Safety Precautions

General Disclaimer

  • The information in this quick installation guide is subject to change due to product updates or other reasons. This guide cannot replace the product labels or the safety precautions in the user manual unless otherwise specified. All descriptions here are for guidance only.
  • Before installations, read through the quick installation guide. For additional information, please see the user manual.
  • All operations should be performed by trained and knowledgeable technicians who are familiar with local standards and safety regulations.
  • Check the deliverables for correct model, complete contents, and intact appearance. Contact the manufacturer if any damage is found or any component is missing.
  • Use insulating tools and wear personal protective equipment when operating the equipment to ensure personal safety. Wear anti-static gloves, clothes, and wrist strip when touching electronic components to protect the inverter from damage. The manufacturer shall not be liable for any damage caused by static electricity.
  • Strictly follow the installation, operation, and configuration instructions in this guide and user manual. The manufacturer shall not be liable for equipment damage or personal injury if you do not follow the instructions. For more warranty details, please visit https://en.goodwe.com/warranty.

Safety Disclaimer

Warning

DC Side:

  1. Ensure the component frames and the bracket system are securely grounded.
  2. Connect the DC cables using the delivered PV connectors. The manufacturer shall not be liable for equipment damage if other connectors are used.
  3. Ensure the DC cables are connected tightly, securely, and correctly. Inappropriate wiring may cause poor contacts or high impedances, and damage the inverter.
  4. Measure the DC cable using the multimeter to avoid reverse polarity connection. Also, the voltage should be under the max DC input voltage. The manufacturer shall not be liable for the damage caused by reverse connection and extremely high voltage.
  5. The PV modules used with the inverter must have an IEC61730 class A rating.

AC Side:

  1. The voltage and frequency at the connecting point should meet the on-grid requirements.
  2. Additional protective devices like circuit breakers or fuses are recommended on the AC side. Specification of the protective device should be at least 1.25 times the rated
  3. PE cable of the inverter must be connected firmly.
  4. You are recommended to use copper cables as AC output cables. If you prefer aluminum cables, remember to use copper to aluminum adapter terminals.

Product:

  1. Do not apply mechanical load to the terminals, otherwise the terminals can be damaged.
  2. All labels and warning marks should be visible after the installation. Do not scrawl, damage, or cover any label on the device.
  3. Unauthorized dismantling or modification may damage the equipment, the damage is not covered under the warranty.
  4. Install the inverter away from high magnetic field to avoid electromagnetic interference. If there is any radio or wireless communication equipment below 30MHz near the inverter, you have to:
    • Install the inverter at least 30m far away from the wireless equipment.
    • Add a low pass EMI filter or a multi winding ferrite core to the DC input cable or AC output cable of the inverter.
  5. Warning labels on the inverter are as follows.

GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-fig-1

Check before Power-on

No. Check Item
1 The product is firmly installed at a clean place that is well-ventilated

and easy-to-

operate.

2| The PE, DC input, AC output, and communication cables are connected correctly and

securely.

3| Cable ties are intact, routed properly and evenly.
4| Unused ports and terminals are sealed.
5| The voltage and frequency at the connection point meet the inverter grid connection requirements.

EU Declaration of Conformity

GoodWe Technologies Co., Ltd. hereby declares that the inverter with wireless communication modules sold in the European market meets the requirements of the following directives:

  • Radio Equipment Directive 2014/53/EU (RED)
  • Restrictions of Hazardous Substances Directive 2011/65/EU and (EU) 2015/863 (RoHS)
  • Waste Electrical and Electronic Equipment 2012/19/EU
  • Registration, Evaluation, Authorization and Restriction of Chemicals (EC) No 1907/2006 (REACH)

GoodWe Technologies Co., Ltd. hereby declares that the inverter without wireless communication modules sold in the European market meets the requirements of the following directives:

  • Electromagnetic compatibility Directive 2014/30/EU (EMC)
  • Electrical Apparatus Low Voltage Directive 2014/35/EU (LVD)
  • Restrictions of Hazardous Substances Directive 2011/65/EU and (EU) 2015/863 (RoHS)
  • Waste Electrical and Electronic Equipment 2012/19/EU
  • Registration, Evaluation, Authorization and Restriction of Chemicals (EC) No 1907/2006 (REACH) You can download the EU Declaration of Conformity on www.goodwe.com.

LED Indicators

GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-2

Product Introduction

Parts DescriptionGOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-3

  1. PV Input Terminal
  2. DC Switch
  3. WiFi/4G/LAN/GPRS Communication Module Port or RS485 Communication Cable Port
  4. DRED/CT/ Remote Shutdown Communication Cable Port
  5. AC Output Terminal
  6. Indicator
  7. LCD
  8. Button
  9. PE Terminal
  10. Mounting Plate
  11. Heat Sink

Dimensions

GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-4

Inverter Installation

GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-5

Space Requirements

GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-6GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-7

Angle Requirements

GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-8

Angle Requirements

GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-9GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-10

Electrical Connection

PE CableGOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-11

AC CableGOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-12

AC-1 ConnectorGOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-13 GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-14

AC-2 ConnectorGOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-15 GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-16

AC-3 ConnectorGOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-17

DC CableGOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-18

DEVALAN

GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-19GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-20

DRED/Remote Shutdown Communication Cable

  • DRED: Australia
  • Remote Shutdown : EuropeGOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-fig-21

CT Communication CableGOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-22

RS485 Communication CableGOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-23

Communication Module

WiFi kit, 4G kit, LAN kit, GPRS, Wi-Fi/LAN Kit module: optional.GOODWE-
GW2900D-NS-Grid-Tied-PV-Inverter-fig-24

Power On and Off

GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-25GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-26

Commissioning

Commissioning via LCD GOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-27Commissioning via SolarGo APPGOODWE-
GW2900D-NS-Grid-Tied-PV-Inverter-fig-28

Monitoring via SEMS Portal AppGOODWE-GW2900D-NS-Grid-Tied-PV-Inverter-
fig-29

For more detailed instructions, scan the QR codes below.GOODWE-GW2900D-
NS-Grid-Tied-PV-Inverter-fig-30

Location: No. 90 Zijin Rd., New District, Suzhou, 215011, China
Web: www.goodwe.com
E-Mail [email protected]

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

GOODWE User Manuals

Related Manuals