COMMSCOPE FHD-H01K Rugged RPs Cables Installation Guide
- June 5, 2024
- CommScope
Table of Contents
- COMMSCOPE FHD-H01K Rugged RPs Cables Installation Guide
- Overview
- Cable handling
- Appendix E Cable installation and power separation guidelines
- Cable termination
- Appendix E Cable installation and power separation guidelines
- Cable splicing
- Cable termination
- Cable grounding
- Lightning protection
- Important guidelines
- Indoor box
- NOTE
- Outdoor protection
- Table E-1. CAT-6A protection equipment parts list
- NOTE
- Ceiling connector
- Patch panel
- Power separation guidelines
- Read More About This Manual & Download PDF:
- References
- Read User Manual Online (PDF format)
- Download This Manual (PDF format)
COMMSCOPE FHD-H01K Rugged RPs Cables Installation Guide
Overview
When installing Rugged RPs, cables that can withstand temperature extremes and inclement weather should be used. In outside environments, avoid contamination or damage to plugs. Plugs must be protected from sunlight and water in a suitable equipment housing or NEMA 4 rated box. It is also important to avoid exposure to water at cut ends of unfilled cables and cords. The following information is available to help you extend the operation of your RP and switches.
Cable handling
Indoor/outdoor cords can be routed outdoors above ground and indoors, and can
be ordered in lengths long enough for direct (home-run) installations from
switch to end equipment. Cords have 20% Insertion Loss De-rating so only 85
meters total can be supported. Extended lengths can be cut in two for
terminating the indoor ends at protectors or panels. Terminations are similar
to typical 4-pair indoor cables.
Unreel long lengths of cable to ensure the cable does not become twisted or
caught on objects.
CommScope recommends using a sock fitted and secured over the plug to pull
cable through long conduits. Sock information
Tie wrap information
Appendix E Cable installation and power separation guidelines
Feed the sock through the conduit and secure the sock on the terminal end of the cable with the tie-wrap. Once the sock and tie-wrap are in place, pull the cable through the conduit.
Cable termination
Before installing the Rugged RP, terminate the RP end of the Ethernet cable with the RJ45, IP67 connector provided in the box.
Flip the plug anti-snag to make it easier to push through the cord grips (flip it back before plugging in).
Appendix E Cable installation and power separation guidelines
Use the split grommet provided. Once it is in place, coat it with silicone to ensure the connector is sealed.
Cable splicing
Some cables are run in one piece from source to destination and have connector
terminations. In other cases, two shorter pieces of cable need to be spliced
together.
When a cable is run to outdoor devices, you should take measures to ensure
that cables are properly protected against moisture entering the cable. This
is especially important when the jacket is stripped back from the wires. Some
cables are gel filled and the termination includes cleaning the excess gel and
blocking the end with silicone sealant to prevent future leakage. A typical
blocking method uses a 2 cm length of Alpha Wire PVC-105-2 tubing or
equivalent.
-
Fill all space inside the tubing with B-sealant.
-
2 Position the filled tube to overlap the end of the inner jacket and seal the gel. Clean off all excess sealant.
NOTE: Tape can be used to stabilize the tube for immediate termination before the sealant sets.
Cable termination
Shielded cables must be properly terminated, either grounded or isolated. For
exposed installations requiring protection, the end of the shield can be
bonded in various ways.
The following procedure is an example of one method.
-
Make a slit along the length of the jacket. Be careful not to tear the underlying shielding.
-
Pull back the jacket along the slit and remove.
-
Fold back the foil shielding and drain wire to expose the inner jacket.
-
Prepare the inner jacket for blocking the gel and direct burial.
a Cut back the inner jacket
b Trim the flute
c Clean the excess gel
NOTE: The flute can be cut longer to match the blocking tube length. -
Fill all space inside the tubing with B-sealant and position the filled tube to overlap the end of the inner jacket and seal the gel.
-
Fold the drain wire and foil back over the tube and position the foil to be folded back over the tube.
-
An extra piece of foil can be used to cover the foil seam.
-
For an HGS620 termination, wrap the drain wire at least two times around and position it where the spring clips will capture them.
-
Tape over the foil for stability.
-
Trim the wire ends.
Cable grounding
For CAT-6A cables, the shield termination method is to use the ground lug and Bbond clip that are available in the 12A1 Grounding Kit.
-
Fold the foil back over the jacket end and wrap the drain wire around the end and push the ground lug over the wrap.
-
Open the B-bonding clip to be placed and closed over the grounding lug
-
The lug tail can be cut off or used for ground attachment.
-
Treat the inner jacket as described in step 4 on page E-7.
For an isolated shield termination, the 1572A and 1592A outer jacket foil and
drain wire are removed a short distance back from the termination and
electrical tape is used
to isolate the foil end.
Lightning protection
CommScope recommends including lightning protection in your OneCell system to isolate equipment from surge damage.
Important guidelines
- Verify hole diameter – blocking may need to remain outside the cover
- Maintain pair twists up to termination points
- Avoid having pairs crossing over each other
Indoor box
To protect the cables in an indoor installation from lightning damage, CommScope recommends using the ITW Linx CAT6-A-LAN protector.
NOTE
The gel filled outdoor cable types will still need blocking. See Cable splicing and Cable termination for instructions on blocking cable.
Outdoor protection
The following is an example of a pole mounted CAT-6A configuration for
protecting remote equipment installed outdoors.
Table E-1 lists the recommended parts for installing the protection equipment.
Table E-1. CAT-6A protection equipment parts list
Part Name | Link to Part on Distributor’s Web site |
---|---|
NEMA 4x enclosure | [Allied Moulded fiberglass |
enclosure](http://www.alliedmoulded.com/catalog/industrial-enclosures-and-
accessories/nonmetallic-enclosures/10x8-to-14x12-fiberglass-jic-
enclosures/am1084h/)
Back panel| Allied Moulded back panel
Ground buss| Ditek surge protection
buss
Bottom Mounted Liquid Tight Cordgrips| Heyco pre-assembled
cordgrips
Bottom Mounted Liquid Tight Bushing| Heyco liquid tight bushings – snap-
in
Protector| Ditek 110RJC6APOE
Protector
Pole mount kit| Allied Moulded pole mount
kit
Figure E-6. Remote equipment protection for outdoor devices
NOTE
Enclosure should be mounted close to the equipment for the best protection.
Figure E-7. Protector box mounted to pole
Ceiling connector
If surge protection is not needed, gel flooded cables can be blocked and transitioned to indoor cable using a ceiling connector. The following link is for the recommended CommScope part. Ceiling connector
-
Terminate the indoor cable first – then lay down a bed of B sealant.
-
Clean all gel from the end of the OSP cable.
-
After the cable and conductors are positioned, fill the area around the cable end with sealant and close the connector housing.
Patch panel
CommScope recommends installing a patch panel in the NOC to connect and manage
CAT-6A cables. The following is a list of recommended CommScope 24 and 48 port
patch panels and high density information outlets.
• 760163436_HFTP-HD6B-1U-24
• 760163444_HFTP-HD6B-2U-48
• 760163451_HFTPA-HD6B-1U-24
• 760163469_HFTPA-HD6B-2U-48
• 760163519_HFTP-J6
• 760163527_HFTP-J10G
For more information, go to CommScope.com or contact your CommScope customer
representative.
Power separation guidelines
For power separation best guidelines, refer to the following standards:
- Telecommunications Pathways and Spaces, TIA-569-C
- Information technology – Implementation and operation of customer premises cabling – Part 2: Planning and installation, ISO/IEC 14763-2
- Information Technology – Cabling Installation – Part 2: Installation Planning and practices inside buildings, BS EN 50174-2
Read More About This Manual & Download PDF:
References
- CommScope | now meets next
- Tubing | FIT® Wire Management | No Shrink | PVC-105-2 | Alpha Wire
- diteksurgeprotection.com/products/17-accessories/25-100-640.html
- diteksurgeprotection.com/products/2-network-protection/62-dtk-110rjc6apoe.html
- Heyco® EPDM Snap-in Liquid Tight Bushings
- Heyco®-Tite Liquid Tight Cordgrips for Pre-assembled Cables
- CAT6 Lightning Protection | CAT6 Surge Protectors
- Installation Tools from LSDI by GRI | George Risk Industries, Inc.