SUNGROW SH6.0RS 6kW Single Phase Hybrid Storage Inverter Installation Guide
- August 6, 2024
- SUNGROW
Table of Contents
- SUNGROW SH6.0RS 6kW Single Phase Hybrid Storage Inverter
- Safety
- Backup Wiring Diagram (For AU / NZ I ZA)
- Scope of Delivery
- Mounting location
- Installation tools
- Mounting
- Battery (Power)-Connector
- WiNet-S2/EyeM4
- COM (Meter, RS485, CAN, ORM)
- COM ( ORM)
- LED panel
- Read User Manual Online (PDF format)
- Download This Manual (PDF format)
SUNGROW SH6.0RS 6kW Single Phase Hybrid Storage Inverter
- Contents may be periodically updated or revised due to product development. The information in this guide is subject to change without notice. In no case shall this guide substitute for the user manual or related notes on the device.
- Make sure to read over, fully understand and strictly follow the detailed instructions of the user manual and other related regulations before installing the equipment. The user manual can be downloaded by visiting the website at http://support.sungrowpower.com/, or it can be obtained by scanning the QR code on the side of the equipment or the back cover of this guide.
- All operations can be performed only by qualified personnel, that must be trained for installation and commissioning of electrical system, as well as dealing with hazards, have knowledge of the manual and of the local regulations and directives.
- Before installation, check that the package contents are intact and complete compared to the packing list. Contact SUNGROW or the distributor in case of any damaged or missing components.
- The cable used must be intact and well insulated. Operation personnel must wear proper personal protective equipment (PPE) all the time.
- Any violation could result in personal death or injury or device damage, and will void the warranty.
Safety
The inverter has been designed and tested strictly according to international safety regulations. Read all safety instructions carefully prior to any work and observe them at all times when working on or with the inverter. Incorrect operation or work may cause:
- injury or death to the operator or a third party;
- damage to the inverter or other properties.
Please follow the safety instructions related to the PV strings and the utility grid.
DANGER
Lethal voltage!
- PV strings will produce electrical power when exposed to sunlight and can cause a lethal voltage and an electric shock.
- Only qualified personnel can perform the wiring of the PV panels.
NOTICE
Danger to life from electric shock due to lethal voltage!
- All electrical connections must be in accordance with local and national standards.
- Only with the permission of the local utility grid company, the inverter can be connected to the utility grid.
Inverter
The warning label on the inverter body are as follows.
Disconnect the inverter from all the external power sources before
maintenance!
Do not touch live parts for 10 minutes after disconnection from the power
sources.
Burn danger due to hot surface that may exceed 60 °C.
Danger to life due to high voltages!
Only qualified personnel can open and maintain the inverter.
Read the user manual before maintenance!
DANGER
Danger to life from electric shocks due to live voltage
- Do not open the enclosure at any time. Unauthorized opening will void warranty and warranty claims and in most cases terminate the operating license.
- When the enclosure lid is removed, live components can be touched which can result in death or serious injury due to electric shock.
Lethal danger from electric shock due to possibly damaged inverter
- Only operate the inverter when it is technically faultless and in a safe state.
- Operating a damaged inverter can lead to hazardous situations that can result in death or serious injuries due to electric shock.
WARNING
Risk of inverter damage or personal injury
- Do not pull out the PV connectors and AC connector when the inverter is running. Disconnect the AC circuit breaker and set the DC load-break switch of the inverter to OF F. Wait 10 minutes for the internal capacitors to discharge. Verify that there is no voltage or current before pulling any connector.
WARNING
All the warning labels and nameplate on the inverter body:
- must be clearly visible; and
- must not be removed, covered or pasted.
CAUTION
Risk of burns due to hot components!
- Do not touch any hot parts (such as the heat sink) during operation. Only the DC switch can safely be touched at any time.
NOTICE
Only qualified personnel can perform the country setting.
Unauthorized alteration may cause:
- A breach of the type-certificate marking.
Risk of inverter damage due to electrostatic discharge (ESD)!
By touching the electronic components, you may damage the inverter. For
inverter handling, be sure to:
- avoid any unnecessary touching; and
- wear a grounding wristband before touching any connectors.
Battery
DANGER
Batteries deliver electrical power, resulting in burns or a fire hazard when
they are short-circuited, or wrongly installed.
Lethal voltages are present in the battery terminals and cables in the
inverter. Severe injuries or death may occur if the cables and terminals in
the inverter are touched.
NOTICE
Improper settings or maintenance can permanently damage the battery.
Incorrect inverter parameters will lead to the premature aging of battery.
EU Declaration of Conformity within the scope of the EU directives
The object of the declaration described above is in conformity with the relevant Union harmonization legislation:
Low Voltage Directive 2014/35/EU (LVD)
Electromagnetic compatibility 2014/30/EU (EMC)
Restriction of the use of certain hazardous substances 2011/65/EU and
2015/863/EU (RoHS)
SUNGROW confirms herewith that the products described in this document are in
compliance with the fundamental requirements and other relevant provisions of
the abovementioned directives. The entire EU Declaration of Conformity can be
found at support.sungrowpower.com
The communication module that comes with the inverter and the technical
parameters of wireless communication are listed in the table below. The model
of the communication module actually delivered shall prevail. The EU
Declaration of Conformity for the communication module can be found at
support.sungrowpower.com
WiNet-S/WiNet-S2:
Radio technology WLAN 802.11b/g/n20/n40
Radio spectrum 802.11b/g/n20 2412 MHz-2472 MHz
Maximum transmission power 802.11n40 2422 MHz-2462 MHz
Technical parameters listed above apply to EU countries only. S20 dBm
Backup Wiring Diagram (For AU / NZ I ZA)
- Note1: If the battery is integrated with a readily accessible internal DC breaker, no additional DC breaker is required.
- The recommended values in the table are for reference only. The actual values must comply with local standard and actual conditions.
- The rated current of breaker 2 is suggested to lower than that of breaker 5 .
- If the rated current of on-site power cables are lower than those recommended above, the breakers specification should be considered to match the power cables in first priority.
- The AC port takes power from the grid and is set according to the grid circuit breaker.
Backup Wiring Diagram (For Other Countries)
Model | 1 | 2 | 3 | 4 | 5 | 6 7 | 8 |
---|---|---|---|---|---|---|---|
SH8.0-10RS | 63A/600V | ||||||
DC breaker* | ,;63A/230V/400V TypeC AC breaker | 63A/230V/400V TypeC AC breaker | |||||
Depends on loads | Depends on household loads and inverter capacity (Optional) |
30mARCD
(Recommended)| 300mARCD
(Recommended)
Note1: * If the battery is integrated with a readily accessible internal DC breaker, no additional DC breaker is required.
- The recommended values in the table are for reference only. The actual values must comply with local standard and actual conditions.
- The rated current of breaker 2 is suggested to lower than that of breaker 5 ·
- If the rated current of on-site power cables are lower than those recommended above, the breakers specification should be considered to match the power cables in first priority.
- The AC port takes power from the grid and is set according to the grid circuit breaker.
Backup Wiring Diagram (For TT system)
Model | 1 | 2 | 3 | 4 | 5 | 6 7 | 8 |
---|---|---|---|---|---|---|---|
SH8.0-1ORS | 63A/600V | ||||||
DC breaker* | 563A/230V/400V | ||||||
TypeC AC breaker | 63A/230V/400V | ||||||
TypeC AC breaker | Depends | ||||||
on loads | Depends on household loads and inverter capacity (Optional} | 30mARCD | |||||
(Recommended} | 300mA RCD |
(Recommended}
Note1: * If the battery is integrated with a readily accessible internal DC breaker, no additional DC breaker is required.
- The recommended values in the table are for reference only. The actual values must comply with local standard and actual conditions.
- The rated current of breaker 2 is suggested to lower than that of breaker 5 ·
- If the rated current of on-site power cables are lower than those recommended above, the breakers specification should be considered to match the power cables in first priority.
- The AC port takes power from the grid and is set according to the grid circuit breaker.
Scope of Delivery
• The images shown here are for reference. The actual product and quantity are
based on delivery.
•• Types of equipment to be applied vary in different regions. Please consult
local customer service for equipment type selection.
••• These accessories are included in the scope of delivery only in Australia
currently.
Mounting location
Installation tools
Mounting
Use appropriate mounting hardware for wall type.
Optimizer
-
Please ensure that the optimizer is installed facing the back of the module. Otherwise, the clip may be damaged.
-
Do not forcibly bend the clips when installing the optimizer by clips. Otherwise, the clip may be damaged.
-
Do not clamp the optimizer into holes in the module frame during installation. Otherwise, the optimizer cannot be removed or the clips may be damaged.
-
It is recommended to install optimizers on the same side of modules.
-
Do not clamp and remove the optimizer multiple times. Otherwise, the clip may become loose, affecting normal use.
PE
The cable specification must comply with local regulations (if available). Otherwise, keep it consistent with the PE wire in the AC cable.
AC
- If local standard have other requirements for cables, set the cable specification according to the local standard.
DC
Optimizer
Backup
The PE wire of Backup terminal is not required for Australia, New Zealand and
South Afric.
Battery (Power)-Connector
Refer to the instructions supplied by the battery manufacturer for the connections on the battery side and configuration.
There are two types of battery connectors, and the product received shall prevail.
WiNet-S2/EyeM4
-
Installation with WLAN communication
-
Installation with Ethernet communication
COM (Meter, RS485, CAN, ORM)
Label | Description |
---|---|
Meter (A2, B2) | For Smart Energy Meter |
BAT-CAN (H, L) | For Li-ion battery communication via CAN protocol. Detail |
battery information refer to inverter user manual.
RS485 (A1, B1)| For inverter daisy chain (Reserved)
For Li-ion battery communication via RS485 protocol. Detail information refer
to inverter user manual.
RSD (RSD-1, RSD-2)| Reserved (Detail availability contact SUNGROW)
RS485_2 (A3, B3)| For EV Charger communication via RS485 protocol.
Enable (EN_H, EN_G)| Enable the battery with a voltage of 12V.
Detail power specification refer to inverter user manual.
ORM (D1/5, D2/6, D3/7, D4/8, R, C)| For external Demand Response Enabling
Device (“AU”/”NZ”)
For Ripple Control Receiver
DO (COM1, COM2, N01, N02)| Reserved (Detail availability contact SUNGROW)
BAT-CAN (H, L)| For Li-ion battery communication via CAN protocol.
Detail battery information refer to inverter user manual.
- Take Smart Energy Meter connection as an example.
COM ( ORM)
Battery (Communication)
For the communication of battery that does not need to be enabled
Method 1
Method 2
EV-Charger (Communication)
Protective Cover Installation (Optional)
Power on
LED panel
- In normal state, the E-day, Pac and SOC information will be displayed alternately. Also you can
- In normal state, the C-ody. Pac and sue Inionation will be displayed dremdtely, Aiso you can touch the LED indicator to switch the information.
- In error state, touch the LED indicator to view multiple error codes.
- If there is no operation for 5 minutes, the display screen will be off. Touch the LED indicator to activate it.
- More information in the QR code or at http://support.sungrowpower.com/