached.
7. Mark mounting hole in top mounting slot along the horizontal line marked
in Step 3 of Installing First Mount Section. (See Figure 17)
NOTE: The mounting holes are 23.62″ apart on-center for middle (M) and middle
(M) or 22.64″ apart on-center for middle (M) and right (N) uprights. (See
Figure 17)
23.62 inches (middle to middle)
22.64 inches (middle to right) (M)
(N)
Line showing
8
9
center of
mounting slots
for mounts in LED
Figure 17 8. Drill two pilot holes (see Table 1 for size) at each location
marked in Step 8 (See Figure 17) and follow fastener information (appropriate
for wall type) located in Table 1.
10
Installation Instructions
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
9. Hold the adjustment washers in place by hand and tighten the fasteners at
the top of the mount.
10. Drill lower pilot holes at attachment locations and use same fasteners
used at top of mount.
11. Install two fasteners and fender washers (D) through lower part of mount
and tighten.
IMPORTANT ! : For larger LED walls it is helpful to check placement and
alignment of the mounts by putting a few LED housings in place in the bottom
row of the installed mounts (referencing the LED screen installation manual
for specific instructions) during the mount installation, checking alignment
before removing the housings, and then continuing the installation. IMPORTANT
! : Continually recheck the alignment and overall flatness of the wall mounts
during the installation process.
12. Continue the installation process until all wall mounts are attached. Use
a magnetic level on front face of outside uprights to make sure they are
plumb. Use a 3/4″ or 19mm socket wrench to adjust hex nuts as needed. (See
Figure 21)
Connecting Mounts Above First Row
1. Lower additional uprights (L, M or N) onto installed uprights, placing
grooves at bottom of uprights over partially installed screws (J) on connector
kit. (See Figure 18)
4. Position spacer plate (P) between uprights (L, M or N) middle upright (M)
between mounting holes. (See Figure 19)
5. Use four 1/4-20 x 1/2″ Phillips flathead screws (Q) to secure uprights (L,
M or N) to each other. (See Figure 19)
(TILD1X4LG4 shown) (M)
5
(Q) x 4
((P)
3
(J) x 2
1
2
(J) x 2
Figure 18
Figure 19
NOTE: Drywall screws (R) do NOT need to be used when installing upper rows
they only need to be used when installing the bottom row.
6. Repeat Steps 4-5 for each spacer plate on the row.
WARNING: Be sure to hold upright (L, M or N) up against wall until screw is
installed in Step 2!
2. Install remaining 1/4-20 x 1/2″ Phillips pan machine screws (J) into hole
above partially installed screws. (See Figure 18)
3. Tighten partially installed screw (J) to secure additional upright to
existing upright. (See Figure 18)
NOTE: Add uprights (M) or (N) one by one from left to right as the mounting
system is being built on the wall.
NOTE: Spacer plates may be attached prior to installing uprights depending on
installer preference.
11
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
Installation Instructions
7. Mark mounting hole in top mounting slot along the horizontal line marked
in Step 3 of Installing First Mount Section. (See Figure 20)
NOTE: The mounting holes are 23.62″ apart on-center for middle (M) and middle
(M) or 22.64″ apart on-center for middle (M) and right (N) uprights. (See
Figure 20)
23.62 inches (middle to middle)
22.64 inches (middle to right) (M)
Depth Adjust using String Line
1. Install #10 x 1/2″ self-tapping screws (H) on the mount in the far left
and far right uprights to assist in plumb leveling. (See Figure 21)
2. Run a string between the self-tapping screws installed in Step 13 to
assist with alignment across long sections of mounts. (See Figure 21)
3. Turn hex nuts in either direction on far left and far right uprights to
assist in plumb leveling. (See Figure 21)
4. Turn hex nuts in either direction on each middle upright to adjust depth
to match the string line as needed. (See Figure 21)
(N)
Line showing
8
9
center of
mounting slots
for mounts in LED
Figure 20
8. Drill two pilot holes (see Table 1 for size) at each location marked in
Step 8 (See Figure 20) and follow fastener information (appropriate for wall
type) located in Table 1.
9. Drill two pilot holes (see Table 1 for size) at each location marked in
Step 7 (See Figure 20) and follow fastener information (appropriate for wall
type) located in Table 1.
10. Hold the adjustment washers in place by hand and tighten the fasteners at
the top of the mount.
11. Drill lower pilot holes at attachment locations and use same fasteners
used at top of mount.
12. Install two fasteners and fender washers (D) through lower part of mount
and tighten.
13. Continue installing uprights across and level as shown in initial
uprights installation section.
14. Repeat steps found in Installing First Mount to Wall Section to install
all additional rows to wall.
IMPORTANT ! : Installation of adjustment washers (A) is unnecessary when
adding additional rows above first row. Only install lag screws (C) and fender
washers (D) into top mounting holes.
12
Installation Instructions
1 Circles indicate tapping screw hole locations for attaching string to assist
with alignment of mounts. Use locations nearest depth adjustment points for
best results.
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
[TILD5X5LG4 shown as example]
Use locations nearest
1
(G) depth adjustment points
for best results.
3
4
[TILD5X5LG4 with multiple middle columns shown as example for using string to assist with alignment.]
33 44
Stwriin1thg25atoligansmsiestnt
Figure 21 13
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
Adjustments Depth Adjust
1. Remove LED housings from mounting system. 2. Turn 3/4″ hex nuts near feet
of mounting system to adjust
depth as needed. (See Figure 22) 3. Replace LED housings onto mounting system.
LED Panels
Installation Instructions
2
2
Figure 22 Installing Housings and LED Screens
WARNING: The TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 LED wall mounts are designed
for use with LED panels only. Exceeding the weight capacity (listed) can
result in serious personal injury or damage to equipment! Do NOT attach LED
panels to TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 LED video wall mounts that
exceed 20 lbs (9.07 kg) regardless of the size or design of the configuration.
IMPORTANT ! : Reference the LED screen installation manual for specific
instructions regarding care, handling, cabling and installation of the LED
housings and screens. NOTE: Begin the installation of the housings in the
lower left
corner of the video wall. NOTE: One complete row of housings should be
installed
before proceeding to the next row. NOTE: Panels may be moved in either
direction for better
access as the panels are being installed. NOTE: Make sure mounting buttons are
properly installed into
back of LED housings prior to installation to mounting system.
14
Begin LED housing install 1 in the lowest left corner of
2
the video wall
[TILD1X3LG4 wall shown as example]
Figure 23 1. Install the first LED housing in the lowest left-hand corner of
the video wall by aligning mounting buttons on the housing with the mounting
holes on the wall mount. (See Figure 23) 2. Move LED housing forward until all
four mounting buttons are through mounting holes in wall mount. 3. Continue
with the next housing (directly to the right of installed housing). NOTE: Be
sure to check the level and plumb of the housings
often during the housing installation. 4. After the second housing is
installed, push to the left until the
first and second housings are touching. 5. Repeat until all housings in a row
are installed. 6. After the first row is installed, install a column on the
far
sides to ensure the panels are perfectly perpendicular. (See Figure 24)
6 6
Figure 24 7. Fill in additional rows above by repeating Steps 2-5. 8. Using
levels, check the level and plumb of the housings
installed on the mounts and adjust as necessary following information in the
Adjustments section. 9. Connect housings following instructions included with
LED screens. 10. Install LED screens following instructions included with
screens.
Installation Instructions
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
Fastener Installation Methods
IMPORTANT ! : See Table 1 for appropriate hardware and pilot hole sizes for
various wall types. IMPORTANT ! : The expanse of the LED wall will most likely
mean that attachment of the wall mounts will not all be in studs. The
attachment method will most likely vary throughout the installation, and more
than one of the various methods outlined here will most likely be used.
Wood Stud/Steel Stud (w/plywood backing)
IMPORTANT ! : The TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 LED wall mounts are
designed to be mounted to a 3/4″ thickness plywood-backed, 2″ x 4″ wood studs
(16″ on center minimum) wall with a maximum drywall thickness of 5/8″ or a
3/4″ thickness plywood-backed, steel stud wall covered with drywall having a
maximum thickness of 5/8″.
1. Use one 5/16″ x 2-1/2″ hex flange head lag bolt (D) and one 5/16″ washer
(E) through product and into pilot hole. (See Figure 25)
2. Repeat for remaining pilot holes.
3. Repeat for remaining pilot holes.
1
(C)
(E)
2
(D)
Figure 26
(E)
1
(D)
2
Figure 25
Concrete or Concrete Block
IMPORTANT ! : The TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 LED wall mounts are
designed to be mounted to a bare 8″ concrete or 8″x8″x16″ concrete block wall.
- Install one UX10X60R anchor (C) into each pilot hole using
a hammer, making sure that the anchor is flush with the wall. (See Figure 26)
2. Use one 5/16″ x 2-1/2″ hex flange head lag bolt (D) and one 5/16″ washer (E) through product into each anchor in wall. (See Figure 26)
NOTE: 5/16″ washers (E) may not be necessary if using adjustment washers (A and B) to install to wall.
15
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
Installation Instructions
Site Requirements for Wood or Steel Stud Installation
*Steel stud ONLY
If back side of wall is unfinished, drywall must be installed
to a minimum of one stud left and right of the stud(s) being used to install
the mount. Drywall must be secured to studs with screws a maximum of 12″
(305mm) apart down center of stud.
16″ or 24″ (on center) Studs
There must be a minimum of 1-7/8″ (48mm) clearance inside wall
Plywood
FRONT
3/4″ minimum thickness plywood covered with drywall having maximum thickness
of 5/8″
5/8″ maximum drywall thickness (Both Sides of Stud)
Stud
Steel Stud (2 x 4 / 25ga minimum) Stud type and structural strength must
conform to the North American Specification for the Design of Cold-Formed
Steel Structural Members. [362 S 125 18, C-Shaped, S-Stud Section] Figure 27
16
Installation Instructions
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
Holder Bracket (Optional)
NOTE: For increased security, holder brackets (H) may be used to secure
displays to outer uprights (L or N).
1. After all displays and mounted and leveled, position holder bracket onto
top of outer upright (L or N). (See Figure 28)
(H)
1
Figure 28 2. Use four #10 x 1/2″ Phillips screws (F) to secure holder
bracket (H) to outer uprights (L or N). (See Figure 29)
2
(F) x 4
(H)
Figure 29 17
Installation Instructions
DIMENSIONS
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
FRONT VIEW
TIL1D1x3LG4
BACK VIEW
DIMENSIONS: INCHES [MILLIMETERS] 18
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
DIMENSIONS…cont’d
FRONT VIEW
Installation Instructions
TILD1x3LG4 (CONTINUED)
BACK VIEW
FRONT VIEW
TILD1x4LG4
DIMENSIONS: INCHES [MILLIMETERS] 19
Installation Instructions
DIMENSIONS (CONTINUED)
BACK VIEW
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
TILD1x4LG4 (CONTINUED)
3.80 96.4 MIN. DEPTH
4.55
115.5 MAX. DEPTH
FRONT VIEW
MOUNT SET UP FOR A SINGLE COLUMN
BACK VIEW
DIMENSIONS: INCHES [MILLIMETERS] 20
Installation Instructions
DIMENSIONS (CONTINUED)
FRONT VIEW
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
TILD1x5LG4
BACK VIEW
21
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
Installation Instructions
TILD1x5LG4
22
Installation Instructions
DIMENSIONS (CONTINUED)
A
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
TILVABP2
TILVAB2 KIT INCLUDES 2 BRACKETS AND HARDWARE
LOOSELY INSTALL THE REAR UPPER SCREWS
SLIDE UPPER MOUNT UPRIGHTS DOWN FROM THE TOP AND INSERT
THE FRONT LOWER SCREWS
DETAIL A SCALE 1 : 1
INSTALL VERTICAL ATTACHMENT BRACKETS AT THE TOP OF THE LOWER UPRIGHTS
IT IS EASIER IF THIS IS DONE PRIOR TO INSTALLING THE MOUNTS ON THE WALL
ALIGN THE FRONT FACES OF THE MOUNTS BY PLACING A LEVEL
ACROSS THE FRONT THEN TIGHTEN SCREWS
C B
DETAIL B SCALE 1 : 2
DETAIL C SCALE 1 : 2.5
DIMENSIONS: INCHES [MILLIMETERS] 23
TILD1X3LG4 / TILD1X4LG4 / TILD1X5LG4 / TILVAB2
Installation Instructions
8800-003408 Rev00 2023 Legrand | AV www.legrandav.com
01/2024
USA/International Europe Asia Pacific
A 6436 City West Parkway, Eden Prairie, MN 55344 P 800.582.6480 / 952.225.6000
F 877.894.6918 / 952.894.6918 A Franklinstraat 14, 6003 DK Weert, Netherlands
P +31 (0) 495 580 852 F +31 (0) 495 580 845 A Office No. 918 on 9/F, Shatin
Galleria
18-24 Shan Mei Street Fotan, Shatin, Hong Kong
P 852 2145 4099 F 852 2145 4477
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>