SANTA FE 4042835 Large Hang Kit for Dehumidifiers Instruction Manual

June 4, 2024
SANTA-FE

SANTA-FE-Logo

SANTA FE 4042835 Large Hang Kit for Dehumidifiers

SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-Product-
Image

Parts Included:

SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-01

  1. (4) Ratchet Straps
  2. (2) Brackets
  3. (4) Eye Bolts (3/8 x 3-7/8)

Tools Required:

  • Tape Measure
  • Level
  • Screw Driver (Phillips or Regular) to use as leverage for Eye Bolts
  • Screws for TJI joists (only applies if you have TJI joists)

Optional Tool:

  • Power Drill with 5/16″ Drill Bit (to pre-drill Eye Bolt holes)

CAUTION!
MAKE SURE THE UNIT IS LEVEL AFTER INSTALLATION.

Standard Joist Instructions Large Horizontal Dehumidifier

  • Step 1: Gently tip the unit up on its back end in order to have access to the bottom foot holes.
    SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-02

  • Step 2: Secure the brackets in place by using the leveling feet and the female threaded holes. (Leveling feet are packaged with the dehumidifier.) Line up the pre-drilled holes on the brackets with the leveling feet holes on the unit. Once lined up, screw in the leveling feet to secure the brackets to the dehumidifier.
    There are four leveling feet to screw in on each dehumidifier.
    Once in place, gently tip the unit back down on the leveling feet with the brackets in place.
    SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-03

Standard Joist Instructions Santa Fe Oasis105/Quest 110

  • Step 1: Gently tip the unit up on its back end in order to have access to the bottom foot holes.
    SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-04

  • Step 2: Secure the brackets in place by using the leveling feet and the female threaded holes. (Leveling feet are packaged with the dehumidifier.) Line up the pre-drilled holes on the brackets with the leveling feet holes on the unit. Once lined up, screw in the leveling feet to secure the brackets to the dehumidifier.
    There are four leveling feet to screw in on each dehumidifier.
    Once in place, gently tip the unit back down on the leveling feet with the brackets in place.

SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-05

  • Step 3: Determine the placement of the unit and turn / screw your first eye bolt into position on the bottom of the floor or rim joist. Use a screw driver as leverage to tighten the eye bolt. Screw in until the threads are no longer visible.
    SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-06

  • Step 4: Distance the second eye bolt 55″ away from the first eye bolt on the same joist and screw into place.

  • Step 5: Skip a joist to place the remaining two eye bolts on the joist parallel to the joist used for the first two eye bolts; leaving one joist not used between the two joists. Eye up the location of the remaining two eye bolts and position them straight across from the first two eye bolts used in steps 3 and 4. The placement should be close but does not need to be precise. Be sure to distance the two eye bolts 55” apart.
    SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-08

  • Step 6: Position the unit directly below the eye bolts. Attach the four ratchet straps to the pre-drilled holes on the hang kit brackets using the non-ratchet clip end.
    SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-09

  • Step 7: Using the ratchet end of the ratchet strap, attach each strap to the eye bolts above the unit. If additional slack on the rope is needed, push the trigger on the ratchet end of the strap up and feed the rope through as needed.
    SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-10

  • Step 8: Pull down on the ratchet rope, lifting the unit in place. We recommend pulling down on each individual ratchet rope 6-12 inches at a time until level.
    CAUTION: MOVING THE STRAPS TOO QUICKLY CAN CAUSE THE UNIT TO ROCK AND TIP.
    SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-11

TJI Joist Instructions

CAUTION!
SCREWING THE EYE BOLTS DIRECTLY INTO THE BOTTOM FLANGE ON THE TJI JOIST WILL WEAKEN THE STRUCTURAL INTEGRITY OF THE JOIST.

When working with TJI floor joists, follow the standard instructions on the previous pages but factor in the following modification listed below:
A 2”x4” piece of wood can be cut to fit between two joists. Standard floor joists are 16″ o.c. (on center) apart from one another. Measure and cut the 2″x4″ accordingly to fit as shown in the diagram below. The 2”x4” will sit on the top side of the bottom flange and can be screwed in place with a few screws going through the web of the joists and into the 2”x4”. The eye bolt will then be screwed into the 2”x4”.

SANTA-FE-4042835-Large-Hang-Kit-for-Dehumidifiers-12

4201 Lien Rd Madison, WI 53704
TOLL-FREE 1-800-533-7533
www.thermastor.com
[email protected]

References

Read User Manual Online (PDF format)

Loading......

Download This Manual (PDF format)

Download this manual  >>

SANTA-FE User Manuals

Related Manuals