Danfoss PXE 02 Industrial Refrigeration Evaporator Control Panels Installation Guide
- June 4, 2024
- Danfoss
Table of Contents
PXE 02 Industrial Refrigeration Evaporator Control Panels
Installation Guide
PXE 02: Component layout
For comprehensive wiring details please refer to the detailed wiring diagram
that is delivered complete with the PXE 02 panels.
Fig. 01
1. EKE 400 Controllers
2. Gas detector relays
3. MCBs
4. Power supplies
5. Fuses
6. Gas detector
7. Internal PE
8. Gas detector terminals
9. Digital input relay terminals
10. A) Gas detection RS485 terminal
B) EKE 400 controller’s RS485 terminals| 11. Gas detection analog outputs
12. Analog inputs
13. Analog outputs
14. Optional motorized valve power
15. DIN rail for accessories (side of the panel)
16. Fan and heater (side of the panel)
17. Rail for wire organization
18. Baseplate (see baseplate layout diagram below)
---|---
PXE 02: Baseplate layout
Fig. 02
A – Type SKIN TOP MULTI
Version 1 – Maximum number of cables – 22 including 6×8-12 mm; 16×3-7 mm
B – Type SKIN TOP MULTI Version 5 with SKIN TOP BRUSH ADD-ON 24 for EMC screen
contact – Maximum number of cables – 27 including 27×4-8 mm
C – Type SKIN TOP ST-M M20 – Gas detector sensor cable.
Note:
- To ensure optimum strain relief, the cable bundle can be fixed with help of a cable tie
- After removing the unused cable from SKIN TOP MULTI – elastic gel will NOT SEAL, please use silicone to ensure proper IP (Ingress Protection)
- Use a plug for the M20 gas detector gland if the gas detector is not present.
NB:
DIFFERENT POTENTIALS 24 V AND 230 V SHOULD BE PLACED IN SEPARATE CABLE
ENTRY
PXE 02: Mounting instructions
Fig. 03
PXE 04: Component layout
For comprehensive wiring details please refer to the detailed wiring diagram
that is delivered complete with the PXE 04 panels.
Fig. 04
1. EKE 400 Controllers
2. Gas detector relays
3. MCBs
4. Power supplies
5. Fuses
6. Gas detector
7. Internal PE
8. Gas detector terminals
9. Digital input relay terminals
10. A) Gas detection RS485 terminal
B) EKE 400 controllers RS485 terminal| 11. Gas detection analog outputs
12. Analog inputs
13. Analog outputs
14. Optional motorized valve power
15. DIN rail for accessories (side of the panel)
16. Fan, heater & thermostat (side of the panel)
17. Rail for wire organization
18. Baseplate (see baseplate layout diagram below)
---|---
PXE 04: Baseplate layout
Fig. 05
A – Type SKIN TOP MULTI Version 1 – Maximum number of cables – 22 including
6×8-12 mm; 16×3-7 mm
B – Type SKIN TOP MULTI Version 5 with SKIN TOP BRUSH ADD-ON 24 for EMC screen
contact – Maximum number of cables – 27 including 27×4-8 mm
C – Type SKIN TOP ST-M M20 – GDA Sensor Cable
Note:
- To ensure optimum strain relief, the cable bundle can be fixed with help of a cable tie
- After removing the unused cable from SKIN TOP MULTI – elastic gel will NOT SEAL, please use silicone to ensure proper IP (Ingress Protection)
- Use a plug for the M20 gas detector gland if the gas detector is not present.
NB:
DIFFERENT POTENTIALS 24 V AND 230 V SHOULD BE PLACED IN SEPARATE CABLE
ENTRY
PXE 04: Mounting instructions
Fig. 06
External wiring considerations: Power supply, Signal wiring, and Fieldbus
-
230 V cabling to and from the panel, the cable glands should be fed with Ø6-11 mm overall nominal diameter cable with conductor areas 0.75-1.5 mm. For low voltage signal to and from the panel should be made with Ø6 mm overall nominal diameter cables with conductor areas 0.75 mm. This is necessary for achieving the panel’s rated IP
-
Unused cable gland openings must be closed, and all gland insert bores must be occupied to achieve the panel’s rated IP.
Gland insert bores may be plugged using the supplied sealing plugs. After removing the unused cable from SKIN TOP MULTI – the elastic gel will NOT SEAL, please use silicone to ensure proper IP. Note: non-punctured insert bores retain IP level 65/66 (depending on panel variant) -
The wiring of Modbus RTU (RS485) must be carried out in accordance with the standard ANSI/TIA/EIA-485-A-1998.
Galvanic separation shall be provided for segments crossing buildings. The common ground shall be used for all devices on the same network including routers, gateways, etc. All bus connections in the cables are made with twisted pair wires.
The recommended cable type for this is AWG 22/0.32 mm2 -
The evaporator controllers and Gas Detector are on separate Modbus RTU networks and therefore have 2 separate panel terminals
-
Connecting panels (evaporator controllers) in series via the correct terminals is shown in fig. 08
-
Remember to terminate the RS485 network following the last physical device with a 120-ohm resistor, as shown in fig. 09
EKE 400 Controllers | GDA Gas detection unit |
---|---|
Panel terminal | |
D+ | X107 |
D- | D- |
GND | GND |
Available Modbus RTU parameters in each controller and gas detector
For a complete overview of all the available Modbus parameters for each
evaporator controller device (there are 500+ Modbus values available per
controller) please refer to the EKE 400 controller datasheet for comprehensive
descriptions and details:
Link
For a complete overview of all the available Gas Detector Modbus parameters
please refer to the Gas Detector Modbus Communication Guide for comprehensive
descriptions and details:
Link
Quick startup – With the CoolConfig software tool
What you will need: CoolConfig software. USB to RS-485 cable. Power to your
control panel.
Step 01: Ensure the latest version of CoolConfig is installed on your PC.
Link to CoolConfig Download:
Link
Step 02: Each controller is to be configured individually. After powering
up, connect your RS485-USB cable to your PC to the terminal labeled X107 on
the PXE 02 or X107 on the PXE 04. The controllers are RS-485 pre-wired in
series.
Step 03: Startup the CoolConfig software. In the CONNECTION tab, choose
the correct COM port your PC and cable are using.
Step 04: Choose the Modbus Slave ID (called ‘Modbus address’ in
CoolConfig), also in the same CONNECTION tab, of the controller you wish to
configure.
For the PXE 02 variants, the Modbus Slave ID is pre-set from the factory as:
Table. 01
Controller | Modbus Slave ID |
---|---|
01 | 1 |
02 | 2 |
For the PXE 04 variants, the Modbus Slave ID is pre-set from the factory as:
Table. 02
Controller | Modbus Slave ID |
---|---|
01 | 01 |
02 | 02 |
03 | 03 |
04 | 04 |
Note:
It is a good idea to ensure the CoolConfig settings are aligned with the
controller settings before moving on to the next step. This is done by
choosing the CONNECTION DETAILS button in the CONNECTION tab. The default
Modbus serial communication settings on all the controllers from the factory
are as follows:
Table. 03
EKE 400 controller’s default comm settings
Baud rate| 38.400 bps
Parity| even
Data bits| 8
Stop bit| 1
Start bit| 1
Step 05: Commence controller configuration. Start with either opening a
previously configured file from the dropdown menu FILE and choosing OPEN or
start with configuring a new application by choosing the VALVE CONFIGURATION
tab.
Other tabs and application drawings will appear after making a choice in the
VALVE CONFIGURATION tab.
Step 06: Once satisfied with your controller configuration, you may write
the configuration to the controller by choosing the WRITE PARAMETERS TO EKE400
button at the top of the software window. Remember to save the different
configurations if required or export them to Excel using the FILE dropdown
menu in the top left corner of the software window.
Step 07: Repeat Step 04 to Step 06 until all controllers are
configured.
Note:
The CoolConfig software allows you to activate the IO for commissioning
purposes which you may find useful.
See the I/O CONFIGURATION and ACTION tabs of CoolConfig.
Quick startup – front door display
After powering up the panel navigating to the different controllers can be
done via the front door display called the MMI. The MMI display is an access
point via CANbus (separate from and not affecting the Modbus RTU network) to
the main status values of each evaporator controller. Follow these steps to
access information in the desired controllers:
Fig. 11 MAIN screen
Step 01: From the “MAIN” screen the “BIOS” screen must be accessed. This
is done by holding both the X and return buttons simultaneously for 4–5
seconds
Fig. 12 BIOS screen
Step 02: Wait until the BIOS menu (see below) is shown on the screen and
release the buttons. The current MCX selection will be displayed in the upper
right
Fig. 13 MCX SELECTION
Step 03: Highlight and select (return button) “MCX SELECTION”
Fig. 14 MAN SELECTION
Step 04: Next, highlight and select (return button) “MAN SELECTION”
Fig. 15 CAN ID
Step 05: Highlight and select, then scroll up and down to select CAN ID
address number and press return
Further information about using the MMI can be found in the MMI instruction
guide:
Link
Further information about the functionality and using the menus can be found
in the EKE 400 datasheet:
Link
Navigating the front door display
The front door HMI gives an overview of the system status and can easily be
navigated via the arrow buttons. The displays give us easy-to-understand
information about the:
- Active alarms
- The status of each evaporator
Navigating from controller to controller is explained in the previous section. Other instructions regarding controller/evaporator information that may be viewed can be found on the EKE 400 datasheet: Link
Panels with Gas Detection
Gas Detector cable and sensor
The gas detector remote sensor is supplied detached from the gas detection
unit and must be connected after mounting. An M25 gland on the right side of
the enclosure bottom plate is reserved for the remote sensor unit cable. Mount
the remote sensor unit and connect the cable as outlined in the final pages of
the panel schematics.
Gas Detector factory default settings – Modbus RTU
The PXE 02 and PXE 04 have variants that are equipped with Danfoss GDA gas
detectors, cables, and sensors. The gas detector unit runs on a parallel
Modbus RTU Fieldbus system to the Evaporator Controllers and may be connected
to the customers gas detector Modbus RTU system via terminal X54 on the PXE 02
panels and terminal X54 on the PXE 04 panels equipped with gas detection. The
Gas Detection Modbus RTU Fieldbus network settings have the following default
settings from the factory:
Table. 04
EKE 400 controller’s default comm settings
Slave ID| 1
Baud rate| 19.200 bps
Parity| even
Data bits| 8
Stop bit| 1
Start bit| 1
NOTE: The Slave ID can be changed but all other serial communication settings cannot be changed.
Gas Detector factory default settings – NH₃ PPM alarm settings
The gas detector will activate an alarm if there is an error detected or if
there is a power failure in the unit. The gas detection units also come with
factory default 2-step alarm set-up ready for use. PPM alarm factory settings
are as follows:
Table. 05
Gas Detector Factory Default Values
Description| Default value
NH₃ PPM high-level ALARM 1| 25 PPM
NH₃ PPM high-level ALARM 2 SHUTDOWN| 35 PPM
NH₃ PPM range| 0–100 PPM
Gas Detector factory default settings – Terminals
The user interface enables the user to configure two individual alarm
settings. ALARM 1 is a pre-alarm that, when activated, indicates the gas level
has passed a user-defined first threshold. If the gas level then passes a
user-defined second threshold, the final ALARM 2 (shutdown) is activated. For
further information on the setup of the gas detection unit via the display and
information on alarm schemes, please refer to the links to relevant
documentation below. Factory default outputs from the panel gas detection unit
are, factory default as follows:
Table. 06
PXE 02 and PXE 04 panels with gas detection
Description| Default value
PPM High-Level ALARM 1 (DO)| X61
PPM High-Level SHUTDOWN ALARM 2 (DO| X63
PPM level (4–20 mA AO)| X54.1
Connecting the Gas Detection safety circuit to the evaporator controllers
The default factory configurations of the PXE 02 and PXE 04 are not set up to
output signals from the gas detector directly to the inputs of the controllers
in the panel. If required, the DO of a selected controller can be set up to
de-energize following a High NH₃ PPM SHUTDOWN ALARM 2 output from the gas
detection unit. This is done by following these steps:
Step 01: Locate the controller input terminal required to de-energize ALL
its DO on a High NH₃ PPM SHUTDOWN ALARM 2 signal from the gas detection unit.
Table. 07
PXE 02 panels
Description| Gas Safety Circuit DI Terminal
EKE 400 Controller 1| X100
EKE 400 Controller 2| X400
Table. 08
PXE 04 panels
Description| Gas Safety Circuit DI Terminal
EKE 400 Controller 1| X100
EKE 400 Controller 2| X200
EKE 400 Controller 3| X300
EKE 400 Controller 4| X400
NOTE: In the following example, the Gas Detector in PXE 04 will be wired
to de-energize the DO from Controller 1 on a High NH₃ PPM ALARM 2 output from
the gas detection unit
Step 02: Remove the jumper from the selected terminal. In this example,
remove the jumper from Controller 1 at X100.
Fig. 18
Step 03: Wire terminal X63 to terminal X100
NOTE: The control sequence the EKE 400 controller will apply on receipt
of this signal may be easily set up by using the CoolConfig software
interface.
IMPORTANT: Only the DO in the controlled evaporator circuit will be de-
energized by this function. AO will not be affected and will continue to
operate according to the output signal of the controller.
Connecting the Gas Detector PPM reading to the Controller
The Gas Detection PPM analog output signal (mA factory default) may be
connected to a controller AI terminal and read on the Modbus RTU controller
network. The actual AI controller terminal the AO terminal from the gas
detection unit will depend on the configuration of the EKE 400 controller. The
control AI can be viewed on the software CoolConfig during controller
configuration and the correct terminal can then be located and wired to from
the gas detection AO terminal X54.1. See the example below where AI2 is to be
used.b
The gas detection terminal and Modbus registers to be noted for these purposes
are as follows:
Table. 09
Gas detector AO terminals for PPM level
| 4 EKE 400 Pane| 2 EKE 400 Panel
PPM AO terminal| X54.1| X54.1
Controller Modbus registers for PPM level
The PPM level may be read off the EKE 400 controller Modbus network (if not
using the gas detection units Modbus network) and will of course depend on the
EKE 400 controller and terminal used. The following Modbus registers are where
the PPM values can be read (depending on the wiring & controller
configuration).
Table. 10
| 2 EKE 400 Controller Panel| 4 EKE 400 Controller Panel
---|---|---
AI| Modbus Register| EKE 400 Controller 1 Terminal| EKE 400
Controller 2 Terminal| EKE 400 Controller 1 Terminal| EKE 400
Controller 2 Terminal| EKE 400 Controller 3 Terminal| EKE 400
Controller 4 Terminal
1| 1005| X150.1| X450: 1| X150.1| X250.1| X350.1| X450: 1
2| 1006| X150.2| X450: 2| X150.2| X250.2| X350.2| X450: 2
3| 1007| X150.3| X450: 3| X150.3| X250.3| X350.3| X450: 3
4| 1008| X150.4| X450: 4| X150.4| X250.4| X350.4| X450: 4
Gas Detector Documentation
Further information about using the menus can be found in the GDA
Application Guide :
Link
Further installation information about installing the GDA can be found in the
GDA Installation Guide:
Link
Further installation information about the Modbus functionality can be found
in the GDA Modbus Communication Guide:
Link
Accessory: Signal conditioners
The PXE 02 and PXE 04 analog output signals from its controllers to evaporator
controlling actuators are 0–10 V type from the factory. It is possible to
purchase signal conditioners as accessories from Danfoss that can be installed
and wired by the customer (please contact a Danfoss sales representative).
Signal conditioners change the analog output signal at the panel terminal from
0–10 V to 4–20 mA. The following is a quick overview of how this may be done.
Step 01: Mount the signal conditioner on the DIN rail provided on the
right side of the panel.
Step 02: Wire the power terminal available in the panel (X77) to the
signal conditioner power terminals and wire the correct AO terminals
(X160-X460) to the input side of the signal conditioner. Please read the
signal conditioner instructions beforehand.
The 4–20mA device may now be wired to the output side of the signal
conditioner.
Accessory: Stepper motor drivers
The PXE 02 and PXE 04 analog output signals from its controllers to
evaporator controlling actuators are 0-10 V type from the factory. It is
possible to purchase Danfoss stepper motor drivers EKF 1A to drive 1 stepper
motor valve and EKF 2A to drive 2 stepper motor valves as accessories that can
be installed and wired by the customer. Stepper motor drivers change the
analog output signal at the panel terminal from 0-10 V to a stepper motor
signal that may be configured according to the stepper motor valve’s
specification. The following is a quick overview of how a stepper motor driver
may be installed in the panel.
Step 01: Mount the stepper motor driver on the DIN rail provided on the
right side of the panel.
Step 02: Wire the power terminal available in the panel (X77) to the stepper motor power terminals and wire the correct AO terminals (X160-X460) to the input side of the stepper motor driver. Please read the stepper motor driver instructions beforehand and configure the driver according to the required application. The stepper motor valve may now be wired to the stepper motor driver. See the installation instructions for the Danfoss EKF 1A and EKF 2A stepper motor drivers for stepper motor driver connection details and observe the wiring recommendations regarding distance to the stepper motor valve: Link
Danfoss can accept no responsibility for possible errors in catalogs,
brochures, and other printed material. Danfoss reserves the right to alter its
products without notice. This also applies to products already on order
provided that such alterations can be made without subsequential changes being
necessary for specifications already agreed upon.
All trademarks in this material are the property of the respective companies.
Danfoss and the Danfoss logotype are trademarks of Danfoss A/S. All rights
reserved.
© Danfoss
Climate solutions
2021.07AN383426363919en-000101 | 16
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>