HARVEY New Construction Nail Fin Window Installation Guide
- June 10, 2024
- HARVEY
Table of Contents
New Construction Nail Fin Window
Installation Guide
Preparing the Opening
- Verify the rough opening (RO) to be plumb, level, square. RO should measure 1/2″ larger than width and height of the window it will receive.
- Flash sill according to flashing instructions. See Basic Flashing Procedure, Step 1.
- Lay fiberglass insulation along rough opening sill and staple in place. Be careful not to over insulate.
Note: Low expanding foam insulation can be used around windows as an alternative to fiberglass. When using foam insulation around windows as an alternative to fiberglass, you must be sure that it is installed in accordance with the manufacturer’s instructions. Over insulating with foam can cause the window to operate incorrectly.
Installing the Window
-
Apply a 3/16″ to 1/4″ bead high-quality sealant (ASTM C920 certified) to the back side of the window’s nail fin in line with the pre-punched nail slots. See Key Note A and B for further sealing details.
-
Center window in opening, resting bottom of unit on the sill plate, making sure the sill is level.
If sill is not level, shim as needed. -
Using 1-3/4″ roofing nails or washer head screws, secure one corner of unit by nailing through the prepunched holes in nail fin. Leave nails loose to make adjustments if
necessary. Check that the frame is plumb, level, square. Shim where needed. Nail guns not recommended. -
Continue nailing top and side fins through every other pre-punched nail slot, making sure window is square in the opening. Check site lines. Nail sill fin last, making sure unit is level along entire length.
-
Using installation screws supplied, secure window utilizing the pre-drilled holes along window jambs on all vinyl products and Majesty double hung windows and shim as needed. Do not over-tighten screws.
See Key Note accessory Majesty windows. -
Insulate to fill the space between the window frame and RO. See Key Note on insulation.
-
Finish flashing installation (Steps 3 and 4).
Basic Flashing Procedure
|
---|---
Flash the sill on bottom of the opening| Install window set in sealant
|
Flash jambs at sides of opening over nail fin| Flash head over top nail fin
(6″ wide flashing recommended)
Flashing Lengths
Sill Flashing: ROW + (2 x flashing width)
Jamb Flashing: ROH + (2 x flashing width) -1″
Head Flashing: ROW + (2 x flashing width) +2″
Legend
RO: Rough opening
ROW : Rough opening horizontal width
ROH : Rough opening vertical height
Key Notes for a Successful Install
A: All Majesty windows and vinyl windows that have applied nail
fin: Prior to installation, seal the window nail fin to the window by
applying a continuous bead of high-quality sealant to the back side of the
nail fin where it meets the window frame. After installation, seal all corners
of mechanically jointed frames and applied nail fin to seal frames and seam
joints.
B: Windows with applied casing: If the window is supplied with the
optional applied flat casing or 908/brick mold casing, a secondary seal should
be applied. Apply a continuous bead of high-quality sealant to the back side
of the nailing flange where it meets the window accessory.
Insulation: Care must be taken to not over fill the void between the RO
and the window frame when using low compression injected foam insulation.
Understand the expansion properties of the foam you are using and apply only
enough foam to fill the void. Avoid over filling the void as this can cause
the window frame to deflect and impede the window’s operation.
Product Specific Notes
Double Hung and Rolling Windows: Slightly open the sashes to get a sight line
that will help square the window.
For larger units, it is recommended that the sash be removed before
installation. Reinstall sashes to verify sight line before finishing.
Casements and Awnings: Verify that the margin between sash and master frame
perimeters is uniform on all 4 sides when slightly open.
Vinyl Rolling Windows: The rough opening must be plumb, level, square. The
sill of the window must be flat, level and supported across the entire width
of the RO to insure alignment of the sash locks and keepers for proper
operation. Use a continuous shim across the entire width of the RO, or use
individual shims at the sill across the entire width of the opening to
provide a level RO sill; space shims no more the 6″ apart along the sill and
ideally located below each sash roller. Drainage holes must be kept free of
obstructions.
Vinyl Mulled Units: Mulled frames will come provided with metal straps located
along the top and bottom of the frame.
Straps should also be used to secure mulled units within the rough opening.
Majesty Casement and Awning Windows: Pre-drill for screwing/nailing 1/3 of the
way down from the top and 1/3 of the way up from the bottom. Install unit
using screws or 8D galvanized finish nails through the window interior frame.
On operating casements and awnings, screws/nail should be applied through the
screen track cavities. On all other Majesty wood windows, pre-drill holes
along jambs and
apply installation screws.
Majesty Product Finishes: All wood surfaces must be finished and sealed within
48 hours of installation.
VERY IMPORTANT: General Practices
Prior to Finishing: Check the operation of all windows to ensure proper
operation. Do not install or finish off windows and doors if damaged, if
visual issues are present, or operation is in question unless instructed to
do so by Harvey Windows + Doors.
Using Shims: It is recommended to use shims made of durable plastic or other
suitable material which does not compress or degrade over time. Shimming is
recommended to align sight line margins between window sash and frames, as
well to align the window plumb, level, square within a rough opening.
Storage and Protection: Harvey windows and doors shall be stored upright on a
flat surface, off the ground, out of the weather in a clean dry, low traffic
area that is not subject to damage. If windows and doors are stored outside,
they should not be stored in direct sunlight and not stacked against each
other. Windows and doors should not be stored in shipping containers unless
the climate can be controlled. Remove all protective films from painted
surfaces and non-permanent labels prior to 30 days after installation.
Initial Quality: Claims against initial quality must be submitted within 90
days from the manufactured date.
Screens: Provide reasonable insect control and are not intended to provide
security or for the retention of a persons or object from the interior.
http://www.harveywindows.com/install
Scan the QR code for Non-English and additional instructions.
http://www.installingharveywindows.com/
Scan QR code for our ENERGY STAR compliant installation center and for best
practices for window removal.
Visit us online at
www.harveywindows.com/install.
Failure to follow these instructions may result in this window unit not
performing up to Harvey’s specifications for its intended use.
All warranties may also be voided.
Harvey Windows + Doors is a trademark of Harvey Industries, LLC.
Part #20117.01 21-098 Revised 2/2022
Documents / Resources
|
HARVEY New Construction Nail Fin
Window
[pdf] Installation Guide
New Construction Nail Fin Window, New Construction Fin Window, Nail Fin
Window, Fin Window, Nail Window, Window
---|---
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>