Introduction: The purpose of this guide is to familiarize installers and technicians on properly setting up an Avalon ESS for multi-inverter multi-BMS use. The goal being full use of up to 12 battery modules in stacks of 6 with 2 BMS.
Scope: This document covers the parallel configuration of two PCs and BMS units to meet specific requirements.

Systems Overview

Requirements:

  • Before initiating parallel operation, update the firmware of each unit (Gateway, SEP, PCS, BMS)
  • Conduct initial testing with one PCS and one BMS to ensure proper functionality.
  • Once individual units are confirmed to work fine, proceed with parallel configuration.

BMS Setup Guide

Step 1: Upload Firmware
Begin by uploading the firmware for all BMS units separately. Use Installer App or Web Console

Updating via Installer App
SOP Avalon BMS upgrade .docx

 | Step| # of People| Expected Time| Tools and Special Tools| Special Knowledge
---|---|---|---|---|---
1| Access Installer App (Using Phone)| 1| 1 minute| Smartphone| Avalon Installer App
2| Update Firmware (Installer App)| 1| 10 minutes| Smartphone| Understanding of firmware updates within the installer App

Updating via Web Console:

 | Step| # of People| Expected Time| Tools and Special Tools| Special Knowledge
---|---|---|---|---|---
1| Access Web Console| 1|  | Laptop, Internet

access.

| Knowledge of

finding IP

 |  |  |  |  | address, Wi-Fi network

credentials

---|---|---|---|---|---
2| Update Firmware (Local Web Console)| 1| 10| Laptop, Internet access| Knowledge of using Web Console

Step 2: Verify BMS and Battery Compatibility

 | Step| # of People| Expected Time| Tools and Special Tools| Special Knowledge
---|---|---|---|---|---
1| Check 1st BMS Voltage| 1| 10 minutes| Multimeter| Understanding of electrical measurements, ability to use a multimeter
2| Check 2nd BMS Voltage| 1| 10 minutes| Multimeter| Understanding of electrical measurements
3| Ensure Voltage Range| 1| 5 minutes| N/A| Understanding of electrical measurements

  • Ensure that the voltage of each battery matches the specified requirements and is within the acceptable range. Each battery module must be within 0.25V DC of one another during commissioning
  • Keep the voltage gap between battery stacks as small as possible. A BMS voltage gap of 3V DC per stack or less is acceptable.

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-System-1

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-System-2

Step 3: Connect Signal Lines.

  • Connect the signal lines for each BMS unit. Do not connect the positive and negative poles of the batteries in parallel at this stage.
  • Ensure that the signal lines are connected correctly according to the guides.
  • Power on each battery individually after connecting the signal lines.
  • BMS1 Master and BMS 2 Slave.

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-System-3

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-System-4

Step 4: Access BMS Web Console or Installer App

  • Once the batteries are powered on, access the web Console or Installer App functionality to verify their connectivity and functionality.
  • Confirm that all BMS units are detected and accessible through the Web Console or Installer App.
  • Once communication is successful, turn o`!>30$.%!3#’!;539.!=>;!@.1&%.!)&##.)$#2!/&E.%!5#.0?

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-System-5

Step 5: Connect Power Lines

  • Connect the power lines, establishing a parallel connection between the positive and negative poles of the batteries.
  • Completing these final steps will ensure that the BMS setup is properly configured for parallel operation.
  • The positive and negative poles coming from the PCS will be connected to a Master BMS
  • From the Master BMS, the positive and negative terminals will be connected to the corresponding terminals of a Slave BMS. This is for 1 SEP, 1 PCS and 2 BMS positive and negative poles.

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-System-6

Use cases: Diagram for 1SEP 1 PCS 2 Parallel BMS

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-System-7

Parallel PCS and BMS
Requirements:

  • Before initiating parallel operation, update the firmware of each unit (Gateway, SEP, PCS, BMS)
  • Conduct initial testing with one PCS and one BMS to ensure proper functionality.
  • Once individual units are confirmed to work fine, proceed with parallel configuration.

 | Step| # of People| Expected Time| Tools and Special Tools| Special Knowledge
---|---|---|---|---|---
1| Parallel System

Wiring

| 2| 2-3 hours|  |
2| Parallel System Communication

Setup

| 1| 45 minutes|  | Wiring diagram
3| Configuring Using Installer App| 1|  | Smartphone| Knowledge of using the Installer App

Parallel System Wiring

  • Parallel BMS
  • Connect to each Inverter PV input independently.
  • Ensure each Inverter connected to the Avalon HV Battery
  • Parallel connect the AC power grid output.

Parallel Communication Setup

  • From SEP to Master PCS all the Communication Cables as regular.
  • Use N-1 double-ended network cables with reinforced shielding for parallel communication.

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-System-8

  • Connect the network cable to the communication port of both the master and slave units (Parallel_IN, Parallel_OUT), staggering the interfaces between them.
  • Set DIP switches 1 & 2 of the first and last PCSs to ON, and those of other slave PCS to OFF

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-System-9

Configuring Using Installer App:
Using Installer App set up the first Master PCS

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-
System-10

Proceed to connect SPH IN to the 2nd PCS and configure it’s settings according to using the Installer App

Master and Slave Configuration

  • Configure PCS 1 and BMS 1 as the master units, responsible for controlling and coordinating the system’s operation.FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-System-11
  • Inverter Parallel Settings
  • Parallel Mode – Parallel
  • Set Master/Slave
  • Parallel Sync lock ON

Proceed to connect SPH IN to the 20* PCS and configure it’s settings according to using the Installer App

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-
System-12

Final Verification
Upon successful completion of the setup process, verify the system configuration as follows:

  • Check the Product List in the Installer App
  • Check the Web Console portal to see all the products.

FORTRESS-POWER-Avalon-Smart-Whole-Home-Backup-
System-13