Single-sided Concrete Base Requirements
The built concrete pad should be compliant with local regulatory requirements.
The following dimensions and construction related descriptions are the minimum
requirements.
No. | Qty. | Description | Notes |
---|---|---|---|
1 | 1 | Concrete pad | Compressive strength > 3000 psi |
2 | 4 | Anchor bolt | M12 x 1.75 P x 100 mm |
3 | 1 | Ethernet cable | Length from concrete > 1500 mm |
4 | 1 | AC power cable | Length from concrete > 1500 mm |
5 | 2 | Cable conduit | Length from concrete > 200 mm; Suggested conduit for |
charging current: 32A use 1/2″, 48A use 3/4″
Fig. 2a EVPS concrete base details
- First build concrete pad for the pedestal. The compressive strength must be over 3000 psi. See Reference picture is shown as Fig. 1a & Fig. 2a. Concrete pad dimensions (400 mm W × 400 mm L × 500 mm H) are shown in Fig. 3.
- Please mount 4 pieces of M12x1.75 anchor bolts on the concrete pad based on the dimensions below. The height of the bolt should be at least 20 mm above the concrete pad and depth of bolt is at least 90 mm.
Dual-sided Concrete Base Requirements
The built concrete pad should be compliant with local regulatory requirements.
The following dimensions and construction related descriptions are the minimum
requirements.
No. | Qty. | Description | Notes |
---|---|---|---|
1 | 1 | Concrete pad | Compressive strength > 3000 psi |
2 | 4 | Anchor bolt | M12 x 1.75 P x 100 mm |
3 | 1 | Ethernet cable | Length from concrete > 1500 mm |
4 | 1 | AC power cable | Length from concrete > 1500 mm |
5 | 2 | Cable conduit | Length from concrete > 200 mm; Suggested conduit for |
charging current: 32A use 1/2″, 48A use 3/4″
Fig. 2a EVPS concrete base details
- First build concrete pad for the pedestal. The compressive strength must be over 3000 psi. See Reference picture is shown as Fig. 1a & Fig. 2a. Concrete pad dimensions (400 mm W × 400 mm L × 500 mm H) are shown in Fig. 3.
- Please mount 4 pieces of M12x1.75 anchor bolts on the concrete pad based on the dimensions below. The height of the bolt should be at least 20 mm above the concrete pad and depth of bolt is at least 90 mm.
Concrete Pad Dimensions
- The conduit must be over 200 mm to avoid liquid entering.
- Be sure lengths of AC power cable and Ethernet (LAN) cable are long enough (1500 mm) to reach through the pedestal body and into the EVC48 charger.
- Follow instructions for the AC charging station on the rack.
- After the AC and LAN cable work is finished, the conduit should be protected by silicone sealant to ensure water, dust and bug resistance.
Note: If using side entry seal with silicone after completion.
Pedestal Installation
-
The pedestal base has 4 holes to align the anchor bolts. Tighten nuts > 400 kgf-cm torque.
-
The AC cable and LAN cable go through the holes off the pedestal body, shown as follows:* RJ-45 8P8C modular plug; crystal head of metal shell; Cat6 STP or higher specification wire AX Option 1: Through side AX Option 2: Through back
-
Final
The pedestal has four screw holes that can be used to fasten the bracket of EVSE, shown as follows (units in millimeters): -
If you want to use metal hoses you will need to supply two hose waterproof joints.
Item no.(Black)| Thread| Suit to RCCN conduit item # BG| Suit to RCCN conduit
item # BG| Thread O.D. D1| Panel mounting hole| Thread length L1
---|---|---|---|---|---|---
BGQF-M25B (BG-23)| M25 × 1.5| BG-23| 28.5| 28.5| 25-25.4| 12
Metric thread BGQF M
Technical Support: 888-728-4094
© 2023 RAB Lighting Inc.
Documents / Resources
| RAB
EVPS and EVPD Pedestal
Bases
[pdf] Instruction Manual
EVPS and EVPD Pedestal Bases, EVPS and EVPD, Pedestal Bases, Bases
---|---
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>