The Thermory Barrel Sauna No55 is designed for up to two people. It comes with all the necessary parts and components to build yourown sauna. The sauna is made up of various staves, panels, cradles, roof boards, flooring, benches, backrest staves, metal bands, legs, adhesive, roof tape, waterproof roof cover, wooden slats for the roof, screws, stainless steel screws, hex nuts, washers, decorative roof finishing boards, and recommended tools.

Product Usage Instructions

  1. Step Zero: Prepare the Site
    • Before you begin, ensure that the sauna will fit in your chosen location.
    • The ideal dimensions for the sauna are approximately 6′ x 7′ x 7′ (L x W x H).
    • Make sure the site is level and free of standing water after rainfall.
    • Concrete, pavers, or crushed stone are preferred as the base for the sauna.
  2. Step One: Measure and Level the Support Cradles
    • Measure the support cradles (A) diagonally from corner to corner. Ensure that measurements a and b are equal to ensure the cradles are square.
    • Place the support cradles (A) on a level site and carefully level them for better stability.
    • Place the center stave (B) on wooden dowels embedded in the outer support cradles (A) and fix it with screws 4.2 x 70 (N).
  3. Step Two: Install the Sauna Body Staves
    • Place 6 sauna body staves (C) on each side of the center stave (B) and fix them with screws 4.2 x 70 (N).
    • Ensure that the panel groove is aligned on every next body stave.
  4. Step Three: Install Front and Rear Panels
    • Place the front panel with sauna doors (F2) and rear panel (E2) into the trimmed grooves, ensuring that each panel is centered, leveled, and completely seated into the floor panel.
    • Bind these panels together by temporarily placing one or two body staves (C) on top of them.
  5. Step Four: Attach Side Panels
    • Attach two front side panels (F, F1) to the front panel (F2) and two back side panels (E, E1) to the rear panel (E2) using screws 5.0 x 120 (M) and stainless steel screws 4.20 x 70 (N1).
    • Ensure that the bench supports face the interior of the sauna.
    • Confirm that the combined width of the panels matches the width of the sauna body staves (C).

Note : For more detailed instructions and visual guidance, you can scan the code on the back of the installation guide.

Everything you need to build your very own Thermory Barrel Sauna is right there in front of you. If it looks like a lot, it is. If it seems too complicated to assemble, it isn’t.
These instructions are specifically written to guide you through each step with ease. And if you need additional encouragement, you can scan the code on the back of this guide to see how it’s done.
The Thermory Barrel Sauna No55 is designed for up to two people. That’s plenty of room for you and the friends helping you put this together. But if you want to enjoy the first steam all by yourself, we understand.

The Wait Is Over

We truly appreciate the opportunity to share our love of sauna culture with you. And if there’s anything we can do to make your sauna experience better, please don’t hesitate to let us know. If not, just relax and enjoy.

BARRELS-No55-Steam-Sauna-Bath-FIG- \(1\)

REQUIRED TOOLS

PARTS 1BARRELS-No55-Steam-Sauna-Bath-FIG- \(2\)

PARTS 2BARRELS-No55-Steam-Sauna-Bath-FIG- \(3\)

INSTALLATION

  • STEP ZERO
    • Before you begin, be sure the sauna will fit in your chosen location.
    • Approximately L x W x H of 6’ x 7’ x 7’ is ideal. Overall dimensions are shown here.
    • Be sure the site is level and free of standing water after rainfall.
    • Concrete, pavers or crushed stone is preferred.
  • STEP ONE
    • Measure support cradles (A) diagonally from corner to corner.
    • Measurements “a” and “b” should be equal to ensure the cradles are square.
    • Be sure cradles remain level.
  • STEP TWO
    • Place the support cradles (A) on level site. Carefully level for better stability.
    • Place the center stave (B) on wooden dowels embedded in outer support cradles (A).
    • Fix center stave (B) to cradles with screws 4.2 x 70 (N).BARRELS-No55-Steam-Sauna-Bath-FIG- \(6\)
  • STEP THREE
    • Place 6 sauna body staves (C) to each side of the center stave (B) and fix with screws 4.2 x 70 (N).
    • Be sure to align the panel groove on every next body stave.
  • STEP FOUR
    • Place front panel with sauna doors (F2) and rear panel (E2) into the trimmed grooves. Be sure each panel is centered, leveled, and completely seated into the floor panel.
    • Bind these panels together by temporarily placing one or two body stave (C) on top of them.BARRELS-No55-Steam-Sauna-Bath-FIG- \(8\)
  • STEP FIVE
    • Two front side panels (F, F1) attach to the front panel (F2) and two back side panels (E, E1) attach to the rear panel (E2) by 4 screws 5.0 x 120 (M) and 4 stainless steel screws 4.20 x 70 (N1).
    • Be sure the bench supports face the interior of the sauna.
    • Confirm that the combined width of the rear wall (E, E2, E1) matches the combined width of the front wall (F, F2, F1).BARRELS-No55-Steam-Sauna-Bath-FIG- \(9\)
  • STEP SIX
    • Continue placing body staves (C) tightly on both sides of the sauna using rubber mallet, while fixing body staves on the front panel with 4.2 x 70 screws.
    • To finish the roof top joint, use top stave (H).
  • STEP SEVEN
    • Install steel bands (I) by wrapping bands around barrel prior to connecting with bolts and nuts (U).
    • Place steel bands evenly around barrel, covering screw heads.
    • Measure from steel band to barrel edge to ensure the steel band is even.
    • Cover roof with roof tape. Rub and smooth with pressure to ensure adhesion.
    • Install interior aspen roof trim (O) with 4.0 x 50 (P1) stainless steel screws.BARRELS-No55-Steam-Sauna-Bath-FIG- \(11\)
  • STEP EIGHT
    • Attach bench supporting leg (J1) to the bench (J), install two sauna benches on wall mounts using stainless steel screws 4.2 x 70 (N1).
    • Hold the seat and leg assembly tight to the sauna wall. Using a level, make sure the bench seat is level from front to back. This will ensure proper placement.
    • Install backrests (J2) at your chosen height using stainless steel screw 4.0 x 50 (P1).BARRELS-No55-Steam-Sauna-Bath-FIG- \(12\)
  • STEP NINE
    • Flooring duckboards (L) can be used for wiring runs, confirm specific wiring runs needed for chosen stove.
  • STEP TEN
    • Place waterproof roof cover (Z) and fix it with wooden slat (Z1) and screws 4.0 x 50 (P).
    • Install front and rear decorative roof finishing boards (W), fixing by screws 4.0 x 50 (P).BARRELS-No55-Steam-Sauna-Bath-FIG- \(15\)

WATCH THE VIDEOBARRELS-No55-Steam-Sauna-Bath-FIG-
\(16\)

**SEE HOW ASSEMBLY WILL LOOK HERE

BARRELS-No55-Steam-Sauna-Bath-FIG-
\(17\)**

Thermory USA – Denver

537 W. Highlands Ranch Pkwy, Ste. 114 Highlands Ranch, CO 80129 720.759.7268 [email protected]

Thermory USA – Buffalo
56 Harvester Ave, Ste. 1-201 Batavia, NY 14020 585.591.6590 [email protected]

SaunaByThermory.com

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

BARRELS User Manuals

Related Manuals