SIGN POLE INSTALLATION GUIDE
TOLL FREE: 1-800-705-1446 WE CAN
HELP!
Sign Pole
STEP 1
Depending upon the type of street sign and your geographical requirements, the
length, and placement may vary. Place the pole on two (2 saw horses and
prepare the drill press using a bit that is at least 1” longer) than the
diameter of the pole and 1/2” in diameter. If drilling will be done without a
press, measure down from the top of the pole on both sides of post to mark the
hole locations. We can supply you with a jig that will allow the pole to rest
inside the shape minimizing movement (additional costs may apply). Measure and
mark the pole for each sign based on the sign mounting specifications keeping
your local mounting regulations in mind. Signs themselves can be used as
templates to determine hole locations and mounting positions.
NOTE: Street signs can have up to 4 signs on each pole so careful
placement is important We will provide you with the specs of the placement
however it is recommended to have 2-3 sets of eyes check the work in the
beginning.
STEP 2
Dig a hole 18-24” deep with a post-hole digger approximately 10” – 16” in
diameter. Adjust the depth of the hole to achieve the desired height of the
post above the road surface. It may be helpful to measure and mark the bottom
of the pole to easily identify the portion of the post that will be installed
in the ground. Federal guidelines require traffic signs to be a minimum of 84”
from the bottom of the sign to the road surface. Your location may have
additional requirements and specifications regarding sign dimensions, mounting
methods, or vinyl types. Be sure to check with your local authority before
installing.
STEP 3
Pour Concrete into the hole once positioned. Note that some localities
prohibit the use of direct burial installations and require DOT approved
“breakaway” sign poles. Check with your local authorities before installation.
Using a cement form to finish the concrete above ground level will prevent
damage to the post and base from edgers and lawnmowers
STEP 4
Before concrete sets completely, be sure to check that the post is straight
and all needed holes are in the correct positions the signs will face in the
appropriate direction.
STEP 5
Once the concrete has been set, finials, bases, and street & traffic signs can
be assembled and attached to the post. Attach your signs and ornamental
components to the post with the provided hardware and accessories as shown on
the following pages
WARNING: Check for underground utilities before digging. Before you begin
any excavation, you must call and have someone check for underground
utilities. Wait the required amount of time for the utility company to
properly survey your property before\ digging any holes. Failing to take these
precautionary steps may result in property damage, injury or even death. The
North America One call referral service at
1-888-258-0808 connects you to a
national directory of utility companies
signaturestreetscapes.com
1-800-705-1446
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>