Centurion Systems (Pty) Ltd reserves the right to make changes to the product described in this manual without notice and without obligation to notify any persons of any such revisions or changes. Additionally, Centurion Systems (Pty) Ltd makes no representations or warranties with respect to this manual. No part of this document may be copied, stored in a retrieval system or transmitted in any form or by any means electronic, mechanical, optical or photographic, without the express prior written consent of Centurion Systems (Pty) Ltd.

Introduction

The D6 SMART is a domestic and light-industrial operator designed to open and close sliding gates weighing up to 600kg. A custom-designed gearbox moulded from robust engineering polymers, coupled to a powerful 24V DC motor, provides fast and reliable automation for entrances to homes and small housing estates.
The system operates off two 12V batteries housed inside the operator using a switch-mode charger to maintain the batteries in a fully-charged state. The batteries provide critical power failure protection.
A non-contact Hall Effect Sensor was selected to ensure reliability and positional accuracy.
The Hall Effect Sensor is highly resistant to dust, oil, dirt or insect ingress, therefore ensuring that the D6 SMART opens and closes gates reliably and accurately.
Advanced features of the D6 SMART logic controller include:

  • Interactive graphic user interface via a smartphone application
  • Automated setup of gate end-points (limits)
  • Independently-adjustable motor speed in both opening and closing directions
  • Fail-safe collision detection and auto-reverse (adjustable sensitivity)
  • Smooth, adjustable start/stop (ramp-up/ramp-down)
  • Multiple operational modes
  • Selectable, adjustable Autoclose
  • Pedestrian (partial) opening
  • Positive Close Mode
  • Independent safety inputs for opening and closing beams
  • Automatic beam test for both opening and closing beams
  • Advanced lightning/surge protection
  • Onboard NOVA code-hopping radio receiver with full channel-mapping capability (limited to 1500 remotes 1)
  1. Multiple buttons per remote can be used

1.1. Important Safety Information

ATTENTION!

To ensure the safety of people and possessions, it is important that you read all of the following instructions.
Incorrect installation or incorrect use of the product could cause serious harm to people.
The installer, being either professional or DIY, is the last person on the site who can ensure that the operator is safely installed and that the whole system can be operated safely.

Warnings for the Installer
CAREFULLY READ AND FOLLOW ALL INSTRUCTIONS before installing the product.

  • All installation, repair, and service work to this product must be carried out by a suitably qualified person

  • This appliance is not intended for use by persons (including children) with reduced physical, sensory or mental capabilities, or lack of experience and knowledge, unless they have been given supervision or instruction concerning use of the appliance by a person responsible for their safety

  • Do not activate your gate unless it is in view and you can determine that its area of travel is clear of people, pets, or other obstructions

  • NO ONE MAY CROSS THE PATH OF A MOVING GATE
    always keep people and objects away from the gate and its area of travel

  • NEVER LET CHILDREN OPERATE OR PLAY WITH THE GATE CONTROLS

  • Secure all easily-accessed gate opener controls in order to prevent unauthorised use of the gate

  • Do not in any way modify the components of the automated system

  • Do not install the equipment in an explosive atmosphere: the presence of flammable gases or fumes is a serious danger to safety

  • Before attempting any work on the system, turn off electrical power to the operator and disconnect the batteries

  • The Mains power supply of the automated system must be fitted with an all-pole switch with contact opening distance of 3mm or greater; use of a 5A hydraulic breaker with all-pole circuit break is recommended

  • Make sure that an earth leakage circuit breaker with a threshold of 30mA is fitted upstream of the system

  • Never short-circuit the battery and do not attempt to recharge the batteries with power supply units other than that supplied with the product, or manufactured by Centurion Systems (Pty) Ltd

  • Make sure that the earthing system is correctly constructed and that all metal parts of the system are suitably earthed

  • Safety devices must be fitted to the installation to guard against mechanical movement risks such as crushing, dragging and shearing

  • Always fit the warning signs visibly to the inside and outside of the gate

  • The installer must explain and demonstrate the manual operation of the gate in case of an emergency and must hand over the User Guide/Warnings to the user

  • The installer must explain these safety instructions to all persons authorised to use this gate, and be sure that they understand the hazards associated with automated gates

  • Do not leave packing materials (plastic, polystyrene, etc.) within reach of children as such materials are potential sources of danger

  • Dispose of all waste products like packing materials, worn-out batteries, etc., according to local regulations

  • Always check the obstruction detection system, and safety devices for correct operation

  • Neither Centurion Systems (Pty) Ltd, nor its subsidiaries, accepts any liability caused by improper use of the product, or for use other than that for which the automated system was intended

  • This product was designed and built strictly for the use indicated in this documentation; any other use, not expressly indicated here, could compromise the service life/operation of the product and/or be a source of danger

  • Everything not expressly specified in these instructions is not permitted

1.2. Safe Disposal of Batteries
ATTENTION!

  • Do not incinerate
  • Do not short the battery terminals
  • Do not charge in a gas tight container
  • Do not open
  • Recharge after use
  • Flush with water at once if contact is made with electrolyte (acid)

WARNING! WARNING! WARNING! WARNING! WARNING!
SAFETY FIRST

MOVING GATE CAN CAUSE SERIOUS INJURY OR DEATH!
KEEP CLEAR! GATE MAY MOVE AT ANY TIME!
DO NOT ALLOW CHILDREN TO OPERATE THE GATE OR PLAY IN THE NEAR VICINITY OF THE GATE.
1.3. Lightning Protection
The electronic controller utilises the same proven surge protection philosophy that is used in all our products. While this does not guarantee that the unit will not be damaged in the event of a lightning strike or power surge, it greatly reduces the likelihood of  such damage occurring. The earth return for the surge protection is provided via the mains power supply earth and/or earth spike located next to the operator.
In order to ensure that the surge protection is effective, it is essential that the unit is properly earthed.
1.4. Theft Protection
While care has been taken in the design of the D6 SMART to prevent unauthorised removal (theft) of the unit, an optional steel theft-deterrent cage with a patented design is also available for added peace of mind.
If a theft-deterrent cage is required, be sure to leave enough clearance from pillars, etc. (Section 7.1.2. – “Minimum Clearances”).

Specifications

2.1. Physical Dimensions

CENTURION D6 SMART Sliding Gate Operator - D6 SMART PHYSICAL
DIMENSIONS

2.2. Technical Specifications

Input voltage¹ 110V – 240V AC 50/60Hz¹
Current consumption (mains) 430mA
DX1 Battery charger current output 1.3A@ 27.6V (+/-5%), 38W
Maximum number of operations per day 150 ³,⁶
Duty cycle – Mains present ²,³ 50%
Motor power supply Battery-driven

(Standard Capacity – 2x12V)
Current consumption (motor at rated load)| 13A
Input / Output sink currents (Max. accessory current draw)
I/O 1-4| 100mA (12/24V)
I/O 5 and 6| 3A (12/24V) 10sec Pulse

TABLE 1

This equipment is compliant with Class A of CISPR 32 / EN 55032.
In a residential environment, this equipment may cause interference.

2.2. Technical Specifications Continued

Fuse Protection Type Rating
Main Control Card Serviceable 25A
**** Aux. Supply **** Resetable Fuse 12V 600mA 8 or 24V 3A (10sec

Pulse)
Charger (Mains Supply)| Non-serviceable| 3A slow-blow
Motor push force – starting| 30kgf
Motor push force – rated| 17kgf
Gate mass – maximum| 600kg
Gate length – maximum| 100m
Gate speed (varies with load) 4| Up to 35m/min @ 17kgf
Manual Override| Lockable with key release
Operations whilst in battery backup mode with 7.2Ah batteries| Operating Mode
Power Saving 15m/min 7kgf| Power Saving 15m/min 17kgf| Normal 30m/min 7kgf| Normal 30m/min 17kgf
Half day 5,6| 209| 96| 102| 70
Full day 5,6| 183| 87| 79| 59
Operations whilst in battery backup mode with 7Ah 28 W batteries| Operating Mode
Power Saving 15m/min 7kgf| Power Saving 15m/min 17kgf| Normal 30m/min 7kgf| Normal 30m/min 17kgf
Half day 5,6| 197| 87| 70| 42
Full day 5,6| 170| 75| 45| 30
Collision Sensing| Electronic
Operating temperature range| -15°C to +50°C
Onboard receiver type| Code-hopping multichannel receiver with selective add and delete
Receiver code storage capacity| 1500 Remotes 7
Receiver frequency| 433.92MHz
Degree of protection| IP55
Mass of unit packed (with standard kit, but excl. rack and battery)| ** 9.1kg
Packaging dimensions (with standard kit, but excl. rack and battery)**| 325mm wide x 244mm deep x 445mm high

  1. Can operate off a solar supply, consult your local dealer for assistance.
  2. Based on 25°C ambient temperature and unit not in direct sunlight.
  3. Based on a motor push force of less than 50% of rated (Starting and Running forces).
  4. Gate opening and closing speeds can be configured to run slower depending on the requirements of individual installations.
  5. Can increase battery capacity for longer standby times.
  6. Based on 4m gate, excluding all accessories.
  7. Multiple buttons per remote can be used.
  8. For previous controller versions.

Product Identification

CENTURION D6 SMART Sliding Gate Operator - PRODUCT
IDENTIFICATION

1. 12V Battery¹
2. D6 SMART Cover
3. DX Control Card
4. Cable Shield
5. Gearbox
6. M10 Nut (17mm Socket)
7. Spring Washer
8. Top Height Adjuster (19mm Socket)
9. Bottom Height Adjuster
10. Heavy Duty M12 Washer
11. M10 Half-Nut
12. D6 SMART Foundation Plate| 13. Mounting Bolt
14. Lower Battery Tray
15. Cable Trunking
16. Earth Harness
17. Switch-Mode 1.3A charger
18. Battery Harness
19. Power Supply Harness
20. Accessory Tray
21. Accessory Retaining Door
22. Top Battery Stabiliser
23. Release Handle
24. Camlock
---|---

1. Batteries are not supplied with the D6 SMART. The D6 SMART supports both 6Ah and 7.2Ah variants.

Required Tools and Equipment

CENTURION D6 SMART Sliding Gate Operator - Tools

New Site Installation Preparation

5.1. General Considerations for the Installation
Always recommend the fitment of additional safety equipment such as safety edges and safety beams, for additional protection against entrapment or other mechanical risks.
Check that no pipes or electrical cables are in the way of the intended installation.
Check that enough space is available for the gate operator, specifically for the release handle (See Section 7.1.2. – “Minimum Clearances”).
Check for loose, sandy soil if installing a foundation, as the soil condition may require a larger foundation.
Never fit the operator on the outside of the gate, where the public have access to it.

Install the gate operator only if:

  • It will not pose a hazard to the public
  • There is sufficient clearance to a roadway and/or public thoroughfares
  • The installation meets all municipal and/or local authority requirements once completed
  • The gate mass and application are within the operator specifications
  • The gate is in good working order, meaning:
  • that it opens and closes freely;
  • does not move on its own if left in any position;
  • it can be installed to have sufficient clearance between moving parts when opening and closing to reduce the risk of personal injury and entrapment;
  • Pushbuttons or key-switches, when required, can be positioned so that the gate is in line-of-sight of the user

5.2. End-Stops
Fit opening and closing end-stops capable of stopping the gate at rated speed. Refer to the specifications at the beginning of this manual for the operating speed.
Make H1 >H2 to ensure gate will not jump over the endstop.

CENTURION D6 SMART Sliding Gate Operator - FITTING END-
STOPS

5.3. Guide-rollers and Anti-lift Brackets
Guide-rollers must be installed to ensure that the gate is held vertical. For improved safety, fit additional support posts to prevent the gate from falling over should the guide-rollers fail.
To prevent unauthorised access, fit anti-lift brackets as shown.
The gap between the anti-lift bracket and the gate must be less than 5mm.
Ensure that the gate cannot be lifted off the motor pinion with the anti-lift bracket fitted.

CENTURION D6 SMART Sliding Gate Operator - ROLLERS

5.4. Starting and Running Forces
Test the starting force of the gate as per the diagram. Use a pull scale in both directions to determine the maximum amount of pull force required to set the gate in motion.
Determine the running force of the gate by continuing to pull on the scale with just sufficient force to keep it running.
Read and note the maximum value in kgf (kilogram-force) shown on the scale.
Where possible, determine the gate mass.
Our warranty will be void if the pull force and / or gate mass exceeds the below operator specifications:

  • Starting force – 30kgf
  • Running (rated) force – 17kgf
  • Maximum gate mass – 600kg

CENTURION D6 SMART Sliding Gate Operator - RUNNING
FORCES

5.5. Cabling Requirements

CENTURION D6 SMART Sliding Gate Operator - Cabling
Requirements

Legend

  1. MAINS SUPPLY CABLE: 90V – 240V AC mains cable via double-pole mains isolator-switch(3coreL.N.E.1.5mm2  SWA) 1,2
  2. Optional intercom cable from motor to dwelling   (n1 + 6 core3  0.22mm 2  multi-strand shielded cable)
  3. Optional intercom cable from motor to entry panel   (n2 0.22mm2  multi-strand shielded cable)
  4.  Optional but recommended infrared safety beams   (3 core 0.22mm 2  multi-stranded)4
  5. Optional access control device (3 core 0.22mm2  multi-stranded)
  6. Optional pedestrian key-switch (2 core 0.22mm2  multi-stranded) OR
  7. Optional keypad (3 core 0.22mm2  multi-stranded)4
  8. Optional external radio receiver (3 core 0.22mm2  multi-stranded)5
  9. Optional pillar lights (3 core LNE SWA, size according to power requirements)6
  10. Optional ground loop for free-exit   (1 core 0.5mm2  multi-stranded – silicone coated)7

n1 means the number of cores required by an intercom.
n2 means the number of cores required by an intercom.

  1. Possibly increase cable thickness if pillar lights are installed.

  2. Type of cable must adhere to municipal bylaws but typically SWA (steel wire armoured) cable is recommended.
    The armouring provides excellent screening, which gives better protection against lightning – earth one end of the screening).

  3. Allows for all features such as pedestrian opening, status LED, etc., to be operated from the intercom handset inside the dwelling.
    Number of cores and type of cable could vary depending on brand of access control system being used.

  4. Wireless accessories are available. Please refer to www.censys.com for further information.

  5. For optimum range, an external receiver can be mounted on the wall.

  6. Requires an external relay.

  7. Consult manufacturer of loop detector for specific details.

Lubrication

The internal gearset of the D6 SMART is lubricated by means of an oil bath.
The D6 SMART is supplied with oil in its gearbox and does not require routine oil changes.

OPERATOR INSTALLATION

7.1. New Site Installations
When installing the D6 SMART, it is important to take note of the information found in Sections 7.1.1. and 7.1.2. when determining the position of the
Foundation Plate, and the height of the D6 SMART in relation to the gate that is to be automated.

7.1.1. Locating an Initial Reference Point
Firstly, it is necessary to establish a reference point. To do this, manually open and close the gate so that it moves past a stationary point (i.e. a vertical spike), and determine which part of the gate (including its wheels) protrudes the furthest towards where the D6 SMART will be installed. Refer to the examples shown below.

Check for wheels, palisade, uprights, etc. that could potentially collide with the pinion.

CENTURION D6 SMART Sliding Gate Operator - FINDING A REFERENCE
POINT

Once the point which protrudes the furthest has been found, this will be the reference point to be used when finding the optimum position for the D6 SMART.

7.1.2. Minimum Clearances
Below are site plan examples illustrating the minimum clearances required when installing the D6 SMART.

CENTURION D6 SMART Sliding Gate Operator - SIDES

7.1.3. Locating the Operator’s Position
To ensure that the operator does not protrude into the driveway, install the base plate at least flush with the driveway entrance.
It is typical to mount the rack above the pinion as shown in Figures 11, 13 and 15 for each type of rack considered. However, in each case, Figures 12, 14 and 16 show the rack mounted underneath.

If there is space to mount the rack underneath without fouling the ground as the gate moves, the following are the pros and cons:
Pros

  • The rack is more hidden from view
  • It provides a very effective anti-lift bracket
  • It ensures that, since the gate beds in, the rack does not drop onto the pinion, loading the operator unnecessarily

Cons

  • Rack teeth face up vertically, potentially collecting dirt
  • Could require the use of a custom bracket

The measurements given below are based on the three different racks supplied by Centurion Systems (Pty) Ltd and are to be used as guidelines only.

Steel Rack

CENTURION D6 SMART Sliding Gate Operator - STEEL RACK ABOVE
PINION

  1. Includes 3mm clearance required between rack and pinion
  2. Distance between bottom of the Foundation Plate and bottom edge of the Rack Tooth

The principles of installation on a Steel rack is to posotion in the middle of the output pinion with the operator fully forward on the slots.

CENTURION D6 SMART Sliding Gate Operator - STEEL RACK BELOW
PINION

  1. Includes 3mm clearance required between rack and pinion
  2. Distance between bottom of the Foundation Plate and top edge of the Rack Tooth

The principles of installation on a Steel rack is to posotion in the middle of the output pinion with the operator fully forward on the slots.

RAZ Rack

CENTURION D6 SMART Sliding Gate Operator - RAZ RACK ABOVE
PINION

  1. Includes 3mm clearance required between rack and pinion
  2. Distance between bottom of the Foundation Plate and bottom edge of the Rack Tooth

The principles of installation on a RAZ rack is to posotion in the middle of the output pinion with the operator fully forward on the slots.

CENTURION D6 SMART Sliding Gate Operator - BELOW
PINION

  1. Includes 3mm clearance required between rack and pinion
  2. Distance between bottom of the Foundation Plate and top edge of the Rack Tooth

The principles of installation on a RAZ rack is to posotion in the middle of the output pinion with the operator fully forward on the slots.

Nylon Angle Rack
If using nylon angle rack, please ensure that the weight and pull force of the gate does not exceed the strength limit of the rack.

CENTURION D6 SMART Sliding Gate Operator - NYLON RACK ABOVE
PINION

  1. Includes 3mm clearance required between rack and pinion
  2. Distance between bottom of the Foundation Plate and bottom edge of the Rack Tooth

The principles of installation on a Nylon rack is to posotion in the middle of the output pinion with the operator fully forward on the slots.

CENTURION D6 SMART Sliding Gate Operator - NYLON RACK

  1. Includes 3mm clearance required between rack and pinion
  2. Distance between bottom of the Foundation Plate and top edge of the Rack Tooth

The principles of installation on a RAZ rack is to posotion in the middle of the output pinion with the operator fully forward on the slots.

7.1.4. Foundation Plate Installation
7.1.4.1. Assembling the Foundation Plate

The Foundation Plate / Adaptor Plate is not supplied with this operator

Place the three mounting bolts through the holes of the foundation plate an secure them into position using three half-nuts.
The M10 half-nuts should be tightened to 20Nm.
The foundation plate can either be set into a new concrete foundation, as in Section 7.1.4.2, or bolted down onto an existing concrete plinth as in Section 7.1.4.3.

CENTURION D6 SMART Sliding Gate Operator - TOP VIEW

7.1.4.2. New Concrete Foundation
Using a pair of pliers, gently bend the two tabs of the foundation plate down to a 90° angle as shown in Figure 19.
Again, using a pair of pliers, gently bend the two legs on each tab to an angle of 90° in opposite directions as shown in Figure 20.

CENTURION D6 SMART Sliding Gate Operator - New Concrete
Foundation

Lay the cabling conduit so that it routes the cables to the back of the Foundation Plate. Ensure that 30mm of conduit protrudes above the concrete.
Using medium-strength concrete (25MPa), cast the plinth according to the dimensions as shown in Figure 21.

CENTURION D6 SMART Sliding Gate Operator -1

When using a concrete foundation, it is recommended that the foundation plate is welded to the rail/track of the gate using a short length of flat bar, as shown in Figure 22.
This makes it possible to complete the whole mechanical and electrical installation without having to wait for the concrete to set. After completing the installation, the concrete can be poured and the operator left in manual mode until the concrete has set. Do not operate the motor until concrete has completely set.

CENTURION D6 SMART Sliding Gate Operator 2

7.1.4.3. Existing Concrete Plinth

If bolting onto an existing concrete plinth, place the foundation plate down in the correct position and use the plate as a template for marking the rawl bolt holes.
Check that the M10 halfnuts are tightened to 20Nm on the mounting bolts.
Rerouting of existing cables may be necessary.

CENTURION D6 SMART Sliding Gate Operator - Existing Concrete
Plinth

7.2. Retro-fit Installations (Existing Sites)
The D6 SMART has been designed to retro-fit into most existing D3, D5, or D5-Evo installations, with the following provisions;

  • If the unit is installed with the gate in the closed position and the unit on the lefthand side (from the inside of the property), the rack should extend at least 75mm past the centre line of the existing pinion
  • If the existing unit is mounted with the maximum clearance to the foundation plate, the new unit will require that the rack be re-adjusted to obtain the correct mesh between the rack and pinion, as the existing bolts will be too short

If the existing foundation plate is in a good condition, it is not necessary to replace it with the D6 SMART Foundation Plate. However, if the existing foundation plate is corroded or needs to be replaced for whatever reason, the D6 SMART foundation plate can
accommodate the existing footprint without the need to re-route cable conduits.

7.2.1. Retro-fitting if the Existing Foundation Plate is Unusable

Thoroughly inspect the existing foundation plate to determine whether or not it is fit to be reused.
A foundation plate that is corroded, or otherwise damaged should be discarded and replaced with the D6 SMART foundation plate.
Follow the procedure found under Section 7.1.4.3. – “Existing Concrete Plinth”.

CENTURION D6 SMART Sliding Gate Operator - fitting

There is an allocated slot for existing conduit from previous D3, D5, and D5-Evo installations as shown in Figure 24.

7.3. Conduit and Cable Length
Route the cables as determined in Section 5.5 – “Cabling Requirements”. Make sure that the conduits protrude above the concrete foundation.
The mains cables should protrude 360mm above the concrete foundation, and all signal cables (i.e. beams, etc.) 550mm above the concrete foundation, as shown in Figure 25.

CENTURION D6 SMART Sliding Gate Operator - fitting1

7.4. Preparing the D6 SMART for Installation

Open the Camlock Cover, and insert the Operator Key into the Camlock. Unlock it by turning the key anti-clockwise.
There is no need to open the Release Handle to remove the cover of the D6 SMART.

CENTURION D6 SMART Sliding Gate Operator - D6 SMART

Remove the cover of the D6 SMARTto expose the internal components, and place it one side in a safe location.

CENTURION D6 SMART Sliding Gate Operator - D6 SMART1

7.4.1. Removing the Charger
Disconnect the Charger from the D6 SMART Control Card at either Point “A” or Point “B”.
If the disconnection is made at Point “A”, note that there are two connector blocks that need to be disconnected from the Control Card.
Disconnect the Earth Harness from the Charger at Point “C”, and store it in a safe place.

CENTURION D6 SMART Sliding Gate Operator - D6 SMART2

Remove the Charger from the lower battery tray by gently pushing the Charger slightly down whilst pulling it towards the front of the D6 SMART. It should slide forward and off with ease.

CENTURION D6 SMART Sliding Gate Operator - D6 SMART3

7.4.2. Removing the Lower Battery Tray

CENTURION D6 SMART Sliding Gate Operator - Lower Battery
Tray

To remove the Lower Battery Tray, firstly ensure that the Camlock is in the “unlocked” position (Figure 30 marked as “A”). Open the release handle until the Camlock Cam is visible.
Using a flat screwdriver, lever the left and right Tabs inward, lift the Lower Battery Tray up, and then out towards the front of the D6 SMART.

7.4.3. Removing the Control Card

Disconnect the Motor Wires at Point “D” and the Override Sensor Harness at Point “E” from the Control Card as Shown in Figure 32.

Remove the Control Card by pushing the right tab behind the Control Card backwards.
This will allow the Control Card to hinge forward.

Lift the Control Card upwards and away form the D6 SMART, which will unhinge it from the hinge tabs found on the sides of the Control Card.
Take care not to snag the remaining harnesses in the harness retainers when removing the Control Card from the platform.
Store the Control Card in a safe place.
The D6 SMART is now ready to be mounted onto the foundation plate.

7.5. Mounting the Gearbox

For a new site installation, place a Half-nut and a Bottom Height Adjuster onto each Mounting Bolt as shown in Figure 35.
Note the orientation of the Bottom Height Adjusters.

Adjust the Half-nuts to be 12mm clear from the Foundation Plate.

CENTURION D6 SMART Sliding Gate Operator - Mounting the
Gearbox1

For a retro-fit installation, remove the original washers and height adjustment nuts from the existing foundation plate and then place a Half-nut and a Bottom Height Adjuster onto each existing Mounting Bolt, as shown in Figure 37.

Note the orientation of the Bottom Height Adjusters.
If the existing unit was mounted with the maximum clearance to the foundation plate, the new unit will require that the rack be re-adjusted to obtain the correct mesh between the rack and pinion.

7.5.1. Removing the Cable Shield
The Cable Shield needs to be removed before mounting the D6 SMART onto its Foundation Plate. This is done by levering the bottom end of the cable shield away from the motor until it unclips from the gearbox, and then slide it up.

CENTURION D6 SMART Sliding Gate Operator - Mounting the
Gearbox3

Once the Cable Shield has been removed, place the D6 SMART into position over the three Mounting Bolts, aligning them with the three slots at the bottom of the gearbox and rest the D6 SMART onto the Bottom Height Adjusters.

CENTURION D6 SMART Sliding Gate Operator - Mounting the
Gearbox4

Once the Gearbox is resting on top of the Bottom Height Adjusters, slide the D6 SMART as far as possible towards the gate to allow for later adjustment.

7.6. Routing the Cables
Route cables as determined in Section 5.5 – “Cabling Requirements”. “Point A” is the entry point for cables with the conduit installed at the back of the unit for new installations as shown in Figure 41.
Although “Point B” is the entry point for cables with the conduit from existing D3, D5 and D5-Evo installations, it is recommended to route the cable under the gearbox and out the back through “Point A” as shown in Figure 42.

CENTURION D6 SMART Sliding Gate Operator - LONGER
CABLES

The method shown in Figure 43 above, is recommended for retro-fit installations, as it is easier to remove the motor should it be necessary to do so at a later stage. However, cable lengthening may be required.
Should the existing cables for a retro-fit installation be too short to route through “Point A” as shown in Figure 43 on the previous page, they can be routed directly through “Point B” to accommodate the shorter length. Note that routing the cables through “Point B” as shown in Figure 44, may make it more challenging to remove the D6 SMART for whatever reason at a later stage.

CENTURION D6 SMART Sliding Gate Operator - SHORTER
CABLES

Replacing the Cable Shield onto the Gearbox

Tilt the top of the Cable Shield towards the Gearbox, and slide it down so that the top of the Cable Shield is flush with the top edge of the Gearbox.

CENTURION D6 SMART Sliding Gate Operator - Cable Shield
onto

From the other side of the gate, firmly push the bottom sides of the Cable Shield inward, towards the gearbox.
Two clicks will be heard (one from each side of the Cable Shield) if the Cable Shield has engaged with the gearbox correctly.

7.7. Manual Override
Before mounting the rack to the gate, ensure that the D6 SMART is in Manual Override. Follow the instructions below.

To disengage (Manual Override) the motor, ensure that the Camlock is in the “unlocked” position, and pull the Release Handle as far left as it will go. The Motor will then be placed in a temporary state of disengagement.

Manual Override Latching
In the event of a power failure, it may be required to lock the cover in place whilst “latching” the manual release (i.e. manual release permanently enabled).
This helps prevent theft of the unit, or its components, and provides full protection from the elements.
With the release handle in the open position, slide the Override Cam located on the inside of the handle towards the gearbox, and a “click” can be heard once it has located correctly. Return the handle to the closed, or locked, position. This allows continued manual operation of the gate while ensuring that the cover remains securely locked in place. See Figure 48.
To re-engage the D6 SMART (i.e. take the operator out of latched Manual Override), push the Release Handle Override Cam to the left and then slide it towards the Camlock. See Figure 49.

CENTURION D6 SMART Sliding Gate Operator - Cable Shield
onto2

7.8. Height Adjustment
The D6 SMART’s unique Height Adjustment System adjusts from the top of the gearbox.
This adds further security to the system, as it is not possible to access the lock nuts from the outside of the gearbox.

CENTURION D6 SMART Sliding Gate Operator - Height
Adjustment

Only add the Spring Washers and Lock Nuts once the Rack has been installed and the operator height is correct. See Section 7.9.2. – “Finalising the Height Adjustment”.
Place a Top Height Adjuster onto each Mounting Bolt so that it engages with the teeth on the Bottom Height Adjuster.

Note the orientation of the Top Height Adjuster as shown in Figure 50 and 51.
Using a ratchet and a 19mm socket, turn the Top Height Adjuster anticlockwise to lift the Operator, or turn it clockwise, to lower the Operator.
Using a spirit level, ensure that the Operator is level. If not, use the Height Adjusters to level the Operator.

7.9. Mounting the Rack
The rack must be securely mounted to the side of the gate. It must be parallel with the gate rail and there must be a 2-3mm gap between the rack teeth and the teeth of the pinion.
Before mounting the rack, raise the operator an additional 3mm. Ensure that the D6 SMART Gearbox is in Manual Override. Refer back to Section 7.7 – “Manual Override”.

Start with the gate either fully-open or fully-closed. Slide the D6 SMART back towards the gate to where the Pinion will sit just under where the rack will be fixed to the gate.
Rest the rack directly onto the Pinion (let it mesh fully) while welding / bolting the rack into position.
Level the other end and fix that end to the side of the gate, as shown in Figure 55.

CENTURION D6 SMART Sliding Gate Operator - Height
Adjustment5

Refer to the instructions on how to fix the different types of rack to a gate in Section 7.9.1. – “Fitting Different Types of Rack to the Gate”.

Slide the gate halfway along the first section and level the unsecured end, ensuring that the rack is resting on the Pinion, not pressing down. Continue this way to fix all sections.
Before fully fixing each section of rack, slide the gate backwards and forwards along the section, checking that the rack is only resting on the Pinion, and not pressing down onto it.

CENTURION D6 SMART Sliding Gate Operator - Height
Adjustment6

Lower the operator 3mm to achieve the required 3mm tooth clearance. Ensure that operator mounting bolts are securely tightened.

7.9.1. Fitting Different Types of Rack to the Gate
Steel Rack

Fix the Steel Rack with the steel angle brackets provided. The brackets must be spaced no more than 300mm apart.

CENTURION D6 SMART Sliding Gate Operator - Steel Rack

When joining different lengths of Steel Rack, a simple way of ensuring that the correct pitch spacing is achieved, is to clamp a small off-cut between the two pieces.
Do not weld the off-cut to the gate or the join.

RAZ Rack

Fix the RAZ Rack to the side of the gate using the TEK screws provided.
Use the vertical slots in order to allow for adjustment.

When fitting RAZ Rack, it is easier to start on the right and work towards the left.
The RAZ Rack sections simply interlock with each other.

Fit an additional fixing screw through the horizontal slots to secure the rack to the gate directly above the Pinion when the gate is in the closed, pedestrian and open positions as shown in Figure 60.
Fit an addition screw through the horizontal slots at the ends of each section of Rack to further strengthen the joins.

CENTURION D6 SMART Sliding Gate Operator - RAZ Rack2

Nylon Angle Rack
Fix the Rack to the side of the gate using TEK screws.
Ensure that all the mounting holes provided in the angle section are used.

When joining two lengths together, simply butt each section firmly together to ensure that the correct pitch is achieved.

7.9.2. Finalising the Height Adjustment

Slide the D6 SMART awayfrom the gate so that the rack is centred above the Pinion.
Final adjustment to the position of the gearbox should be done at this point.

7.9.2.1. Placing and Routing the Earth Harness

Place the Ring Lug-end of the Earth Harness onto the mounting bolt on the right-hand side of the Gearbox.

To ensure that the Earth Harness is able to reach the Charger once connected to the mounting bolt, it is recommended that it is positioned at the angle depicted by the middle line, but not at an angle exceeding the lines at either side of it as the Earth Harness will not be able to reach the Charger.

Route the Earth Harness up to the left and place it into the Cable Management Clip as shown in Figure 68.
The Earth Harness will need to be routed under the battery at a later stage.

7.9.2.2. Placing the Spring Washers and Lock Nuts
Only add the Spring Washers and Lock Nuts once the Rack has been installed and the operator height is correct.
Place one Spring Washer and one Lock Nut onto each of the Mounting Bolts. Tighten all of the Lock Nuts with a 17mm socket to secure the Earth Harness and the height of the D6 SMART firmly in position.

CENTURION D6 SMART Sliding Gate Operator - Harness3

7.10. Re-assembling the D6 SMART
7.10.1. Override Sensor
If the Override Sensor has previously been removed, take note of how it is placed back into position correctly, before continuing with the installation.

CENTURION D6 SMART Sliding Gate Operator - OVERRIDE
SENSOR

7.10.2. Routing the Override Sensor Harness
It is important to ensure that the harness for the Override Sensor is routed through the correct location when inserting the Lower Battery Tray back into position.

The Override Sensor harness is routed directly in front of the electric motor.
There is a groove located in the middle of the Lower Battery Tray, on the motor’s side. The harness needs to be routed between the electric motor and the Lower Battery Tray here as the Lower Battery Tray is placed back into position.

7.10.3. Placing the Lower Battery Tray and Charger Back into Position
Ensure that the Camlock is in the “unlocked” position and that the Release Handle is partially open.
Place the Lower Battery Tray into position. Whilst doing this, route the cabling and harnesses through. A click from both sides will be heard if the tray is fitted correctly.

CENTURION D6 SMART Sliding Gate Operator - TRAY
PLACEMENTPlace the Charger back into position by aligning the three feet at the bottom of the Charger with the three slots found on top of the Lower Battery Tray.
Place the studs of the Charger into the three holes on the Lower Battery Tray. Firmly press the Charger down, and push it toward the Electric Motor, sliding it along the slots.

CENTURION D6 SMART Sliding Gate Operator - CHARGER
PLACEMENT

7.10.4. Placing the Control Card back into Position

Tilt the control card and align the wider gap with the clips shown in Figure 74.

CENTURION D6 SMART Sliding Gate Operator - CHARGER
PLACEMENT1

Once aligned, hinge the Control Card under the tab’s lip, and firmly press downward on both sides in front of the Control Card.
This will engage the Control Card into the hinges at the front of the Accessory Tray.
A click from both sides will be heard if this is done correctly.

CENTURION D6 SMART Sliding Gate Operator - CHARGER
PLACEMENT2

7.10.5. Reconnecting the Harnesses to the Control Card and Charger
Reconnect the Motor Wires at Position “A” and the Override Harness at Point “B” on the Control card.

The black motor wire is connected on the far Left of the Control Card, and the blue on the immediate right of the black.

CENTURION D6 SMART Sliding Gate Operator - Control

Reconnect the Charger Harness to the point from which it was disconnected earlier, either at Position “C” or at Position “D”.
If the connection is made at Point “C”, note that there are two connector blocks that need to be reconnected to the Control Card.CENTURION D6 SMART
Sliding Gate Operator - Control1 Utilise the Cable Retainers at the bottom of the accessory storage to neaten up the wiring, and the overall installation.
Connect the Earth Harness into the right-hand side of the Charger at Point “E”.

CENTURION D6 SMART Sliding Gate Operator - Control2

Completing the Installation

8.1. Fitting the Batteries

Gently push the left tab behind the Control Card backwards. This will allow the entire upper assembly to hinge forward.

CENTURION D6 SMART Sliding Gate Operator - Fitting the
Batteries

Place a Battery into the designated area found on top of the Lower Battery Tray on the left. Route the Power and Signal cables between the right Battery compartment and the Electric Motor then place the remaining Battery in it’s designated area on the right.

Note the orientation of the two Batteries. Ensure that the Battery Terminals always face the direction of the Charger.
Take extra care not to pinch the Earth Harness when placing the Battery on the right. The Earth Harness must be routed under this Battery and out the gap found in front of the Battery once in position.

CENTURION D6 SMART Sliding Gate Operator - Fitting the
Batteries1

Swing the upper assembly back into position over the batteries. A click should be heard if this is done correctly.
Failure to properly click the control card and upper assembly into place will result in erratic behaviour of the gate motor.

CENTURION D6 SMART Sliding Gate Operator - Fitting the
Batteries2

Connect both batteries up with the supplied harness, and ensure that it is connected to the left side of the Charger.
Route the accessory cables around the back of the Charger and through the cable retainers found in front of the Control Card.
Please ensure that the battery connections match the selected battery terminals RED to RED, BLACK to BLACK.

CENTURION D6 SMART Sliding Gate Operator - Fitting the
Batteries3

8.2. Accessory Installation and Storage
There are dedicated trays below the D6 SMART Control Card to conveniently install and store any accessories connected to the Operator.
Opening the two retaining doors, reveal the storage space for accessory products, such as the G-ULTRA, or External Receivers.

CENTURION D6 SMART Sliding Gate Operator - Storage

Wire the accessory device to the operator, place it into the space provided, and close the door.

CENTURION D6 SMART Sliding Gate Operator - Storage1

8.3. Wiring the Control Card on its Default Settings
The D6 SMART Control Card’s Input / Output terminals are defaulted with the following configuration;

Control Card Terminal Default Setting
I/O1 Trigger (TRG)
I/O2 Pedestrian (PED)
I/O3 Infrared Beam Close (IRBC)
I/O4 Gate Status
--- ---
I/O5 Unassigned
I/O6 Unassigned

8.3.1. Closing Infrared Beam Wiring (I5 Infrared Beams)

CENTURION D6 SMART Sliding Gate Operator - Closing Infrared Beam
Wiring

8.3.2. Closing Infrared Beam Wiring (Photon Infrared Beams)

CENTURION D6 SMART Sliding Gate Operator - Closing Infrared Beam
Wiring1

8.3.3. Wireless Photon SMART beams

CENTURION D6 SMART Sliding Gate Operator - Closing Infrared Beam
Wiring2

8.3.4. External Radio Receiver and Loop Detector Wiring

CENTURION D6 SMART Sliding Gate Operator - Closing Infrared Beam
Wiring3

8.3.5. Anti-tamper Alarm with Two Wizo-Link Devices

  • The trigger/TRG (green wire) in Figure 89 can be either wired into IO1 – IO6, depending on the sites individual needs
  • IO1 – IO6 can be configured using the MyCentsys Pro mobile application
  • IO1 is configured as trigger/TRG by default

Two WiZo-Link wireless modules may be connected to the system for a signal to be wirelessly relayed to a third party alarm in the event that the anti-tamper input is triggered.

CENTURION D6 SMART Sliding Gate Operator - ALARM WIRING WITH TWO
WIZOS

8.3.6. Solar Panel Wiring
8.3.6.1. Wiring a single Solar Panel

CENTURION D6 SMART Sliding Gate Operator - SINGLE SOLAR
PANEL

8.3.6.2. Wiring Two Solar Panels

CENTURION D6 SMART Sliding Gate Operator - SINGLE SOLAR
PANEL1

8.3.7. Earth Spike Installation
For further surge protection, an Earth Spike1 can be installed. Route the earth cable from the Earth Spike around to the back of the D6 SMART, and under the Gearbox by the Cable Shield. Connect it to the Mounting Bolt on the right of the Gearbox where the
Charger Earth is located by means of a Ring Lug.
See Section 7.9.2.1. – “Placing and Routing the Earth Harness”.
Utilise the Cable Management Clip to keep the wiring neat and out of the way.

CENTURION D6 SMART Sliding Gate Operator - SINGLE SOLAR
PANEL2

1. Not supplied with the D6 SMART.

8.3.8. G-ULTRA to D6 SMART Wiring

CENTURION D6 SMART Sliding Gate Operator - SMART
Wiring

8.3.9. 12V Siren to D6 SMART Wiring

CENTURION D6 SMART Sliding Gate Operator - SMART
Wiring1

8.3.10. Synchronisation of Two D6 SMART Operators
The following diagram illustrates how to connect two D6 SMART controllers so that the operation of the operators is synchronised.
Configure the settings as follows for the respective controllers;

CENTURION D6 SMART Sliding Gate Operator - SMART
Wiring2

8.4. Commissioning the System

  1. Scan the QR Code in Figure 96.
  2. Select the App Store applicable to the operating system being used, either Apple App Store, Android Google Play Store or the Huawei App Gallery.
  3. Download and install the application.

Alternatively, go directly to the app store of the operating system being used, and search for the app “MyCentsys Pro”. Download and install the application onto the smartphone.

  1. Once installed, open the application.
  2. From the list of operators, select the operator that is applicable to this installation.
  3. Connect to the relevant operator.
  4. Use the app by following the prompts to configure the D6 SMART.

8.4.1. MyCentsys Remote Application
Introducing an intuitive and user-friendly commanding hub for all SMART and ULTRA devices. MyCentsys Remote puts the ultimate in control and flexibility at your fingertips, delivering an all-in-one, fully-customisable experience for your compatible access
automation solutions. Download MyCentsys Remote free by scanning the QR code.

  1. Scan the QR Code in Figure 96.
  2. Select the App Store applicable to the operating system being used, either Apple App Store, Android Google Play Store or the Huawei App Gallery.
  3. Download and install the application.

Alternatively, go directly to the app store of the operating system being used, and search for the app “MyCentsys Remote”. Download and install the application onto the smartphone.

  1. Once installed, launch the application.
  2. Register with the relevant details.
  3. Select the “+ SMART”.
  4. From the list of operators, select the operator that is applicable to this installation.
  5. Wait for the device added message after tapping on the selected operator.
  6. Select the operator on the home screen to view all available triggers and device status.

Once all the necessary accessories and harnesses have been connected, ensure that the Camlock is in the “unlocked” position, and place the D6 SMART cover onto the gearbox. Once the cover is secured in place, lock the Camlock to lock the cover in place.

8.5. Applying the Warning Decal

Apply the supplied warning decals to the gate as indicated on the reverse side of the decal.

General Maintenance

9.1. Gate Maintenance

Description Frequency Corrective Action
Ensure that the gate track is clear of debris at all times Daily Clean

around the gate and gate operator. Consider installing gate brooms on the bottom of the gate
Ensure that the endstops are sturdy and secure| Every 3 months| If the endstops are damaged or loose, contact an installer to replace
Check that the rack is securely mounted to the gate over its full length| Every 3 months| Contact installer
Contact an installer to inspect and verify that all safety equipment, e.g. safety beams, is functioning correctly| Every 6 months| N/A
Ensure that the gate moves smoothly when in Manual Override.
Check wheels and guide-rollers for signs of wear| Every 6 months| Place the motor in Manual Override and manually open and close the gate.
If the wheels and/or guide-rollers are excessively worn, contact an installer to replace
Check the track for damage or corrosion| Every 6 months| If the track is damaged, contact an installer to replace
If pedestrian gate / emergency gate is fitted within the main gate, ensure that the lock operates smoothly| Every 6 months| Dry lubricate if necessary (graphite)

9.2. D6 SMART Maintenance
Before performing any maintenance, ensure that the D6 SMART is isolated!

Description Frequency Corrective Action
Check for insect infestations Every 3 months Clean and remove any nests

that are settling in and around the motor and Control Card Insert a moth ball, which may help to repel insects, at the bottom of the gearbox
Check that the M10 half-nuts are tight on the foundation plate bolts| Every 6 months| Torque setting 20Nm
Check that there is no sand build-up inside the unit| Every 6 months| Remove batteries and lower battery tray and clear out the sand build-up
Check pinion and rack engagement| Every 6 months| If the mesh is too loose or the rack is riding on the pinion, contact an installer to correct
Check the condition of the pinion| Every 6 months| If the pinion is excessively worn, contact an installer to replace
Check the condition of the override cam lock| Every 6 months| Dry lubricate if necessary (graphite)
If used, check the condition of the theft- deterrent cage| Every 6 months| Ensure that the device is serving its purpose
If used, check the condition of the theft- deterrent cage lock and that it operates| Every 6 months| Dry lubricate if necessary (graphite)

Product Ancillaries

CENTURION D6 SMART Sliding Gate Operator - Product
Ancillaries

Solar Supply Solution
Alternative means of powering the system – consult your CENTURION dealer| Photon SMART Safety Beams
Fully-wireless infrared beams. Always recommended on any SMART automated installation| Theft-Detterant Cage & Padlock
Patented design provides excellent deterrence against theft, tampering and vandalism
CENTURION D6 SMART Sliding Gate Operator - Product
Ancillaries1
G-ULTRA
The ultimate GSM solution for monitoring and activating the operator via your mobile phone| G-SPEAK ULTRA
Answer your intercom from anywhere for maximum security and convenience – powered by 4G technology| Gate Stations
Communication hub for the G-SPEAK ULTRA GSM intercom – available in both durable plastic and stylish and strong metal enclosures
CENTURION D6 SMART Sliding Gate Operator - Product
Ancillaries2

12V-24V SMART Siren
The ultimate security companion, designed to seamlessly integrate with your existing SMART gate and garage door operators| SMART PowerPack
Power unwavering gate performance for busy sites. Run your gate directly from mains. Optional battery backup for added flexibility
CENTURION D6 SMART Sliding Gate Operator - Product
Ancillaries3| CENTURION D6 SMART
Sliding Gate Operator - Product Ancillaries4
---|---
Steel, Nylon RAZ or Nylon Angle Rack
A variety of rack available in different lengths, for different strengths| P36
Passive sensitive edge for sliding gates provides additional protection against
crushing| SMARTGUARD or SMARTGUARDair Keypad
Cost-effective and versatile wired and wireless keypad, allowing access to users with a customised code| FLUX SA Loop Detector
Allows free-exit of vehicles from the property – requires ground loop to be fitted

Installation Handover

Once the installation has been successfully completed and tested, it is important for the installer to explain the operation and safety requirements of the system.
NEVER ASSUME THE USER KNOWS HOW TO SAFELY OPERATE AN AUTOMATED GATE!

Even if the user has used one before, it does not mean they know how to SAFELY operate it. Make sure that the user fully understands the following safety requirements before finally handing over the site.
The following needs to be understood by the user:

  • How to operate the Manual Release mechanism. (Show them how by demonstration)

  • How the obstruction detection and all other safety features work. (Show them how by demonstration)

  • All the features and benefits of the Operator, i.e. Beams, etc.

  • All the safety considerations associated with operating an automated gate. The user should be able to pass this knowledge on to all other users of the automated system and must be made aware of this responsibility.

  • Do not activate the Gate Operator unless you can see it and can determine that its area of travel is clear of people, pets, or other obstructions

  • DO NOT CROSS THE PATH OF A MOVING GATE. Always keep people, pets and objects away from a moving gate and its area of travel

  • NEVER LET CHILDREN OPERATE OR PLAY WITH THE GATE CONTROLS, and do not allow children or pets near the gate area

  • Avoid close proximity with moving parts where fingers, hands or clothing could be pinched and caught

  • Secure all easily-accessible gate operator controls in order to prevent unauthorised use of the gate

  • Keep the automated gate system properly maintained, and ensure that all working areas are free of debris and other objects that could affect the gate operation and safety

  • On a monthly basis, check the obstruction detection system and safety devices to ensure correct operation

  • All repair and service work to this product must be done by a suitably qualified person

  • This product was designed and built strictly for the use documented herein. Any other uses not included herein, could compromise the operating condition of the product and/or be a source of danger!

Centurion Systems (Pty) Ltd does not accept any liability caused by improper use of the product, or for use other than that for which the automated system was designed.
Ensure that the customer is in possession of the User Guide and that you have completed the installation details in the back of the User Guide.

Warranty Information

You can register your product(s) online at www.centsys.com, which will assist you in keeping a record of your date of purchase or installation, serial numbers, etc.
All of our products are manufactured with extreme care, thoroughly inspected and tested.
The goods supplied by us shall be subject to the provisions of sections 55 to 57 of the Consumer Protection Act (68/2008) except where the provisions of the warranty contained in our product documentation are more favourable to the purchaser.
Subject to the warranty contained in our product documentation, if applicable, our products are warranted for a period of twenty-four months after delivery.
However, it is expressly noted that batteries carry a six month warranty due to the nature of these products being such that they are subject to possible misuse. Please note that warranties will be honoured on a carry-in basis; in other words, the product in question must be taken in to one of our branches, or to the authorised reseller that the product was purchased from, for assessment and, if necessary, repair. For equipment not of our manufacture, the warranty as supplied by the original manufacturer will apply
if such warranty is more favourable to the purchaser than the relevant provisions of the Consumer Protection Act (Act 68/2008 of South Africa), or any other applicable law as so required in different countries in which the product was sold. Such warranty is valid only once full payment has been received for such goods.

Australian customers:
Our goods come with guarantees that cannot be excluded under the Australian Consumer Law. You are entitled to a replacement or refund for a major failure and compensation for any other reasonably foreseeable loss or damage. You are also entitled to have the goods repaired or replaced if the goods fail to be of acceptable quality and the failure does not amount to a major failure

Any warranty may be voidable on any equipment which:

  1. Has not been installed in accordance with the installation instructions provided.
  2. Has been subject to misuse or which has been used for any purpose other than that designed for by the manufacturers.
  3. Has damage caused as a result of handling during transit, atmospheric conditions (including lightning), corrosion of metal parts, insect infestation, power surges or other forces outside of the control of the manufacturer.
  4. Has been repaired by any workshop and / or person NOT previously authorised by the manufacturer.
  5. Has been repaired with components not previously tested, passed or authorised by Centurion Systems (Pty) Ltd, South Africa or one of its subsidiary companies.

Connect with us on:
@CenturionSystemsRSA
@Centurion.Systems
@Centurion.Systems
@AskCenturion
@Centurion-Systems
@Centurion.Systems
@CenturionSystems
Centurion-Systems

Subscribe to the newsletter: www.centsys.com/subscribe
WhatsApp – Technical Support
South Africa: +27 (0)83 650 4010
International: +27 (0)83 650 4244
Monday to Friday: from 08h00 to 16h30 (GMT+2)
Saturday: from 08h00 to 14h00 (GMT+2)

E&OE Centurion Systems (Pty) Ltd reserves the right to change any product without prior notice All product and brand names in this document that are accompanied by the ® symbol are registered trademarks in South Africa and/or other countries, in favour of Centurion Systems (Pty) Ltd, South Africa.
The CENTURION and CENTSYS logos, all product and brand names in this document that are accompanied by the TM symbol are trademarks of Centurion Systems (Pty) Ltd, in South Africa and other territories; all rights are reserved.
We invite you to contact us for further details.

Doc number: 1401.D.01.0012_02042024
www.centsys.com

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

Related Manuals