Goodman Condensing Ac Unit Installation Guide

June 13, 2024
Goodman

Goodman Condensing Ac Unit

Goodman-Condensing-Ac-Unit-product

NOTICE

  • THIS UNIT IS SHIPPED WITH A NITROGEN/HELIUM HOLDING CHARGE ONLY. UNIT MUST BE EVACUATED AND CHARGED PER INSTALLATION INSTRUCTIONS WITH REFRIGERANT LISTED ON SERIAL RATING PLATE.
  • UNITS SHIPPED WITH A HOLDING CHARGE ARE INTENDED FOR COMPONENT REPLACEMENT ONLY ON EXISTING SYSTEMS, AND NOT INTENDED FOR USE IN NEW SYSTEMS OR NEWLY CONSTRUCTED HOMES.
  • UNITS MUST ONLY BE USED AS REPLACEMENT COMPONENTS FOR PRE-2010 INSTALLED SYSTEMS.

Important Safety Instructions

The following symbols and labels are used throughout this manual to indicate immediate or potential safety hazards. It is the owner’s and installer’s responsibility to read and comply with all safety information and instructions accompanying these symbols. Failure to heed safety information increases the risk of personal injury, property damage, and/or product damage.

WARNING: HIGH VOLTAGE!

  • Disconnect ALL power before servicing.
  • Multiple power sources may be present.
  • Failure to do so may cause property damage, personal injury or death.

WARNING: ONLY individuals meeting the requirements of an “Entry Level Technician”, at a minimum, as specified by the Air Conditioning, Heating and Refrigeration Institute (AHRI) may use this information. Attempting to install or repair this unit without such background may result in product damage, personal injury, or death.

Shipping Inspection

Always keep the unit upright; laying the unit on its side or top may cause equipment damage. Shipping damage, and subsequent investigation is the responsibility of the carrier. Verify the model number, specifications, electrical characteristics, and accessories are correct prior to installation. The distributor or manufacturer will not accept claims from dealers for transportation damage or installation of incorrectly shipped units.

Codes & Regulations

This product is designed and manufactured to comply with national codes. Installation in accordance with such codes and/ or prevailing local codes/regulations is the responsibility of the installer. The manufacturer assumes no responsibility for equipment installed in violation of any codes or regulations.

The United States Environmental Protection Agency (EPA) has issued various regulations regarding the introduction and disposal of refrigerants. Failure to follow these regulations may harm the environment and can lead to the imposition of substantial fines. Should you have any questions please contact the local office of the EPA.

If replacing a condensing unit or air handler, the system must be manufacturer approved and Air Conditioning, Heating and Refrigeration Institute (AHRI) matched. Refer to the unit Specification Sheet for the recommended indoor model selection. NOTE: This unit must be used with a purchased single stage room thermostat with 24 VAC control circuitry. Do not operate the unit in a structure that is not complete (either as part of new construction or renovation). Such operation will void the warranty.

Installation Clearances

This unit is designed for outdoor installations only. Special consideration must be given to location of the condensing unit(s) in regard to structures, obstructions, other units, and any/all other factors that may interfere with air circulation. Where possible, the top of the unit should be completely unobstructed; however, if vertical conditions require placement beneath an obstruction there should be a minimum of 60 inches between the top of the unit and the obstruction(s). The specified dimensions meet requirements for air circulation only. Consult all appropriate regulatory codes prior to determining final clearances.

Goodman-Condensing-Ac-Unit-fig-2

Another important consideration in selecting a location for the unit(s) is the angle to obstructions. Either side adjacent the valves can be placed toward the structure provided the side away from the structure maintains minimum service clearance. Corner installations are strongly discouraged.

This unit can be located at ground floor level or on flat roofs. At ground floor level, the unit must be on a solid, level foundation that will not shift or settle. To reduce the possibility of sound transmission, the foundation slab should not be in contact with or be an integral part of the building foundation. The foundation slab should be a minimum of 6” wider than the unit in all directions.

Ensure the foundation is sufficient to support the unit. A concrete slab raised above ground level provides a suitable base. The selected site should be no greater than 50’ below or 70’ above the evaporator section. For optimum performance, the minimum length of interconnecting tubing is preferred. When possible minimize the amount of bends and turns.

Rooftop Installations

If it is necessary to install this unit on a roof structure, ensure the roof structure can support the weight and that proper consideration is given to the weather-tight integrity of the roof. Since the unit can vibrate during operation, sound vibration transmission should be considered when installing the unit. Vibration absorbing pads or springs can be installed between the condensing unit legs or frame and the roof mounting assembly to reduce noise vibration.

Rigging

Warning: To avoid possible injury or death, all panels must be in position and secured before lifting this equipment.

Goodman-Condensing-Ac-Unit-fig-3

Use field-supplied spreader bars when lifting the unit to minimize the possibility of lifting cable/straps damage. To protect the cabinet louvers, use protective material such as plywood behind the cable/straps. Arrange the straps to form a central suspension point.

NOTE: When raising and setting the unit, observe all safety rules. Remove shipping skid and all protection and lifting material after the unit is in place.

Safe Refrigerant Handling

While these items will not cover every conceivable situation, they should serve as a useful guide.

WARNING: Refrigerants are heavier than air. They can “push out” the oxygen in your lungs or in any enclosed space.To avoid possible difficulty in breathing or death:

  • Never purge refrigerant into an enclosed room or space. By law, all refrigerants must be reclaimed.
  • If an indoor leak is suspected, throughly ventilate the area before beginning work.
  • Liquid refrigerant can be very cold. To avoid possible frostbite or blindness, avoid contact and wear gloves and goggles. If liquid refrigerant does contact your skin or eyes, seek medical help immediately.
  • Always follow EPA regulations. Never burn refrigerant, as poisonous gas will be produced.

WARNING: To avoid possible explosion:

  • Never apply flame or steam to a refrigerant cylinder.
  • If you must heat a cylinder for faster charging, partially immerse it in warm water.
  • Never fill a cylinder more than 80% full of liquid refrigerant.
  • Never add anything other than R-22 to an R-22 cylinder.
  • The service equipment used must be listed or certified for the type of refrigerant used.
  • Store cylinders in a cool, dry place. Never use a cylinder as a platform or a roller.

WARNING: To avoid possible explosion, use only returnable (not disposable) service cylinders when removing refrigerant from a system.

  • Ensure the cylinder is free of damage which could lead to a leak or explosion.
  • Ensure the hydrostatic test date does not exceed 5 years.
  • Ensure the pressure rating meets or exceeds 400 lbs.
  • When in doubt, do not use cylinder.

Refrigerant Lines

NOTE: For improved refrigerant management, equip the evaporator coil with a field-supplied thermal expansion valve (TXV) and the liquid line with a field-supplied liquid line solenoid. Ensure the solenoid is installed as close as possible to the evaporator coil to prevent refrigeration migration in the compressor “OFF” cycle.

Use only refrigerant grade (dehydrated and sealed) copper tubing to connect the condensing unit with the indoor evaporator. After cutting the tubing, install plugs to keep refrigerant tubing clean and dry prior to and during installation. Tubing should always be cut square keeping ends round and free from burrs. Clean the tubing to prevent contamination.

Do NOT let refrigerant lines come in direct contact with plumbing, ductwork, floor joists, wall studs, floors, and walls. When running refrigerant lines through a foundation or wall, openings should allow for sound and vibration absorbing material to be placed or installed between tubing and foundation. Any gap between foundation or wall and refrigerant lines should be filled with a pliable silicon-based caulk, RTV or a vibration damping material. Avoid suspending refrigerant tubing from joists and studs with rigid wire or straps that would come in contact with the tubing. Use an insulated or suspension type hanger. Keep both lines separate and always insulate the suction line.

Cond Unit (Tons)

| REFRIGERANT LINE LENGTH (ft)
---|---
0- 24| 25- **49*| 50-74**
Line Diameter (In. OD)
Suct| Liq| Suct| Liq| Suct| Liq**
7 1/2| 1 1/8| 5/8| 1 3/8| 5/8| 1 3/8| 5/8
10| 1 3/8| 5/8| 1 5/8| 5/8| 1 5/8| 5/8

  • Full rating line size
    ** Lines greater than 74 feet in length or vertical elevation changes more than 50 feet refer to the Remote Cooling Service Manual or contact your distributor for assistance.

Goodman-Condensing-Ac-Unit-fig-4

Insulation is necessary to prevent condensation from forming and dropping from the suction line. Armflex (or satisfactory equivalent) with 3/8” min. wall thickness is recommended. In severe conditions (hot, high humidity areas) 1/2” insulation may be required. Insulation must be installed in a manner which protects tubing from damage and contamination. Where possible, drain as much residual compressor oil from existing systems, lines, and traps; pay close attention to low areas where oil may collect.

NOTE: If changing refrigerant types, ensure the indoor coil and metering device is compatible with the type of refrigerant being used; otherwise, the indoor coil must be replaced. To facilitate oil return to the compressor, a horizontal suction line should be pitched (1/2” per 10’ toward the condensing unit.

Filter Drier and Sight Glass

A liquid line filter drier is factory installed. Field-install the supplied sight glass/moisture indicator on the liquid line as close as practical to the service valve.

Burying Refrigerant Lines

If burying refrigerant lines can not be avoided, use the following checklist.

  1. Insulate liquid and suction lines separately.
  2. Enclose all underground portions of the refrigerant lines in waterproof material (conduit or pipe) sealing the ends where tubing enters/exits the enclosure.
  3. If the lines must pass under or through a concrete slab, ensure lines are adequately protected and sealed.

Refrigerant Line Connections

NOTICE: THIS UNIT IS SHIPPED WITH A NITROGEN/HELIUM HOLDING CHARGE ONLY. UNIT MUST BE EVACUATED AND CHARGED PER INSTALLATION INSTRUCTIONS WITH REFRIGERANT LISTED ON SERIAL RATING PLATE.

NOTE: Holding charge must be removed before brazing. Open service valves slowly to remove holding charge. Close valves before brazing to prevent contaminants from entering system.

IMPORTANT: To avoid overheating the service valve, TXV valve, or filter drier while brazing, wrap the component with a wet rag, or use a thermal heat trap compound as recommended by the compound manufacturer. Use a brazing alloy of 2% minimum silver content. Do not use flux.

  1. The ends of the refrigerant lines must be cut square, deburred, cleaned, and be round and free from nicks or dents. Any other condition increases the chance of a refrigerant leak.
  2. “Sweep” the refrigerant line with nitrogen or inert gas during brazing to prevent the formation of copper-oxide inside the refrigerant lines.
  3. After brazing, quench the joints with water or a wet cloth to prevent overheating of the service valve.
  4. Ensure the filter drier paint finish is intact after brazing. If the paint of the steel filter drier has been burned or chipped, repaint or treat with a rust preventative. This is especially important on suction line filter driers which are continually wet when the unit is operating.

NOTE: Be careful not to kink or dent refrigerant lines. Kinked or dented lines will cause poor performance or compressor damage. Do NOT make final refrigerant line connection until plugs are removed from refrigerant tubing.
NOTE: Before brazing, verify indoor piston size by checking the piston kit chart packaged with indoor unit.

Leak Testing (Nitrogen or Nitrogen-Traced)

WARNING

  • To avoid the risk of fire or explosion, never use oxygen, high pressure air or flammable gases for leak testing of a refrigeration system.
  • To avoid possible explosion, the line from the nitrogen cylinder must include a pressure regulator and a pressure relief valve. The pressure relief valve must be set to open at no more than 150 psig.

Pressure test the system using dry nitrogen and soapy water to locate leaks. If you wish to use a leak detector, charge the system to 10 psi using the appropriate refrigerant then use nitrogen to finish charging the system to working pressure then apply the detector to suspect areas. If leaks are found, repair them. After repair, repeat the pressure test. If no leaks exist, proceed to system evacuation.

System Evacuation

Condensing unit liquid and suction valves are closed to contain the charge within the unit. The unit is shipped with the valve stems closed and caps installed.

WARNING: REFRIGERANT UNDER PRESSURE!

  • Failure to follow proper procedures may cause property damage, personal injury or death.

NOTICE

  • THIS UNIT IS SHIPPED WITH A NITROGEN/HELIUM HOLDING CHARGE ONLY. UNIT MUST BE EVACUATED AND CHARGED PER INSTALLATION INSTRUCTIONS WITH REFRIGERANT LISTED ON SERIAL RATING PLATE.
  • UNITS SHIPPED WITH A HOLDING CHARGE ARE INTENDED FOR COMPONENT REPLACEMENT ONLY ON EXISTING SYSTEMS, AND NOT INTENDED FOR USE IN NEW SYSTEMS OR NEWLY CONSTRUCTED HOMES.
  • UNITS MUST ONLY BE USED AS REPLACEMENT COMPONENTS FOR PRE-2010 INSTALLED SYSTEMS.

NOTE: Holding charge must be removed before brazing.

  1. Openservice valves before attaching vacuum pump.
  2. Connect the vacuum pump with 250 micron capability to the service valves.
  3. Evacuate the system to 250 microns or less using suction and liquid service valves. Using both valves is necessary as some compressors create a mechanical seal separating the sides of the system.
  4. Close pump valve and hold vacuum for 10 minutes. Typically pressure will rise during this period.
  • If the pressure rises to 1000 microns or less and remains steady the system is considered leak-free; proceed to startup.
  • If pressure rises above 1000 microns but holds steady below 2000 microns, moisture and/or noncondensable may be present or the system may have a small leak. Return to step 2: If the same result is encountered check for leaks as previously indicated and repair as necessary then repeat evacuation.
  • If pressure rises above 2000 microns, a leak is present.

Check for leaks as previously indicated and repair as necessary then repeat evacuation. Refer to the Remote Condensing Unit Service Manual for more detailed instructions on system evacuation, preliminary charge adjustment, and final charge adjustment.

Electrical Connections

WARNING: HIGH VOLTAGE!

Disconnect ALL power before servicing. Multiple power sources may be present. Failure to do so may cause property damage, personal injury or death due to electric shock. Wiring must conform with NEC or CEC and all local codes. Undersized wires could cause poor equipment performance, equipment damage or fire.

WARNING: To avoid the risk of fire or equipment damage, use copper conductors.

NOTICE: Units with reciprocating compressors and non-bleed TXV’s require a Hard Start Kit.

This unit is designed for three phase operation. DO NOT OPERATE ON A SINGLE PHASE POWER SUPPLY. Measure the power supply to the unit. The supply voltage must be in agreement with the unit rating plate power requirements.

RATED VOLTAGE MINIMUM SUPPLY VOLTAGE MAXIMUM SUPPLY VOLTAGE
208/230V 197 253
460V 414 506

The condensing unit rating plate lists pertinent electrical data necessary for proper electrical service and overcurrent protection. Wires should be sized to limit voltage drop to 2% (max.) from the main breaker or fuse panel to the condensing unit. Consult the NEC, CEC, and all local codes to determine the correct wire gauge and length. The wire size must be sufficient to carry the Minimum Circuit Ampacity (MCA) listed on the serial plate.

The supply voltage can be unbalanced (phase to phase) within 2%. The following formula can be used to determine the percentage of voltage unbalance for your unit.

  • Example: L1-L2 = 220V
    • L2-L3 = 216V
  • Average Voltage = (220 + 216 + 213)/3
    • = 649/3
  • Maximum Deviation from Average = 220 – 216 = 4
  • % Voltage Unbalance = 100 x (4/216)
    • = 400/216

MAXIMUM ALLOWABLE LENGTH IN FEET TO LIMIT VOLTAGE DROP TO 2%

Wire

Size (AWG)

| Minimum Circuit Ampacity (MCA)
10| 15| 20| 25| 30| 35| 40| 45
14| 75| 50| 37| NR| NR| NR| NR| NR
12| 118| 79| 59| 47| NR| NR| NR| NR
10| 188| 125| 95| 75| 63| 54| NR| NR
8| 301| 201| 150| 120| 100| 86| 75| 68
6| 471| 314| 235| 188| 157| 134| 118| 110

*Based on NEC 1996

Example: A 7 ½ Ton unit is to be installed. The distance from the building to the unit is 75’. Calculate the minimum wire size assuming no more than 2% voltage drop.

MCA for 7 1/2 Ton 230V unit = 43.3 (from S&R plate).

Applying previous table wire sizes less than #8 AWG cannot be used for circuits which have a rating of 45A. The #8 wire is not suitable since the maximum length for a 45A circuit is 68’.
Solution: Use a #6 AWG wire suitable up to 110’.

NOTE: It is the contractors’s responsibility to follow the NEC (USA) or CEC (Canada) when sizing the service wire for this unit.

Local codes often require a disconnect switch located near the unit; do not install the switch on the unit. Refer to the installation instructions supplied with the indoor furnace/air handler for specific wiring connections and indoor unit configuration. Likewise, consult the instructions packaged with the thermostat for mounting and location information.

Overcurrent Protection

The following overcurrent protection devices are approved for use.

  • Time delay fuses
  • HACR type circuit breakers

These devices have sufficient time delay to permit the motorcompressor to start and accelerate its load. Refer to the unit serial plate and this table for the maximum overcurrent protection permitted. Run all line voltage wiring a conduit from the service disconnect box to the unit. Refer to the NEC (USA) or CEC (Canada) codes for the correct size conduit based on the wire size. The conduit enters the control box through the hole provided in the bottom.

NOTE: The control box hole is sized for 3/4” conduit. If permitted by code, a flexible conduit is preferred to minimize vibration transmission from the unit to the building. Connect the line voltage wires to the L1, L2, and L3 terminals of the definite purpose contactor (located in the unit control box). Refer to the wiring diagram attached to the unit when making these connections.

Three Phase Compressor Rotation

CAUTION: Use care when handling scroll compressors. Dome temperatures could be hot.

Three phase scrolls are power phase dependent and can compress in more than one direction. Verify proper rotation for three phase compressors by ensuring the suction pressure drops and discharge pressure rises when the compressor is energized.

NOTE: When operated in reverse, a three phase scroll compressors is noisier and its current draw substantially reduced compared to marked values. To correct, disconnect power and switch any two leads at the unit contactor and re-observe.

High Voltage Connections

Route power supply and ground wires through the high voltage port and terminate in accordance with the wiring diagram provided inside the control panel cover.

Low Voltage Connections

Goodman-Condensing-Ac-Unit-fig-6

Condensing unit control wiring requires a two-conductor low voltage circuit from the room thermostat. The wiring should be no smaller than 18 AWG and the field connection for this circuit must be made in the unit control box using solderless connectors (i.e. wire nuts). See the following diagram for a typical low voltage hook-up.

System Start Up

  • Never operate the compressor with the suction valve closed to test the compressor’s pumping efficiency. In some cases, this can result in serious compressor damage and loss of warranty coverage.

NOTICE

  • THIS UNIT IS SHIPPED WITH A NITROGEN/HELIUM HOLDING CHARGE ONLY. UNIT MUST BE EVACUATED AND CHARGED PER INSTALLATION INSTRUCTIONS WITH REFRIGERANT LISTED ON SERIAL RATING PLATE.
  • UNITS SHIPPED WITH A HOLDING CHARGE ARE INTENDED FOR COMPONENT REPLACEMENT ONLY ON EXISTING SYSTEMS, AND NOT INTENDED FOR USE IN NEW SYSTEMS OR NEWLY CONSTRUCTED HOMES.
  • UNITS MUST ONLY BE USED AS REPLACEMENT COMPONENTS FOR PRE-2010 INSTALLED SYSTEMS.

For the 7-1/2 ton unit starting charge should be 15 lb of R-22 and 18 lbs for the 10 ton unit. The length of line set, indoor unit airflow, condensing unit location and number of tubing fittings will have an impact on final unit charge amount. Turn the electrical power on, and let the system run. Wait for the refrigerant pressures to stabilize.

Charge Verification

WARNING: REFRIGERANT UNDER PRESSURE!

  • Do not overcharge system with refrigerant.
  • Do not operate unit in a vacuum or at negative pressure.
  • Failure to follow proper procedures may cause property damage, personal injury or death.

CAUTION: Use refrigerant certified to AHRI standards. Use of used refrigerant may cause compressor damage that is not covered under warranty. Most portable machines cannot clean used refrigerant to meet AHRI standards.

NOTICE: Violation of EPA regulations may result in fines or other penalties.

CAUTION: Operating the compressor with the suction valve closed may cause serious compressor damage.

Final Charge Adjustment

The outdoor temperature must be 60°F or higher. Set the room thermostat to COOL, fan switch to AUTO, and set the temperature control well below room temperature. After system has stabilized per startup instructions, check subcooling and superheat as detailed in the following section.

Expansion Valve System

  1. Purge gauge lines. Connect service gauge manifold tobase-valve service ports. Run system at least 10 minutes to allow pressure to stabilize.
  2. Temporarily install thermometer on liquid (small) line near liquid line service valve with adequate contact and insulate for best possible reading.
  3. Check subcooling and superheat. Systems with TXV application should have a subcooling of 11 ± 2 ºF and superheat of 9 ± 1 ºF.
    • If subcooling and superheat are low, adjust TXV to 9 ± 1 ºF superheat, then check subcooling.
    • NOTE: To adjust superheat, turn the valve stem clockwise to increase and counter clockwise to decrease.
    • If subcooling is low and superheat is high, add charge to raise subcooling to 11 ± 2ºF then check superheat.
    • If subcooling and superheat are high, adjust TXV valve to 9 ± 1 ºF superheat, then check subcooling.
    • If subcooling is high and superheat is low, adjust TXV valve to 9 ± 1 ºF superheat and remove charge to lower the subcooling to 11 ± 2ºF.
    • NOTE: Do NOT adjust the charge based on suction pressure unless there is a gross undercharge.
  4. Disconnect manifold set, installation is complete.
    • Subcooling Formula = Sat. Liquid Temp. – Liquid Line Temp.

NOTE

  • Check the Schrader ports for leaks and tighten valve cores if necessary. Install caps finger-tight.
  • Subsequent opening and replace of the cap will require only 1/2 to 1 hex flat. See the table below for the torque required for an effective seal on the valve bonnet (1/6 turn past finger tight.

TUBING SIZE| TORQUE

(ft- lbs)

---|---
5/8| 14
1 3/8| 16

  • After closing the valve bonnet, perform a final refrigerant leak test on the valves and sweat connections. Return the room thermostat to the desired settings.

Troubleshooting

Qualified Installer/Servicer Only

When troubleshooting, the first step should always be to check for clean coils, clean filter(s), and proper airflow. Indoor airflow should be 375 to 425 CFM per ton of cooling based on the size of the outdoor unit. The most common way of establishing indoor airflow is heating temperature rise. Indoor airflow will then be (Heating output of equipment) / (1.1 x temp. rise). In other cases, measurement of external static pressure is helpful. For details, see the Installation Instructions for your indoor unit.

TROUBLESHOOTING ANALYSIS TABLE

COMPLAINT PROBABLE CAUSE REMEDY


1. High Head Pressure

| 1.   Excessive charge of refrigerant in system.

2.  Inadequate supply of air across the condenser coil.

3.   Non-condensate gases in the system.

| 1. Purge or pump-down excessive charge.

2. Make certain that coil is not fouled in any way, or that air is not re- circulating.

3. Purge these gases from the system.

Recharge system, if necessary.

2. Low Head Pressure| 1.   System low on refrigerant.

2.   Compressor valves broken.

| 1. Charge system until sight glass is clear of bubbles.

2. Replace compressor.


3. Low Suction Pressure

| 1.   Liquid line valve closed.

2.   Restricted liquid line.

3.  The bulb of the thermal expansion valve has lost its charge.

4.   System low on refrigerant.

5.   Dirty filters.

6.   Coil frosted up.

7.   Flash gas in the liquid line.

8.   Quantity of air through evaporator not adequate.

| 1. Open the liquid line valve.

2. Replace filter-dryer.

3. Detach the bulb from the suction line and hold in one hand. If no liquid refrigerant goes through the valve, replace the valve.

4. Test the unit for leaks. Add refrigerant until sight glass is free from bubbles, after repairing leak.

5. Clean or replace filter.

6. Defrost and clean coil. Clean or replace filters.

7. Excessive liquid line drop. Check liquid line size.

8. Increase the blower speed.


4. High Suction Pressure

| 1.   Expansion valve stuck open.

2.  Expansion valve bulb not in contact with suction line.

3.   Suction and/or discharge valve leaking or broken.

| 1. Correct valve action or replace the valve.

2. Fasten bulb securely to suction line.

3. Replace compressor.




5. Compressor will not start.

| 1.   Disconnect switch open.

2.   Blow fuse or fuse at disconnect switch.

3.   Thermostat set too high.

4.   Selector switch in “Off” position.

5.   Contactor and/or relay coils burned out.

6.  Loose or open electrical connection in either the control or power circuit.

| 1. Close the disconnect switch.

2. Check the cause of failure and replace the fuse.

3. Adjust to lower temperature.

4. Turn selector switch knob to “Cool” position.

5. Replace contactor and/or relay.

6. Inspect and secure all electrical connections.

Wiring Diagram

Warning: HIGH VOLTAGE!

  • DISCONNECT ALL POWER BEFORE SERVICING OR INSTALLING THIS UNIT.
  • MULTIPLE POWER SOURCES MAY BE PRESENT. FAILURE TO DO SO MAY CAUSE PROPERTY DAMAGE, PERSONAL INJURY OR DEATH.

Goodman-Condensing-Ac-Unit-fig-7

Goodman-Condensing-Ac-Unit-fig-1

Download PDF:Goodman Condensing Ac Unit Installation Guide

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

Goodman User Manuals

Related Manuals