Product Information

This product is a conversion kit designed for rewiring 2-lamp luminaires to operate with LEDVANCE LED TUBE T8 EM, UNIVERSAL, or LEDVANCE LED TUBE T5 AC. The rewiring process must be carried out by a qualified electrician and requires the use of specific tools and materials.

The new wires used for rewiring must comply with the latest versions of EN 50525 and EN 60598-1 standards. They should have a minimum cross-section of 0.4 mm2 and a nominal thickness of 0.5 mm  for insulation. The conversion kit includes the necessary materials for the rewiring process.

Product Usage Instructions

  1. Ensure that the luminaire’s ECG mounting has been removed before starting the rewiring process.
  2. Gather the following tools: wire cutter, wire stripper, and different screwdrivers.
  3. Follow the provided circuit diagram for direct wiring of a 2-lamp luminaire on AC mains.
  4. Step 1: Connect the mains line L to the fuse using a WAGO connector.
  5. Step 2: Connect the second fuse line to both right lamp holders, ensuring correct connection of all ECG clamps.
  6. Step 3: Connect the lines of the left and right lamp holders for lamp 1 and 2.
  7. Step 4: Connect both left lamp holders to the neutral line “N” using WAGO connectors if needed.
  8. Step 5: Remove the ECG.
  9. Step 6: Secure all wires with adhesive sockets and cable ties.
  10. Step 7: After the CE conformity test, attach a new nameplate clearly visible and permanently on the luminaire, removing or covering the old nameplate.
  11. Step 8: Conduct a final visual inspection of all components and ensure that all wires are securely fixed inside the WAGO connectors. Make sure that cables are not pinched during the luminaire mounting. Repair or replace any defective parts if necessary. Re-connect the earth conductor (PE) if needed.

For specific wiring examples with typical ECGs, refer to the user manual’s section “Wiring examples with typical ECG.” Follow the general work steps and connect the lines according to the provided instructions for each ECG type.

For 2-lamp luminaires to AC mains direct wiring for operation with LEDVANCE LED TUBE T8 EM, UNIVERSAL or LEDVANCE LED TUBE T5 AC

Rewiring of 2-lamp Luminaires

Rewiring must be executed by a qualified electrician.

Luminaire to be rewired (ECG mounting already removed)

LEDVANCE-T8-EM-2-Lamp-Luminaires-SubstiTUBE-Conversion-Kit
\(1\)

Tools needed: wire cutter, wire stripper, different screwdrivers
New wires must comply with latest version of EN 50525 and EN 60598-1, have a minimum cross section of 0,4 mm2 and the isolation have a nominal thickness of 0,5 mm.

Material included in conversion kit

Content conversion kit:

  • 6 WAGO connectors
  • 4 adhesive sockets for cable ties
  • 4 cable ties
  • New blank name plate for luminaire (to be fixed clearly visible and permanently on the luminaire)
  • Pre-wired microfuse (T2A 250V)

General Work Steps

Direct wiring circuit diagram of a 2-lamp luminaire on AC mains

LEDVANCE-T8-EM-2-Lamp-Luminaires-SubstiTUBE-Conversion-Kit
\(3\)V

Remove wiring from ECG step by step and re-connect as prescribed below

LEDVANCE-T8-EM-2-Lamp-Luminaires-SubstiTUBE-Conversion-Kit
\(4\)

  • Step 1: Connect mains line “L” to fuse with one wire using a WAGO connector
  • Step 2: Connect second fuse line to both right lamp holders. Pay attention to correct connection of all ECG clamps within the following steps.
  • Step 3: Connect lines of left and right lamp holders for lamp 1 and 2.
  • Step 4: Conenct both left lamp holders to neutral line „N“. Use WAGO connectors if needed.
  • Step 5: Remove ECG.
  • Step 6: Fix all wires with adhesive sockets and cable ties.
  • Step 7: After CE conformity test, fill in and fix new name plate clearly visible and permanently on luminaire while removing or pasting over old name plate. LEDVANCE-T8-EM-2-Lamp-Luminaires-SubstiTUBE-Conversion-Kit \(7\)
  • Step 8: Conduct final visual inspection of all components and check if all wires have been fixed tightly inside of the WAGO connectors. Cables should not be pinched during the mounting of the luminaire. Defect parts must be repaired or replaced. LEDVANCE-T8-EM-2-Lamp-Luminaires-SubstiTUBE-Conversion-Kit \(8\)
    If needed, re-connect earth conductor (PE) LEDVANCE-T8-EM-2-Lamp-Luminaires-
SubstiTUBE-Conversion-Kit \(9\)

Wiring examples with typical ECG

Remove wiring from ECG step by step and re-connect as prescribed belowLEDVANCE-T8-EM-2-Lamp-Luminaires-SubstiTUBE-Conversion-Kit
\(10\)

  • Step 1: Connect mains line “L” to fuse with one wire

    • ECG with 7 connectors (e.g. Siemens, OSRAM, BAG)
    • Siemens ECG LEDVANCE-T8-EM-2-Lamp-Luminaires-SubstiTUBE-Conversion-Kit \(12\)

  • Step 2 Connect second fuse line to line „7“ and „5“

  • Step 3: Connect line „6“ to line „3“

  • Step 4: Connect line „4“ to line „2“

  • Step 5: Connect line „1“ to line „N“
    Further steps according to general work steps.

OSRAM ECG LEDVANCE-T8-EM-2-Lamp-Luminaires-SubstiTUBE-Conversion-Kit
\(13\)

  • Step 2: Connect second fuse line to line „24“ and „26“ Step 3: Connect line „25“ to line „22“
  • Step 4: Connect line „27“ to line „23“
  • Step 5: Connect line „21“ to line „N“
  • Further steps according to general work steps.

BAG ECG

  • Step 2: Connect second fuse line to line „1“ and „7“
  • Step 3: Connect line „6“ to line „5“
  • Step 4: Connect line „3“ to line „2“
  • Step 5: Connect line „4“ to line „N“
    Further steps according to general work steps.
ECG with 6 connectors (e.g. Philips, Tridonic)

Philips ECG LEDVANCE-T8-EM-2-Lamp-Luminaires-SubstiTUBE-Conversion-Kit
\(15\)

  • Step 2: Connect second fuse line to line „1“ and „6“
  • Step 3: Connect line „2“ to line „3“
  • Step 4: Connect line „4“ to line „5“
  • Step 5: Connect both connection lines of left lamp holders to „N“ Further steps according to general work steps.

Zumtobel/ Tridonic ECG

  • Step 2: Connect second fuse line to line „11“ and „16“
  • Step 3: Connect line „12“ to line „13“
  • Step 4: Connect line „14“ to line „15“
  • Step 5: Connect both connection lines of left lamp holders to „N“ Further steps according to general work steps.

General Work Steps CCG Luminaire

Circuit diagram of a double-flame luminaire with traditional CCG, fluorescent lamp and starter

LEDVANCE-T8-EM-2-Lamp-Luminaires-SubstiTUBE-Conversion-Kit
\(17\)

Circuit diagram of a double-flame luminaire with traditional CCG, fluorescent lamp and starter

Circuit diagram of a rewired, double-flame luminaire with LED tubes on AC mains

LEDVANCE-T8-EM-2-Lamp-Luminaires-SubstiTUBE-Conversion-Kit
\(18\)

  • Step 1: Connect mains line “L” to fuse with one wire using a WAGO connector.
  • Step 2: Connect second line of fuse in parallel with a lamp holder of one lamp (see circuit diagram above). It is recommended to use the side that had been previously connected to the CCG.
  • Step 3: Remove starter holder to establish a connection between the right and left lamp holder
  • Step 4: Connect cables leading to starter holder using a WAGO connector.
  • Step 5: Remove CCGs.
  • Step 6: Fix cables using existing cable brackets and mount additional cable ties and adhesive sockets.

ABOUT LEDVANCE
With offices in more than 50 countries and business activities in more than 140 countries, LEDVANCE is one of the world’s leading general lighting providers for professional users and end consumers. Having emerged from the general lighting business of OSRAM GmbH, LEDVANCE offers a wide-ranging assortment of LED luminaires for a broad spectrum of application areas, intelligent lighting products for Smart Homes and Buildings, one of the largest LED lamps portfolios in the industry as well as traditional light sources

  • LEDVANCE GmbH Parkring 29 – 33 85748 Garching Germany
  • LEDVANCE.COM
  • Subject to change without notice. Errors and omission excepted.

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

Related Manuals