  • Product: Emergency Bulkhead
  • Model: EM154C HO BKD 15S
  • Input Voltage: Indoor 220V 50Hz / 240V 60Hz
  • LED Type: GLOW
  • IP Rating: IP65
  • Color Temperature (CCT): 6500K
  • Lumen Output: 175lm
  • Power Consumption: 4.5W
  • Weight: 1.47kg
  • Dimensions (mm): 167 x 83 x 321

Product Usage Instructions

Installation

  1. Switch off the mains supply before installation.
  2. For Model A Ceiling, drill a hole in the base tray.
  3. Connect the battery to the converter.
  4. Connect the power supply to the LED board.

Lumen Adjustment

  • Switch the jumper position to select lower or higher lumen output.

Battery Replacement

  1. To replace the battery, disconnect it from the converter.
  2. Remove the old battery and replace it with a LiFePO4 -26650-6600mAh-6.4V battery.
  3. Connect the new battery to the converter.

Maintenance

  • Clean the luminaire with a dry cloth.
  • Ensure electrical connections are made by a qualified electrician.

FAQ

Q: What should I do if the red indicator is flashing?

A: The red indicator flashing indicates an abnormal battery or lamp connection. Check and rectify the issue promptly.

Q: How do I perform a function test in emergency mode?

A: Press the test button for 10 seconds to reset the time and initiate the function test.

WHAT’S IN THE BOX

FEATURES

DIMENSIONS

Inrush current

  • ATTENTION OBSERVE PRECAUTIONS FOR HANDLING ELECTROSTATIC SENSITIVE DEVICES.
  • The luminaire shall be installed by a qualified electrician and wired under the latest lEE electrical regulations or national requirements.
  • When the light source reaches its end of life the whole luminaire shall be replaced.
  • Clean with a dry cloth.
  • Philips Lighting warranty is applicable only if the indicated drivers are used.

INSTALLATION INSTRUCTION

Battery replacement

LiFePO4 -26650-6600mAh-6.4V

Luminous Intensity Distribution

Spacing Data (1 lux)

  1. For indoor use only.
  2. The luminaire complies with IEC60598-1IEC 60598-2-22.
    • The luminaire must be installed by a qualified electrician and wired under the latest IEE
    • Electrical regulations or the national requirements.
  3. Turn off the power supply before checking, installation, maintenance, or moving.
  4. Do not switch on before completing installation.
  5. Batteries shall only be replaced by the manufacturer his service agent or a similar qualified person.
  6. Batteries should be replaced when the luminaire no longer meets the 3-hour duration performance.
  7. Product mains surge immunity is 0.5/1KV (diff. / comm. mode). To prevent excessive currents and voltages from damaging the device, make sure that the power supply input is equipped with additional protection devices such as surge protectors. For any questions regarding the product’s surge protection, please consult the manufacturer’s professional.

Please inform yourself about the local waste disposal, separation, and collection system for electrical and electronic products and packaging. Please act according to your local rules and do not dispose of your old product and packaging with your normal household waste. The correct disposal of the packaging, your product, and/or batteries will help prevent potential negative consequences for the environment and human health. Batteries should be disposed of separately from the municipal waste stream via designated collection facilities. When disposing of a product that contains non-user replaceable batteries, the non-user replaceable batteries shall be removed by a professional.

Testing Record

  • Product:——————–
  • Location:———————-
  • Installation Date:————————

Emergency Bulkhead

Specifications For Self-Test

  • Function Test
    • The function test is conducted every month for 3 minutes to check whether the battery connection is abnormal and discharge the battery and the connection of the LED module.
  • Duration Test
    • An initial duration test is conducted when the battery is connected to the controller for the first time and connected to mains but after 24 hours of charging.
    • The yearly duration test is conducted for 3 hours on one day from the 300th day to the 365th day every year. It will also check the connection of the battery and LED module.

Description corresponding to the color and status of the charge indicator

Failure indication status should be checked and rectified as soon as possible.

Test button for manual inspection on function test or duration test mode of operation

Duration Description
Press for <2s Simulate emergency mode.
**** Press for 3-5s Start duration test manually. The test can be aborted by

pressing off (1-2s).

  • Must be conducted when the initial duration test finished and after another 24 hours of battery charging.

Press for 5-8s| Start the Function test manually for the 60s. The test can be aborted by pressing off (1-2s).
Press for >10s| Time Reset.

Note:

  • When the mains is on, the green indicator will be permanently on. It will check the connection of the battery and the connection of
  • LED module. If it is a non-maintained fitting, the connection of the LED module does not need to be checked. When the mains are off, no test will be performed.
  • The luminaires on which we want to perform the function and duration tests must be connected to the main supply for at least 24 uninterrupted hours. If the mains is off during these tests, the tests will be postponed for 3 days.
  • When the fault is corrected, the indicator will only be reset to its normal status after the mains are reconnected or the test switch is pressed.
  • Accuracy of the timing of the test interval is ensured that it has an accuracy of ±75 s per week. The timing function will be retained through periods of mains supply failure or interruption for up to 7 days.

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

Related Manuals