HINKLEY FR30526 Extra Large Single Tier Chandelier Installation Guide
- July 15, 2024
- HINKLEY
Table of Contents
A Division of Hinkley Lighting, Inc.
33000 PIN OAK PARKWAY
AVON LAKE, OHIO 44012
toll free 800.446.5539
phone 440.653.5500
Hanging in structures for fixtures
weigh more than 50lbs
IS19-50 hanging instructions
Drawing1 – Fixture Assembly
-
Shut off electrical current before starting. If the fixture you are replacing is turned on and off by a wall switch, simply turn the switch off. If not, remove the appropriate fuse (or open the drcuit breakers) until the fixture is dead.
• DO NOT RESTORE CURRENT – EITHER BY FUSE, BREAKER, OR SWITCH – UNTIL THE NEW FIXTURE IS COMPLETELY WIRED AND IN PLACE. -
Supply wires shall enter the outlet box (A) through any knockout except the top center knockout – see Drawing 1.
-
Fixture is to be mounted by a 3/8 – 18 NPSM thread steel pipe, 34″ threads at both ends (not supplied). Pipe should be anchored to structure or bridging member with sufficient strength to support 4 times the fixtures weight – see Drawing 2.
-
Adjust pipe so ¥2” of 3/8 steel pipe extends into the junction box, at the center knock out.
-
Please refer to the back of this sheet for the safety cable installation instructions and ONLY complete steps 1 and 2 at this time.
-
Thread pipe coupler (B) onto protruding pipe inside outlet box.
Secure in place by tightening allen head screw (C) — see Drawing 1. -
Thread hexnut (D) onto thread nipple (E). Thread nipple (E) into coupler (B). Secure in place by tightening hexnut (D) against coupler (B) and then tightening allen screw (F).
-
Thread hexnut (G) onto nipple (E). Slip ground wire lip (H) over nipple (E) and thread hexnut (J) onto nipple (E).
-
Weave ground wire, supply wire, and safety cable through chain, up through canopy and out the opening on the side of coupler (B). Make wiring connections using IS-18.
-
Secure canopy (X) using hex nut (Y) and nipple (E)
-
Next cover hex (Y) with finial (Z)
-
Continue the page to for glass installation
Drawing2 – Installation Example
Assembly Instructions 30526
DRAWING 2 – SHADE DETAIL
-
Find a clear area in which you can work.
-
Unpack fixture and glass from carton.
-
Carefully review instructions prior to assembly.
-
Next use quick connectors to secure chain and stems to the main body of fixture
-
Lamp fixture using appropriate E12 base bulbs (L )
-
Next screw on glass (G) to socket (M) -Drawing
-
Repeat process for the other piece of glass.
-
Fixture can now be powered on
SAFETY WARNING: READ WIRING AND GROUNDING INSTRUCTIONS (IS 18) AND ANY ADDITIONAL DIRECTIONS. TURN POWER SUPPLY OFF DURING INSTALLATION. IF NEW WIRING IS REQUIRED, CONSULT A QUALIFIED ELECTRICIAN OR LOCAL AUTHORITIES FOR CODE REQUIREMENTS.
I. S. 1 8 wring grounding instructions
Drawing1 – Flush Mount
SAFETY WARNING: READ WIRING AND GROUNDING INSTRUCTIONS (IS 18) AND ANY
ADDITIONAL DIRECTIONS.
TURN POWER SUPPLY OFF DURING INSTALLATION. IF NEW WIRING IS REQUIRED, CONSULT
A QUALIFIED ELECTRICIAN OR LOCAL AUTHORITIES FOR CODE REQUIREMENTS
wiring instructions
Indoor Fixtures
- Connect positive supply wire (A) (typically black or the smooth, unmarked side of the two-conductor cord) to positive fixture lead (B) with appropriately sized twist on connector – see Dra wings 1 or 2.
- Connect negative supply wire (C) (typically white or the ribbed, marked side of the two-conductor cord) to negative fixture lead (D).
- Please refer to the grounding instructions below to complete all electrical connections
Outdoor Fixtures
-
Connect positive supply wire (A) (typically black or the smooth unmarked side of the two-conductor cord) to positive fixture lead (B) with appropriately sized twist on connector — see Drawings 2 or 3.
-
Connecting tive supply wire (C) (typically white or the ribbed, marked side of the two-conductor cord) to negative fixture lead (D).
-
Cover open end of connectors with silicone sealant to form a watertight seal.
• If installing a wall mount fixture, use caulk to seal gaps between the fixture mounting plate (backplane) and the wall. This will help prevent water from entering the outlet box. If the wall surface is lap siding, use caulk and a fixture mounting platform specially. -
Please refer to the grounding instructions below to complete all electrical connections.
grounding instructions
Drawing 3 – Post – Mount
Flush Mount Fixtures
For positive grounding in a 3-wire electrical system, fasten the fixture
ground wire (E) (typically copper or green plastic coated) to the fixture
mounting strap (M) with the ground screw (S) – see Drawing 1.
Note : On straps for screw supported fixtures, first install the two mounting
screws in strap. Any remaining tapped hole can be used for the ground screw.
Chain Hung Fixtures
Loop fixture ground wire (E) (typically copper or green plastic coated) under
the head of the ground screw (S) on fixture mounting strap (M) and connect to
the loose end of the fixture ground wire directly to the ground wire of the
building system with appropriately sized twist-on connectors – see Drawing 2.
Post-Mount Fixtures
Connect fixture ground wire (E) (typically copper or green plastic coated)
to power supply ground with appropriately sized twist-on connector inside
post. Cover open end of connector with silicone sealant to form a watertight
seal -see Drawing 3.
33000 Pin Oak Parkway, Avon Lake,
OH 44012 800.446.5539 / 440.653.5500
hinkley.com
Documents / Resources
|
HINKLEY FR30526 Extra Large Single Tier
Chandelier
[pdf] Installation Guide
FR30526 Extra Large Single Tier Chandelier, FR30526, Extra Large Single Tier
Chandelier, Single Tier Chandelier, Tier Chandelier, Chandelier
---|---
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>