Carrier 30SZ/SZV Water Cooled Condenserless Liquid Chillers User Manual
- June 13, 2024
- Carrier
Table of Contents
30SZ/SZV Water Cooled Condenserless Liquid Chillers
Product Information
Product Name | 30SZ/SZV Water-Cooled/Condenserless Liquid Chillers |
---|---|
Nominal Cooling Capacity | 14-112 kW |
Frequency | 50 Hz |
For detailed control operation, please refer to the Pro-Dialog
Control manual for the 30SZ/SZV series.
Carrier is participating in the Eurovent Certification
Programme. Products are as listed in the Eurovent Directory of
Certified Products.
Installation, Operation, and Maintenance Instructions
-
The cover graphics are for illustrative purposes only and are
not contractually binding. -
START-UP CHECK LIST:
Start up date | [Enter start up date] |
---|---|
Equipment sold by | [Enter equipment seller] |
Contract No | [Enter contract number] |
Installed by | [Enter installer] |
Contract No | [Enter contract number] |
Site address | [Enter site address] |
Equipment type and serial No | 30SZ [Enter serial number] |
ELECTRICAL DATA
30SZV | [Enter electrical data for 30SZV] |
---|---|
Supply voltage Ph 1 | [Enter supply voltage for Phase 1] |
Ph 2 | [Enter supply voltage for Phase 2] |
Ph 3 | [Enter supply voltage for Phase 3] |
Nominal voltage | [Enter nominal voltage] |
% network voltage | [Enter network voltage percentage] |
Current draw Ph 1 | [Enter current draw for Phase 1] |
Ph 2 | [Enter current draw for Phase 2] |
Ph 3 | [Enter current draw for Phase 3] |
Control circuit voltage | [Enter control circuit voltage] |
Control circuit fuse | [Enter control circuit fuse rating] |
Main circuit breaker rating | [Enter main circuit breaker rating] |
PHYSICAL DATA
Condenser|
---|---
Entering water temp.| [Enter entering water temperature]
Leaving water temp.| [Enter leaving water temperature]
Pressure drop (water)| [Enter pressure drop for water]
Evaporator|
Entering water temp.| [Enter entering water temperature]
Leaving water temp.| [Enter leaving water temperature]
Pressure drop (water)| [Enter pressure drop for water]
30SZ/SZV Water-Cooled/Condenserless Liquid Chillers
Nominal cooling capacity 14-112 kW 50 Hz
For the operation of the control please
refer to the Pro-Dialog Control manual for the 30SZ/SZV series
Carrier is participating in the Eurovent Certification Programme. Products are as listed in the Eurovent Directory of Certified Products.
Installation, operation and maintenance instructions
1
The cover graphics are for illustrative purposes only, and are not contractually binding. 2
CONTENTS START-UP CHECKLIST
…………………………………………………………………………………………………………………………………………… 4 1 – SAFETY
CONSIDERATIONS ……………………………………………………………………………………………………………………………….. 5 1.1 –
General ………………………………………………………………………………………………………………………………………………………………… 5 1.2 –
Equipment and components under pressure
………………………………………………………………………………………………………………. 5 1.3 – Transport
……………………………………………………………………………………………………………………………………………………………… 5 2 –
INSTALLATION …………………………………………………………………………………………………………………………………………………… 7 2.1 –
Siting the unit (all sizes)
…………………………………………………………………………………………………………………………………………. 7 2.2 – Moving and
handling …………………………………………………………………………………………………………………………………………….. 7 2.3 –
Location ……………………………………………………………………………………………………………………………………………………………….. 7 2.4
– Mounting ……………………………………………………………………………………………………………………………………………………………… 7 2.5
– Vertical and horizontal installation
………………………………………………………………………………………………………………………….. 7 3 – PHYSICAL DATA
……………………………………………………………………………………………………………………………………………….. 10 4 – ELECTRICAL
DATA ………………………………………………………………………………………………………………………………………….. 10 5 –
DIMENSIONS/CLEARANCES ……………………………………………………………………………………………………………………………. 11 6 –
HYDRAULIC CONNECTIONS …………………………………………………………………………………………………………………………… 12 6.1 –
Refrigerant line connections (30SZV)
……………………………………………………………………………………………………………………. 14 6.2 – Electrical connections
………………………………………………………………………………………………………………………………………….. 18 6.3 – Liquid
refrigerant charge ………………………………………………………………………………………………………………………………………. 18 7 –
START-UP …………………………………………………………………………………………………………………………………………………………… 20 7.1 –
Necessary checks/precautions before start-up
…………………………………………………………………………………………………………. 20 7.2 – Initial checks
………………………………………………………………………………………………………………………………………………………. 20 7.3 –
Refrigerant system description
………………………………………………………………………………………………………………………………. 20 7.4 – Compressor
replacement ………………………………………………………………………………………………………………………………………. 20 7.5 –
Description of unit protection devices
……………………………………………………………………………………………………………………. 20 7.6 – Operating limits
…………………………………………………………………………………………………………………………………………………… 21 8 – GENERAL
MAINTENANCE ………………………………………………………………………………………………………………………………. 21 8.1 –
Electrical connections …………………………………………………………………………………………………………………………………………..
21 8.2 – Hydraulic connections
………………………………………………………………………………………………………………………………………….. 21 8.3 – Plate heat
exchanger cleaning ……………………………………………………………………………………………………………………………….. 22 8.4 –
Refrigerant circuit ………………………………………………………………………………………………………………………………………………..
22 8.5 – Controls ………………………………………………………………………………………………………………………………………………………………
22 9 – SERVICE ……………………………………………………………………………………………………………………………………………………………..
22 9.1 – Lubrication
…………………………………………………………………………………………………………………………………………………………. 22 9.2 – Servicing
recommendations ………………………………………………………………………………………………………………………………….. 22
3
START-UP CHECK LIST
Start up date: …………………………………………………………….
Equipment sold by: ……………………………………………………………………………………………………… Contract No: …………………………………………………………..
Installed by: …………………………………………………………………………………………………………………. Contract No: …………………………………………………………..
Site address: ……………………………………………………………………………………………………………………………………………………………………………………………………………
Equipment type and serial No: 30SZ ……………………………………………………………………………………………………………………………………………………………….
ELECTRICAL DATA:
30SZV …………………………………………………………………………………………………………………………………………………………….
Supply voltage Ph 1: ………………………………………. V
Ph 2: ………………………………………. V
Ph 3 ……………………………………………… V
Nominal voltage: …………………………………………………… V
% network voltage: ……………………………………………………………………………………………..
Current draw
Ph 1:……………………………………….. A
Ph 2 :………………………………………. A
Ph 3: …………………………………………. A
Control circuit voltage: ………………………………………….. V
Control circuit fuse: ………………………………………………………………………………………. A
Main circuit breaker rating: …………………………………………………………………………………………………………………………………………………………………………………….
PHYSICAL DATA: Condenser:
Entering water temp.: ……………………………………………… oC Leaving water temp.:
……………………………………………… oC Pressure drop (water): ……………………………………………. kPa
Evaporator: Entering water temp.: ……………………………………………………oC Leaving water temp.: …………………………………………………… oC Pressure drop (water): ……………………………………………….. kPa
SAFETY DEVICE SETTING:
High pressure switch:
cut-out: …………………………………….. kPa
cut-in: ………………………………………………… kPa
Low pressure switch:
cut-out: …………………………………….. kPa
cut-in: ………………………………………………… kPa
Step controller:
cut-out 1st step: …………………………. oC
cut-in 1st step: ……………………………………….. oC
cut-out 2nd step: ………………………… oC
cut-in 2 nd step: …………………………………….. oC
Oil level: …………………………………………………………………………………………………………………………………………………………………………………………………………………
Oil visible in sight glass? ………………………………………………………………………………………………………………………………………………………………………………………..
ACCESSORIES Commissioning engineer (name):
………………………………………………………………………………………………………………………………………………………………………….. Customer
agreement
Name: ……………………………………………………………………………… Date:
……………………………………………………………………………………………….. Remarks:
Note: Complete this start-up list at the time of installation 4
1 – SAFETY CONSIDERATIONS
1.2 – Equipment and components under pressure
1.1 – General
Installation and servicing of air conditioning equipment can be hazardous due
to system pressure and electrical components. Only trained and qualified
service personnel should install, start-up or service air conditioning
equipment.
Only authorised, trained and qualified technicians should be allowed to carry
out work on the electrical or refrigerant components.
Untrained personnel can perform the basic maintenance functions such as
cleaning the outside of the unit (without pressing on the control). All other
functions, such as cleaning of the outside of the remote control, cleaning of
the unit interior, checking the cut-out devices of the installation etc. must
be done by qualified service personnel.
When working on air conditioning equipment, observe precautions in the
literature, tags and labels attached to the unit and other safety precautions
that may apply.
Follow all safety codes. Wear safety glasses and work gloves. Use a quenching
cloth for unbrazing operations.
These products incorporate equipment or components under pressure,
manufactured by Carrier or other manufacturers. We recommend that you consult
your appropriate national trade association or the owner of the equipment or
components under pressure (declaration, re-qualification, retesting, etc.).
The characteristics of this equipment/these components are given on the
nameplate or in the required documentation, supplied with the products.
1.3 – Transport
1. To prevent damage whilst in transit, do not remove the unit from the skid,
until it is at its final location.
2. Ensure that the chains or ropes do not rub against the unit. 3. Avoid
swinging the unit in a way that might cause it to fall. 4. Never roll or swing
the unit more than 15°.
IMPORTANT: Ensure that all unit panels are fixed in place before moving the
unit. Raise and set down the unit carefully. Do not stack more than three
units during transport.
Rigging (30SZ/SZV 018-036)
WARNING: Before performing service or maintenance operations on the unit, turn
off the main power switch to the unit. Electrical shock could cause personal
injury.
Only for use when repairing “Original Spare Parts”. For repairs, special
attention must be paid to the correct installation of the spare parts. The
parts must always be installed in their original position.
During unit operation, some of the refrigerant circuit elements could reach a
temperature in excess of 70oC so only trained or qualified personnel should
access areas protected by access panels.
This unit should not be installed in an explosive atmosphere.
The unit can operate in normal radioelectric atmospheres in residential,
commercial and light industrial installations. For other applications, please
consult Carrier.
ATTENTION: Even if the compressor motors have been switched off, the power
circuit remains energized, unless the unit or circuit disconnect switch is
open. Refer to the wiring diagram for further details.
Attach appropriate safety labels.
5
Centre of gravity (approx.)
Y
G X
30SZ
004 005 006 007 009 011 018 024 027 036
XG* mm 340 340 340 340 340 340 483 493 493 490
YG* mm 280 280 275 285 280 278 342 333 333 324
ZG* mm 359 364 369 373 377 380 442 467 467 473
30SZV
004 005 006 007 009 011 018 024 027 036
XG* mm 335 335 335 335 335 335 478 488 488 485
Z
YG* mm 287 287 282 292 287 285 349 340 340 331
ZG* mm 349 354 359 363 367 370 432 457 457 463
- Measured from point A
All dimensions are in mm
A
Weight distribution (approx.)
Y
X 3
1 Control box
Z 2
4
30SZ 004 005 006 007 009 011 018 024 027 036
1
30
32
34
42
48
52
94
116 120 130
2
36
37
40
50
56
61
98
119 122 132
3
18
18
19
24
30
32
112 122 124 133
4
21
23
23
28
34
37
120 123 126 135
30SZV 004 005 006 007 009 011 018 024 027 036
1
24
25
26
33
39
43
76
94
94
96
2
33
34
36
47
52
56
92
112 115 124
3
17
17
18
22
26
28
106 115 117 125
4
20
22
22
27
33
35
116 120 122 130
The weights are given in kg
6
2 – INSTALLATION
1. Inspect shipment. Inspect the unit. If it is damaged, or if the shipment
is incomplete, immediately file a claim with the shipping company.
2. Check that the local power supply agrees with the specification on the
unit nameplate.
2.1 – Siting the unit (all sizes)
Check that: – The location is able to support unit operating weight (see
Physical Data table). – There is sufficient space for servicing around the
unit (see
chapter ‘Dimensions/clearances). – When installing on the ground, the selected
site is not
subject to flooding. – The installation is in accordance with local rules and
standards which govern the installation of air conditioning equipment. –
Vibration absorbers have been provided throughout the installation to prevent
noise from being transmitted.
3. On the right- and the left-hand side of the top panel of the lower unit,
position two insulation strips of 15 mm thickness and 10 mm height, so that
the holes made previously are centred under the insulation strip. The
insulation strip absorbs the transmission of vibrations from the higher to the
lower unit. When selecting the insulation strip the unit weight must be
considered. Punch holes into the insulation strips to align with the holes in
the unit top panel (Fig. “Vertical installation, sizes 004-011”). The
insulation strips and fixings should be determined by the installer.
4. Place the other unit above the lower unit so that the nuts that secure the
base panel of the upper unit are aligned with the holes in the panel.
5. Fix one unit to the other with the four bolts (M8). 6. The power supply
must be separate for each unit. Please
consult the wiring diagrams.
VERY IMPORTANT: Do not stack more than 3 units.
Vertical installation, sizes 004-011
2.2 – Moving and handling
30SZ/30SZV 004-011
Do not remove the skids until the unit has been moved to its
final location. The units may be moved by means of rollers
under the skids, or with slings.
When lifting with hoist and slings, use spreaders to avoid
damaging the unit panels.
Always place slings under the skids, never attach them to
1
piping or to any other components on the unit.
2
2.3 – Location
These units must be located indoors and where the temperature
3
is maintained between 5°C and 40°C.
The strength of the supporting surface must be adequate to
support the weight of the unit with refrigerant and water charge.
Install reinforcement if necessary.
2.4 – Mounting
Mount the unit on the floor or on a solid platform. Use an isolation pad under the unit to reduce sound transmission. Use flexible joints in the water piping to reduce sound transmission from the units.
2.5 – Vertical and horizontal installation
These units can be modularly installed, either vertically or horizontally. Do not stack more than three units for sizes 004-011 or more than 2 units for sizes 018-036.
2.5.1 – Modular vertical installation (sizes 004-011) 1. Place the lower unit
in the desired location. 2. Make 4 holes of 8.5 mm diameter in the top panel
of the
lower unit (see Fig. “Holes in the unit top panel”). These holes are already
marked.
Legend 1 Insulation strip 2 Washers 3 Bolts
7
Holes in the unit top panel
Vertical installation, sizes 018-036
125
300
1
125
1
30
690
30
2
Legend
À 4 holes for vertical assembly (ref. )
3
2.5.2 – Modular vertical installation (sizes 018-036)
1. Place the lower unit in the desired location.
2. Remove the lifting hooks in the top panel of the lower
unit. In order to do this it is necessary to turn them
counter-clockwise.
3. On the right- and the left-hand side of the top panel of the
lower unit, position two insulation strips of 15 mm
thickness and 10 mm height, so that the holes provided for
the lifting hooks are centred under the insulation strip.
The insulation strip absorbs the transmission of vibrations
from the higher to the lower unit. When selecting the
insulation strip the unit weight must be considered. Punch
holes into the insulation strips to align with the lifting
hooks (Fig. “Vertical installation, sizes 018-036”).
4
Vibration absorbers can also be installed as shown in Fig.
“Vertical installation, sizes 018-036”.
4. Place the other unit above the lower unit so that the holes
through which the U-frame of the bottom panel of each
2
unit is secured are aligned with the holes provided for the
lifting hooks (Fig. “Vertical installation, sizes 018-036”).
5
5. Fix one unit to the other with the four bolts (M12).
6. The power supply must be separate for each unit. Please
consult the wiring diagrams.
VERY IMPORTANT: Do not stack more than 2 units.
Legend 1 Nut 2 Washers 3 Vibration absorber 4 Screw 5 Insulation strip
8
2.5.3 – Horizontal modular installation (sizes 004-011) Place the units side
by side so that the holes are aligned. Fix the units in position with nuts
(M6) and screws (Figures “Side grooves” and “Horizontal assembly”).
Side grooves
2.5.4 – Check compressor mountings (sizes 018-036)
IMPORTANT: For unit transport, the compressor is held down by bolts and plain
lock washers (see Fig. “Assembly for transportation”). After the unit is
installed remove these bolts one at a time and reassemble with flanged washers
and neoprene snubbers, as shown, using new self-locking bolts supplied with
the unit.
180
Tighten the new bolts until the head bolt comes into contact
with the flanged washer, then loosen each bolt until the flanged
1
washer can be moved from side to side using finger pressure
(see Fig. “Assembly for unit start-up”).
590
Assembly for transportation
95
1
83
384
83
Legend
À 4 grooves for horizontal assembly (ref. )
Horizontal assembly
Assembly for unit start-up
1 Legend
À Joining screw M6 x 65 (ref. )
9
3 – PHYSICAL DATA
30SZ/SZV
Nominal cooling capacity
30SZ*
kW
30SZV**
kW
Operating weight
30SZ
kg
30SZV
kg
Refrigerant charge***
30SZ
kg
Compressor type
No. of control steps
Capacity control
%
Evaporator type (30SZ/SZV)
Net water volume
l
Water connections
Inlet-outlet
in
Max. water pressure
kPa
Condenser type (30SZ)
Net water volume
l
Water connections
Inlet-outlet
in
Max. water pressure
kPa
004
005
006
14.60 13.70
16.10 15.40
19.50 18.50
105
110
116
94
98
102
R-407C
1.5
1.6
2.20
Scroll
1
1
1
–
–
–
Plate heat exchanger
1.23
1.42
1.71
MPT gas
1-1/4
1-1/4
1-1/4
1000
1000
1000
Plate heat exchanger
1.23
1.42
1.71
MPT gas
1-1/4
1-1/4
1-1/4
1000
1000
1000
007
22.90 22.10
144 129
2.16
1 –
1.90 1-1/4 1000
1.90 1-1/4 1000
009
27.90 26.40
168 150
2.30
1 –
2.37 1-1/4 1000
2.37 1-1/4 1000
011
33.50 32.30
182 162
2.97
1 –
2.85 1-1/4 1000
2.85 1-1/4 1000
018
024
027
036
56.00 52.00
78.00 72.00
85.00 77.00
112.00 106.00
424
480
390
441
492
530
448
475
8.10
9.00
Semi-hermetic
2
2
50-100 66-100
10.20 11.60
2
2
66-100 66-100
4.70
1-1/2 1000
5.60
1-1/2 1000
6.60
1-1/2 1000
8.40
1-1/2 1000
4.70
1-1/2 1000
5.60
1-1/2 1000
6.60
1-1/2 1000
8.40
1-1/2 1000
- Evaporator entering water temperature 12°C, evaporator leaving water temperature 7°C, condenser entering water temperature 30°C, condenser leaving water temperature 35°C.
** Evaporator entering water temperature 12°C, evaporator leaving water temperature 7°C; condensing temperature dewpoint 50°C. *** The 30SZV units have a nitrogen holding charge only.
4 – ELECTRICAL DATA
30SZ
Nominal power supply Voltage range Nominal unit power input Nominal unit
current drawn Maximum unit power input Maximum unit current drawn
Starting current
30SZV
Nominal power supply Voltage range Nominal unit power input Nominal unit
current drawn Maximum unit power input Maximum unit current drawn Starting
current
V-ph-Hz V kW A kW A A
V-ph-Hz V kW A kW A A
004
005
400-3-50
360-440
3.88
4.06
6.85
6.95
5.34
6.19
9.05
9.70
59.5
70.5
004
005
400-3-50
360-440
4.14
4.43
7.65
7.75
4.44
5.10
9.05
9.70
59.5
70.5
006
007
009
011
018
024
6.03 10.75 8.51 14.10 94.0
006
7.03 12.45 10.00 16.50 116.0
007
7.33 13.70 10.87 18.00 127.0
009
9.89 15.70 13.31 21.16 159.0
011
15.70 25.50 19.58 33.30 104.0
018
23.70 34.00 26.50 42.55 134.0
024
6.36 11.70 6.77 14.10 94.0
7.32 13.50 7.53 16.50 116.0
8.02 15.45 9.29 18.00 127
10.70 17.50 11.34 21.16 159.0
16.40 27.90 18.18 33.30 104.0
23.80 36.35 24.23 42.55 134.0
027
036
25.80 38.45 29.83 53.10 152.0
027
36.30 54.95 42.66 70.10 207.0
036
26.10 41.40 26.58 53.10 152.0
36.70 58.80 37.77 70.10 207.0
- Evaporator entering water temperature 12°C, evaporator leaving water temperature 7°C, condenser entering water temperature 30°C, condenser leaving water temperature 35°C.
** Evaporator leaving water temperature 10°C, condenser entering water temperature 50°C, condenser leaving water temperature 55°C. Evaporator entering water temperature 12°C, evaporator leaving water temperature 7°C, condensing temperature dewpoint 50°C. Evaporator leaving water temperature 10°C, condensing temperature dewpoint 60°C.
Electrical data notes
· 30SZ/SZV units have a single power connection point. · The control box
includes the following standard features:
– the start-up and motor protection devices for each compressor. – the control
devices
· Field connections: All connections to the system and the electrical
installations must be in full accordance with all applicable local codes.
· The Carrier 30SZ/SZV units are designed and built to ensure con-formance
with these codes. The recommendations of European standard EN 60204-1
(corresponding to IEC 60204-1)-(machine safety – electrical machine components
– part 1: general regulations) are specifically taken into account, when
designing the electrical equipment.
Notes: · Conformance with EN 60204-1 is the best means of ensuring compliance
with
the Machines Directive § 1.5.1. Generally the recommendations of IEC 60364 are
accepted as compliance with the requirements of the installation directives. ·
Annex B of EN 60204-1 describes the electrical characteristics used for the
operation of the machines. 1. The operating environment for 30SZ/SZV units is
specified below: · Environment – Environment as classified in EN 60634 § 3: –
ambient temperature range: +5°C to +40°C, class AA4 – humidity range (non
condensable):
50% rh at 40°C 90% rh at 20°C
– altitude: £ 2000 m – indoor installation – presence of water, class AD2
(possibility of water drops) – presence of hard solids, class AE2 (no
significant dust present) – presence of corrosive and polluting substances,
class AF1 (negligible) – vibration and shock, class AG2 , AH2 – Competence of
personnel, class BA4 (personnel trained in accordance
with IEC 60364) 2. Power supply frequency variation: ± 2 Hz. 3. The neutral
(N) line must not be connected directly to the unit (if necessary
use a transformer). 4. Overcurrent protection of the power supply conductors
is not provided with the
unit. 5. The factory-installed disconnect switch(es) is (are) of a type
suitable for power
interruption in accordance with EN 60947-3 (corresponding to IEC 60947-3). 6.
The units are designed for connection to TN networks (IEC 60364). For IT
networks the earth connection must not be at the network earth. Provide a
local earth, consult competent local organisations to complete the electrical
installation.
NOTE: If particular aspects of an actual installation do not conform to the
conditions described above, or if there are other conditions which should be
considered, always contact your local Carrier representative.
- The required protection level for this class is IP21B (according to reference document IEC 60529). All 30SZ/SZV units are protected to IP23C and fulfil this protection condition.
10
5 – DIMENSIONS/CLEARANCES 30SZ 004-011
30SZ 018-036
30SZV 004-011
30SZV 018-036
All dimensions are in mm. Nominal power supply 400-3-50 NOTE: When designing an installation, refer to the certified drawings, available on request.
Legend 1 Discharge line 2 Liquid line A Condenser B Evaporator
11
6 – HYDRAULIC CONNECTIONS
Make the heat exchanger water connections with the necessary components, using
material which will guarantee that the screwed joints are leakproof.
The figures “Typical hydraulic installation” show a typical hydraulic circuit
installation in an air conditioning system.
For an application with a hydraulic circuit, the following recommendations
must be taken into account:
1. The water pump should discharge into the evaporator. 2. It is advisable to
install shut-off valves to allow isolation
of the most important circuit components, as well as the unit itself. These
valves (ball, globe and butterfly valves) should produce a minimum loss of
charge when they are open. 3. Provide circuit drains at the lowest point as
well as the necessary clearances around the unit. 4. Install purges in the
higher sections of the installation. 5. Pressure ports and pressure gauges
should be installed upstream and downstream of the water pump. 6. Thermometers
should be installed in the unit water inlet and outlet. 7. All piping must be
adequately insulated.
Installation of the following components is OBLIGATORY: 1. A flow switch
should be installed in a straight horizontal
stretch with a length of at least five times the line diameter on either side.
It must be positioned in the evaporator inlet pipe and must be electrically
connected in accordance with the wiring diagram. The installation should
incorporate a protection device which is activated when there is no water
circulating in the heat exchanger. 2. The presence of particles in the water
can lead to obstructions in the plate heat exchanger. In these installations a
mesh filter should be installed at the heat exchanger inlet, with a mesh size
of less than 1.2 mm (see Fig. “Mesh filter”). 3. After assembling the system,
or repairing the circuit, the whole system must be thoroughly cleaned with
special attention paid to the state of the filters. 4. When low temperatures
are expected, or if the unit is installed in a low temperature atmosphere, an
adequate amount of ethylene glycol should be added.
Use the curve (see Fig. “Ethylene glycol”) to determine the correct ethylene
glycol concentration for the temperature.
Mesh filter
NOTE: The use of these filters is strongly recommended.
12
Typical hydraulic installation (30SZ)
Typical hydraulic installation (30SZV)
Legend
1
Water chiller (30SZ)
2
Fan coil units
3
Water circulating
pump
4
Inertia accumulator
5
Expansion vessel
6
Pressure gauges at
pressure intake
7
Manual shut-off valves
8
Mesh filter
9
Pressure inlets
10
Thermometers
11
Flow switch
12
Automatic purge
13
Drain
14
Charge valve
15
Flexible coupling
Legend
1
Water chiller (30SZV)
2
Fan coil units
3
Water circulating pump
4
Inertia accumulator
5
Expansion vessel
6
Pressure gauges at
pressure intake
7
Manual shut-off valves
8
Mesh filter
9
Pressure inlets
10
Thermometers
11
Flow switch
12
Automatic purge
13
Drain
14
Charge valve
15
Flexible coupling
16
Condenser
IMPORTANT: Refer to the certified drawings, to make the unit hydraulic connections. 13
6.1 – Refrigerant line connections (30SZV)
6.1.1 – Recommendations for the installation of liquid chillers with remote
condensers To guarantee optimum and reliable performance of the 30SZV units
(split units for connection to condensers) it is necessary to comply with the
regulations described below, when these units are connected to remote
condensers.
1. Install a valve in the discharge piping. 2. Size the discharge and liquid
line piping according to the
recommendations in the following paragraphs (if necessary, install a double
riser to ensure correct oil circulation in the refrigerant circuit). 3.
Depending on the layout and the routing of the discharge piping it may be
necessary to install additional silencers (to reduce pulsations and noise
emission) between the liquid chiller and the condenser. 4. Select a condenser
with an integrated subcooler to obtain a minimum of 3 K subcooling at the
inlet to the expansion device. 5. Keep the condensing pressure as stable as
possible (pressostat staging or fan control via Pro-Dialog Plus). A speed
controller may be required for the first fan stage for operation at low
ambient temperature and partial load. 6. If the system can have several
operating modes (summer/ winter, dual set point etc.), it is necessary to
install a tank (or receiver) to absorb the variations in charge.
6.1.2 – General Refrigerant pipe sizing must be carried out, taking account of
the following constraints:
Oil return to the compressor must be ensured for the majority of applications.
Oil return is ensured by entrainment. A minimum refrigerant velocity is
required to ensure entrainment. This velocity depends on the pipe diameter,
the refrigerant and oil temperature (these are treated as being the same in
most cases). A reduction of the pipe diameter permits an increase of the
refrigerant velocity. The problem of a minimum entrainment velocity does not
exist for the pipes that carry liquid refrigerant as the oil is fully miscible
here.
6.1.3 – Use of pipe sizing diagrams On page 16 of this document two pipe
sizing diagrams are shown. They allow an estimate of the cooling capacity,
corresponding to 1.5 K pressure drop for different pipe diameters, based on
the pipe length.
The following procedure can be used for pipe sizing: 1. Measure the length (in
metres) of the piping under
consideration. 2. Add 40 to 50% to take account of special characteristics. 3.
Multiply this length by the appropriate correction factor
from Table 1 (this correction factor depends on the saturated suction and
discharge temperatures). 4. Read the pipe size from diagrams “Discharge
piping” and “Liquid line piping”. 5. Calculate the equivalent lengths for
parts included in the piping under consideration (such as valves, filters,
connections). The equivalent lengths are normally available from the component
supplier. Add these lengths to the length caculated in step 3. 6. Repeat steps
4 and 5 is necessary.
The diagrams in the appendix can obviously be used to calculate the actual
pressure drops for the piping under consideration: 7. Based on the pipe
diameter and the cooling capacity find
the equivalent length, producing 1.5 K pressure drop in Figs. “Discharge
piping” and “Liquid line piping”. 8. Calculate the equivalent pipe length as
described in steps 1, 2, 3 and 5. 9. Calculate the length ratio from steps 8
and 7 (equivalent length from step 8 DIVIDED by the equivalent length from
step 7). 10. Multiply this ratio by 1.5 to find the equivalent pressure drops
in °C.
The pressure drop at the compressor discharge (pipes linking the compressor outlet with the condenser inlet) must be limited to avoid system performance losses (the compressor power input inceases, and the cooling capacity decreases).
As a first estimate and for standard air conditioning applications, a one degree Celsius pressure drop on the discharge side decreases the cooling capacity 2% and increases the compressor power input by 3%. Increasing the pipe diameter permits limiting the pressure drops.
The pressure drop in the liquid line (linking the condenser outlet to the expansion device) must not result in a change in phase. The estimate of these pressure drops must include those for the possible accessories, such as solenoid valves, filters, dehumidifier etc.
14
6.1.4 – Discharge pipe sizing The discharge piping must be sized to achieve reasonable pressure drops: a variation of 1.5 K of the saturated temperature is normally accepted (approx. 60 kPa variation for a condensing temperature of 50°C).
6.1.5 – Liquid line sizing The 30SZV compressors are supplied with an oil that is fully miscible with refrigerant R407C in the liquid phase. Consequently low refrigerant velocities in the liquid lines are not a problem.
For most applications the refrigerant gas velocity is sufficient to entrain the liquid refrigerant/oil mixture. Nevertheless, Table 2 shows the minimum required cooling capacities for different pipe diameters and different saturated discharge temperatures.
The admissible pressure drops in the liquid lines depend mainly on the subcooling level of the liquid refrigerant at the condenser outlet. Pressure drops corresponding to 1.5°C saturated temperature must not be exceeded.
This table is based on 8 K superheat, a saturated suction temperature of 4°C and 8 K subcooling. Table 3 shows the correction factors to be applied to the values from Table 2, if the operating conditions are different from those previously stated.
Special attention must be paid to the liquid line sizing when the expansion device ist positioned higher than the condenser. It may now be necessary to increase the pipe diameter to compensate for the additional pressure of the liquid refrigerant column. If the liquid refrigerant head ist very high, it may even be necessary to increase the subcooling to prevent an phase change in the liquid line. This can be done e.g. by a liquidvapour heat exchanger or an additional coil.
At 45°C the volume mass of refrigerant R407C in the liquid phase is approximately 1050 kg/m3. A pressure of 1 bar corresponds to a liquid head of: 100 000/(1050 x 9.81) = 9.7 m.
Table 1 – R-407C correction factors for copper tube
30SZV
Saturated suction temperature, °C
Cond. temp. -18
°C
S HG L
27
2.01 1.36 1.09
32
2.11 1.27 1.08
38
2.22 1.17 1.08
43
2.34 1.09 1.08
49
2.49 1.03 1.09
54
2.66 0.97 1.12
60
2.87 0.93 1.16
66
3.13 0.91 1.21
71
3.46 0.89 1.29
-12 S HG L 1.61 1.34 1.07 1.69 1.23 1.06 1.78 1.13 1.06 1.88 1.06 1.06 1.99 0.99 1.07 2.13 0.94 1.10 2.29 0.90 1.13 2.49 0.87 1.18 2.74 0.85 1.26
-7 S HG L 1.31 1.30 1.06 1.37 1.19 1.04 1.44 1.10 1.04 1.52 1.02 1.04 1.61 0.96 1.05 1.72 0.90 1.07 1.85 0.86 1.11 2.01 0.84 1.15 2.21 0.82 1.22
-1 S HG L 1.07 1.26 1.04 1.12 1.16 1.03 1.18 1.06 1.02 1.24 0.99 1.02 1.32 0.93 1.03 1.40 0.87 1.05 1.50 0.83 1.08 1.63 0.81 1.12 1.79 0.78 1.19
4 S HG L 0.89 1.23 1.03 0.93 1.12 1.01 0.97 1.03 1.01 1.03 0.96 1.00 1.09 0.90 1.01 1.16 0.85 1.03 1.24 0.81 1.06 1.34 0.78 1.10 1.47 0.76 1.16
10 S HG L 0.74 1.19 1.01 0.77 1.09 1.00 0.81 1.00 0.99 0.85 0.93 0.99 0.90 0.87 0.99 0.96 0.82 1.01 1.03 0.78 1.04 1.11 0.75 1.08 1.21 0.73 1.13
Legend S Suction HG Hot gas L Liquid
Table 2 – Minimum capacity for oil entrainment in the discharge piping (kW) for R407C copper tube
30SZV
Outside pipe diameter
1/2″ Saturated condensing temperature, °C
5/8″ 3/4″ 7/8″
27
0.81
1.48 2.39 3.66
32
0.84
1.51 2.46 3.76
38
0.84
1.51 2.50 3.80
43
0.88
1.55 2.53 3.87
49
0.88
1.55 2.53 3.87
54
0.88
1.55 2.53 3.87
60
0.84
1.55 2.53 3.87
66
0.84
1.51 2.46 3.80
71
0.81
1.48 2.43 3.69
Table 3 – R407C correction factors for oil entrainment in the discharge piping
1-1/8″ 1-3/8″ 1-5/8″ 2-1/8″ 2-5/8″ 3-1/8″ 3-5/8″ 4-1/8″
7.14 12.06 18.64 37.21 63.94 99.81 145.60 201.98 7.28 12.34 19.06 38.09 65.42
102.13 148.94 206.66 7.42 12.56 19.41 38.76 66.61 103.96 151.62 210.35 7.53
12.73 19.66 39.25 67.42 105.23 153.48 212.92 7.56 12.80 19.77 39.50 67.84
105.90 154.43 214.26 7.56 12.80 19.77 39.46 67.81 105.86 154.40 214.19 7.49
12.70 19.62 39.18 67.32 105.05 153.24 212.60 7.39 12.45 19.27 38.44 66.08
103.12 150.42 208.66 7.17 12.17 18.78 37.49 64.43 100.55 146.69 203.49
Saturated suction temperature, °C
-23
-18
0.86
0.89
-12
-7
-1
0.92
0.94
0.97
See chapter “Discharge pipe sizing”
4
10
1.00
1.03
15
Equivalent length (m)
Discharge piping
200
100
50 40 30 20
10
5 4 3 2
3 45
Legend
1 1/2″
2 3/8″
3 3/4″
4 7/8″
5 1 1/8″
6 1 3/8″
1
2
3
4
5
67
8
7 1 5/8″
8 2 1/8″
10
20 30 40 50
100
200 300 400 500 1000
Cooling capacity (kW)
Equivalent length (m)
Liquid piping
200
100
50 40 30 20
10
5 4 3 2
345
1
2
3 45
67
10 20 30 40 50 100 200 300 400 1000
Cooling capacity (kW)
Legend 1 3/8″ 2 1/2″ 3 5/8″ 4 3/4″ 5 7/8″ 6 1 1/8″ 7 1 3/8″
16
Temperature °C Pressure drop, kPa
Ethylene glycol curve
5 0 – 5 – 10 – 15 – 20 – 25 – 30 – 35 – 40 – 45 – 50 – 55 – 60 – 65
0
20
40
60
80
100
Ethylene glycol % in water
Condenser water pressure drop
A B CDE F G H I J 100
80 70 60 50 40 30
20
10 8 7 6 5 4
3
2
1 0.1
0.2 0.3 0.4 0.6 0.8 1
2
Water flow rate, l/s
34
6 8 10
A. 30SZ 004 B. 30SZ 005 C. 30SZ 006 D. 30SZ 007 E. 30SZ 009
F. 30SZ 011 G. 30SZ 018 H. 30SZ 024 I. 30SZ 027 J. 30SZ 036
Evaporator water pressure drop
A B CDE F G H I J 100
80 70 60 50 40 30
20
10 8 7 6 5 4
3
2
1 0.1
0.2 0.3 0.4 0.6 0.8 1
2
Water flow rate, l/s
34
6 8 10
A. 30SZ – SZV 004 B. 30SZ – SZV 005 C. 30SZ – SZV 006 D. 30SZ – SZV 007 E. 30SZ – SZV 009
F. 30SZ – SZV 011 G. 30SZ – SZV 018 H. 30SZ – SZV 024 I. 30SZ – SZV 027 J. 30SZ – SZV 036
Pressure drop, kPa
17
6.2 – Electrical connections
WARNING: To prevent electrical shock or equipment damage, make sure
disconnects are open before electrical connections are made. If this action is
not taken, personal injury may occur.
6.2.1 – Inserting line power leads into the unit Install airtight cable
conduit connectors through the knockouts provided. Route all cables across the
connectors to the terminal blocks in the control box.
Use copper cables for the power supply into the unit.
Field wiring must comply with all applicable codes.
Take special care when making the earth connection. (Caution: Not all cables marked GND are earth cables.)
Voltage to the unit must be within 10% of the voltage and 10% of the current indicated on the nameplate. Contact your local power company for correction of an incorrect line voltage.
Check the voltage before selecting supply wiring fuses and controls.
WARNING: Operation of the unit on improper line voltage constitutes abuse and is not covered by the Carrier warranty.
IMPORTANT: To ensure the correct unit power supply (cable entry, conductor cross section, protection devices etc.), consult the electrical data table, the wiring diagram supplied with the unit and the applicable standards concerning the installation of air conditioning equipment.
Never operate a unit if the voltage imbalance exceeds 2%. The following formula must be used to determine the percentage of voltage imbalance.
Voltage imbalance % =
Largest deviation from average voltage Average voltage
Example: Nominal supply: 400-3-50
AB = 404 V
BC = 399 V
Motor
AC = 394 V
6.3 – Liquid refrigerant charge
6.3.1 – Checking the charge
WARNING: When adjusting the refrigerant charge always ensure that water is
circulating in the condenser and evaporator to prevent any possibility of
freezing up. Damage caused by freezing is not covered by the product warranty.
30SZ units are shipped with a sufficient charge of refrigerant. Refer to the
Physical Data table. If it is nevertheless necessary to add more refrigerant,
run the unit at full capacity for some time and then add refrigerant until
there are no bubbles in the sight glass. This will generally mean adding more
refrigerant than would be needed to prevent bubbles from being seen in the
sight glass.
30SZV condenserless units are shipped with only a nitrogen charge, leaving the
whole system to be charged after the installation is complete. To adjust the
charge continue adding liquid refrigerant, with the unit running at full
capacity until there are no bubbles visible in the sight glass.
WARNING: To ensure proper operation of 30SZ units there must be at least 5 K
of subcooling as the liquid refrigerant enters the expansion valve.
30SZ and 30SZV units use a HFC-407C refrigerant charge. For your information,
we are reproducing here some extracts from the official publication dealing
with the design, installation, operation and maintenance of air conditioning
and refrigeration systems and the training of people involved in these
activities, agreed by the air conditioning and refrigeration industry.
Average voltage = 404 + 399 + 394 = 399 = 400 V 3
Determine maximum deviation from average voltage:
AB = 404 – 400 = 4 BC = 400 – 399 = 1 AC = 400 – 394 = 6
Largest deviation is 6 volts. Percentage voltage imbalance is therefore:
6 x 100 = 1.5 % 400
CAUTION: The installer must install protection devices, as required by the applicable legislation.
18
6.3.2 – Refrigerant guidelines Refrigeration installations must be inspected
and maintained regularly and rigorously by specialists. Their activities must
be overseen and checked by properly trained people. To minimise discharge to
the atmosphere, refrigerants and lubricating oil must be transferred using
methods which reduce leaks and losses to a minimum.
– Leaks must be repaired immediately – A valve on the condenser liquid
refrigerant outlet line
enables the refrigerant charge to be transferred to the receiver provided
specifically for this purpose (not supplied). – If the residual pressure is
too low to make the transfer alone, a purpose-built refrigerant recovery unit
must be used. – Compressor lubricating oil contains refrigerant. Any oil
drained from a system during maintenance must therefore be handled and stored
accordingly. – Refrigerant under pressure must never be discharged to the
atmosphere.
6.3.3 – Recharging liquid refrigerant
CAUTION: 30SZ units are charged with liquid HFC-407C refrigerant.
This zeotropic refrigerant consists of 23% R-32, 25% of R-125 and 52% R-134a,
and is characterised by the fact that at the time of the change in state the
temperature of the liquid/vapour mixture is not constant, as with azeotropic
refrigerants. All checks must be made, using the appropriate
pressure/temperature diagram.
6.3.4 – Undercharge If there is not enough refrigerant in the system, this is
indicated by gas bubbles in the moisture sight glass. There are two
possiblities:
· Small undercharge (bubbles in the sight glass, no significant change in
suction pressure). – After detection and repair the unit can be recharged. –
The replenishment of the charge must always be done in the liquid phase at the
liquid line. The refrigerant cylinder must contain a minimum of 10% of its
initial charge.
· Significant undercharge (large bubbles in the sight glass, drop in suction
pressure). – Small units (charge below 20 kg per circuit). Completely drain
the refrigerant charge, using a refrigerant recovery unit, repair and then
recharge completely, following the precautions given above. – Large units
(charge above 20 kg per circuit). After detection and repair completely
recharge the unit as described above, operate it for a few minutes and then
let a specialist carry out a chromatographic analysis to verify the
composition of the blend (range: R-32: 22-24%, R-125: 23-27%, R-134a: 50-54%).
WARNING: If brazing is necessary, it should be done in a neutral atmosphere:
nitrogen. Combustion of refrigerant produces toxic phosgene gas.
VERY IMPORTANT: – Never use the compressor to pump down the system. – Never
introduce liquid refrigerant into the suction line. – Do not overcharge the
system with refrigerant.
Leak detection is especially important for units charged with refrigerant R-407C. A refrigerant leak in the liquid or vapour phase will have an effect on the composition of the remaining fluid.
NOTE: Regularly carry out leak checks and immediately repair any leak found.
19
7 – START-UP
Unit start-up is done by the electronic control described in the manual
“30SZ/SZV Pro-Dialog Plus control”, and must always be carried out under the
supervision of a qualified air conditioning engineer.
7.1 – Necessary checks/precautions before start-up
– Ensure that all electrical connections are properly tightened.
– Ensure that the unit is level and well-supported. – Check that the hydraulic
circuit has sufficient water flow
and that the pipe connections correspond to the installation diagram. – Ensure
that there are no water losses. Check the correct operation of the valves
installed. – All the panels should be fitted and firmly secured with the
corresponding screws. – Make sure that there is sufficient space for servicing
and maintenance purposes. – Ensure that there are no refrigerant leaks. –
Confirm that the electrical power source agrees with the unit nameplate
rating, wiring diagram and other documentation for the unit. – Ensure that the
power supply corresponds to the applicable standards. – Make sure that
compressors float freely on the mounting springs.
WARNING: The compressors are mounted on vibration isolators. Do not loosen or
remove the support mounting bolts.
– Liquid solenoid valve (30SZV) – All units, except condenserless units,
include the R-407C
refrigerant charge necessary for correct operation.
7.4 – Compressor replacement
30SZ/SZV 004-011 As the compressors are hermetic, when an internal fault
occurs, the compressor must be replaced. This must be done as detailed below:
– Disconnect the unit from the electrical supply. – Remove the panels. –
Remove the gas from the refrigerant circuit using recovery
equipment to avoid contaminating the atmosphere. – Electrically disconnect the
compressor. – Unbraze or unscrew the suction and discharge lines,
taking care not to damage the rest of the components. – Remove the fastenings.
– Replace the compressor, ensuring that it contains
sufficient oil. – Braze or screw in the lines (brazing in a neutral
atmosphere). – Connect the compressor according to the wiring diagram. – Pump
down the compressor. – Fill in the refrigerant charge indicated on the
nameplate.
30SZ/SZV 018-036 These units have semi-hermetic compressors, and their
internal components can be repaired, if it not necessary to replace the
compressor.
7.5 – Description of unit protection devices
7.2 – Initial checks
With the unit in operation, ensure that the high and low pressure values shown
on the display are within the normal limits. It is advisable to simulate unit
shutdown due to high pressure, in order to make sure that the pressurestat
works properly. To do so, proceed as follows: – High pressure shutdown: Shut
off the water inlet to the
outdoor heat exchanger. The unit should stop at a pressure of 2700 kPa. The
high pressure switch has manual reset.
Check that the motor and compressor power consumption is approximately the
same as shown on the unit nameplate. These values are also shown in the
Electrical Data table.
7.3 – Refrigerant system description
The unit includes the following protection devices: – Internal or external
compressor protection (depending on
the model) – Main switch – Anti-short-cycle protection – Thermomagnetic
compressor switch – Thermomagnetic control switch – Anti-freeze protection –
Evaporator leaving water limit thermostat – Temperature sensor fault detector
– Oil pressure safety switch (30SZV 018-036) – High pressurestat: This
protects the unit against excessive
condensing pressure. The high pressurestat has factoryfixed non-adjustable
settings. To check, see section “Initial Checks”. – Low pressure safety
switch.
The refrigerant circuit incorporates the following principal elements: – Plate
heat exchanger, made of brazed steel. The special
shape of these plates makes them very efficient. – Copper refrigerant lines –
Expansion valve – Compressors (hermetic or semi-hermetic) – Filter drier –
Schrader valves – Safety elements: high pressurestats, fusible plugs – High-
pressure, low-pressure and oil pressure sensor
(30SZV 018-036)
20
7.5.1 – Pressure switch settings
8 – GENERAL MAINTENANCE
30SZ/SZV 004-011 High pressurestat
30SZ/SZV 018-036 High pressurestat
- Factory-fitted
Cut-out 2700 kPa 2700 kPa
Cut-in –
Reset Manual Manual
WARNING: Alteration of factory settings other than the design set-point, without manufacturer’s authorisation, may void the warranty.
ATTENTION: Before starting any servicing or maintenance operation on the unit,
make sure that the power supply has been disconnected. A current discharge
could cause personal injury.
In order to obtain maximum performance from the unit special attention should
be paid to the following points.
8.1 – Electrical connections
If ethylene glycol is used in the system, the manufacturer must be asked for
permission to change the unit protection parameters.
7.6 – Operating limits
These units have been designed to operate within the following limits:
30SZ
Water Evaporator entering temperature Evaporator leaving temperature Condenser
entering temperature Condenser leaving temperature
Minimum
+9°C +5°C*
+16°C +18°C
Maximum
+16°C +13°C
+50°C +55°C
- Operation down to 0°C leaving water temperature is possible with anti-freeze solution and special control configuration by Carrier Service.
30SZV
Water
Minimum
Evaporator entering temperature Evaporator leaving temperature
+9°C +5°C*
Condensing temperature at the dewpoint +30°C
Maximum
+16°C +13°C
+60°C
- Operation down to 0°C leaving water temperature is possible with anti-freeze solution and special control configuration by Carrier Service.
The supply voltage should be within the limits permitted by the compressor.
Ensure that there are no faulty contacts in the terminal blocks, printed
cicuits, contactors, etc. Make sure that all the electrical connections are
properly tightened, and that all the electrical components (contactors,
relays, etc) are firmly secured to the corresponding rails. Pay special
attention to the condition of the connecting cables between the control
elements and the electrical box, and to that of the unit power supply cable.
Check the starting and running consumptions are within the limits specified in
the corresponding technical information.
8.2 – Hydraulic connections
Ensure that there is no water leakage in the system. Drain the unit, if it is
expected to be shut down for a prolonged period. This operation is essential
if temperatures are expected to drop below freezing, and if no glycol solution
is used.
Carefully clean the system water filter.
21
8.3 – Plate heat exchanger cleaning
9 – SERVICE
In some applications, for example when very hard water is used, there is more
tendency for fouling. The heat exchanger can always be cleaned by circulating
a cleaning fluid.
A weak acid solution should be used (5% phosphoric acid or, if frequently
cleaned 5% oxalic acid), and the cleaning fluid should be pumped through the
heat exchanger (Fig. “Tank installation”).
The tank installation can be permanent or, alternatively, the connections can
be prepared and, at any given time, a portable cleaning device can be
connected.
To achieve optimum cleaning the acid solution should be circulated at a
minimum of 1.5 times the normal operational flow speed, and preferably in
reverse direction. The installation should then be flushed with large amounts
of water to totally remove the acid before the system is started up.
Tank installation
1
2
Legend 1 Heat exchanger 2 Weak acid solution tank
9.1 – Lubrication
The compressor has its own oil supply and oil should not be added unless a
leak has occurred.
9.2 – Servicing recommendations
– Before replacing any of the elements in the cooling circuit, ensure that the
entire refrigerant charge is removed from both the high and low pressure sides
of the unit.
– The control elements of the cooling system are highly sensitive. If they
need to be replaced, care should be taken not to overheat them with blowlamps
whilst soldering. A damp cloth should be wrapped around the component to be
soldered, and the flame directed away from the component body.
– Always use silver soldering rods. – If the total unit gas charge has to be
replaced, the quantity
should be as given on the nameplate and the unit should be properly evacuated
beforehand. – During unit operation all panels should be in place, including
the electrical box access panel. – If it is necessary to cut the lines of the
refrigerant circuit, tube cutters should always be used and never tools which
produce burrs. All refrigerant circuit tubing should be of copper, specially
made for refrigeration purposes. – If a temperature sensor needs to be
replaced, the new sensor should be correctly installed. The sensor cable must
be positioned as the original sensor cable.
Cleaning should be done at regular intervals and should never be left until the unit has become blocked. The time intervals between cleaning depend on the quality of the water used, but as a general rule it is advisable to clean it at least once a year.
8.4 – Refrigerant circuit
Ensure that there is no leakage of refrigerant or oil from the compressor. Check that the high and low side operating pressures are normal. Check the cleanliness of the refrigerant-water heat exchangers by checking the pressure drop across them.
8.5 – Controls
Check the operation of all relays, high/low pressurestats and controls.
22
23
Order No.: 13401-76, 11.2000. Supersedes order No.: New Manufacturer reserves the right to change any product specifications without notice.
Manufactured by: Carrier SA, Montluel, France Printed in the Netherlands on totally chlorine-free paper.
24
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>