EATON LoadStar-S Platform Leaves Data Cable-Controlled Luminaires Instructions

June 5, 2024
EATON

EATON LoadStar-S Platform Leaves Data Cable-Controlled Luminaires

EATON
LoadStar-S Platform Leaves Data Cable-Controlled Luminaires
pp

Description of installation

Compact cabinet

  • Visible defects have to be announced immediately.
  • For installation all electronic components of the system must be covered up to protect them against dirt and filings.
  • Strip final circuits after introducing and deposit them onto connection terminal strip X1.1-X5.1,terminals 5 up to max. 72.
  • Connect bus lines with terminal strip ACU Module.
  • Connect mains with terminal strip X8/Q1 and battery line with terminal strip X8/Q2.
  • Deposit shunting lines mains /battery onto terminal X7/X9.
  • Check all connections about accuracy and stability.
  • Do the revision-marking of the final circuits on the modules.
  • Commissioning and other work
    • Remove all fuses.
    • Short the circuits and carry out the isolation measurement.
    • Remove jumper and reinsert the circuit fuses.
    • Switch on the mains voltage and insert the mains fuses.
    • Check voltage.
    • Before insertion battery fuse check the voltage and polarity.
    • Activate fault analysis by pressing the key ‘FT’ for a function test.
    • Set up system as specified in the mounting and operating instructions of LoadStar-S with STAR-technology.

**Stand-alone cabinet

EATON LoadStar-S Platform Leaves Data Cable-
Controlled Luminaires 2**

Example of installation

  1. Sub distribution board general lighting

  2. Light switch general lighting

  3. General lighting

  4. Staircase light push buttons incl. glow lamp

  5. DLS/3Ph bus module for switching the connected safety lighting and monitoring up to 3 phases.

  6. Final circuits of the safety lighting

  7. RS 485 bus. For connecting max. 25 modules. Max. line length for line topology 1200 m. Type of cable: IY(ST)Y 4 x 2
    x 0.8 mm². If line length longer than 1200 m a repeater/router has to be installed.

  8. Terminal resistance 120 Ohm terminates the bus at the start and at the end to prevent reflections.

  9. ACU bus. Up to 32 LoadStar-S units can be networked via the internal ACU bus in order to forward actions assigned to
    one unit to all units. Bus topology: linear, double terminated (no stub lines permitted). Cable type (minimum requirement): IY(ST)Y 4 x 2 x 0.8 mm (twisted pair, shielded) – the shield of the cables must be connected to the SE terminals of the ACU module. The 120Ω ohm terminating resistor is integrated in the ACU modules and can be activated by the two upper DIL switches.

  10. Terminal resistance 105 Ohm terminates the bus at the start and at the end to prevent reflections.

  11. Terminal strip X1.1, to connect the bus lines, for central switch of the manual phase monitors, potential-free signal
    contacts, analog inputs.

  12. Final circuits safety lighting. For connection to 5 up to max.88 circuits on a 3-level-isolating neutral terminal acc. to
    system equipment and type.

  13. Touch Display, for configuration and monitoring of the components.

  14. Circuit change-over module SKU CG-S, 1 x 6 A, 2 x 3 A and 4 x 1.5 A.

  15. PSU Module for supplying external and internal modules with 24V DC

  16. BCM.1 Battery Control Module

  17. Charging Module CM.1 1,7 A

  18. 230/400V 50Hz mains circuit connection one or three phase, acc. to type of system

  19. 230/400V 50Hz distribution mains one or three phase, acc. to type of system.

  20. Temperature sensor

  21. 216V lead acid battery acc. to EN 60896-2. 5.5 up to 308 Ah acc. to type of system.

  22. 216V battery circuit connection

  23. 216 V DC distribution to battery

www.ceag.de