EG4 IV-8000-HYB-AW-IV-8000-HYB-AW-00 12kPV Hybrid Inverter User Guide
- July 7, 2024
- Eg4
Table of Contents
EG4 IV-8000-HYB-AW-IV-8000-HYB-AW-00 12kPV Hybrid Inverter
TECHNICAL SPECIFICATIONS
AC INPUT DATA| | |
---|---|---|---
NOMINAL AC VOLTAGE| 120/240VAC; 120/208VAC (L1/L2/N required)
FREQUENCY| | | 50/60Hz
MAX. AC INPUT POWER| | | 12000W
MIN. GENERATOR SIZE| | | >5000W
MAX. GEN | GRID PASSTHROUGH CURRENT| | | 80A | 80A
AC GRID OUTPUT DATA| | |
MAX. OUTPUT CURRENT| 33.3A@240VAC | 38.5A @208VAC
OUTPUT VOLTAGE| | 120/240VAC; 120/208VAC
NOMINAL POWER OUTPUT| | | 8000W
OUTPUT FREQUENCY| | | 50/60Hz
POWER FACTOR| | 0.99 @ Full Load
REACTIVE POWER ADJUST RANGE| | | ±0.8
MAX CONT. LINE WATTAGE| | | 4000W
0.5s| 1s| 1min| 12min
PEAK POWER| | |
16kW| 12kW| 10kW| 8.8kW
OPERATING FREQUENCY| | | 50/60Hz
THD (V) @FULL LOAD| | | <3%
| Single| | Parallel
TRANSFER TIME|
20ms – Default, 10ms – Selectable| 20ms
PV INPUT DATA| | |
NUMBER OF MPPTS| | | 2
INPUTS PER MPPT| | | 2
MAX. USABLE INPUT CURRENT| | | 25/25A
MAX. SHORT CIRCUIT INPUT CURRENT| | | 31/31A
DC INPUT VOLTAGE RANGE| | | 100-600 VDC
UNIT STARTUP VOLTAGE| | | 100 VDC
MPPT OPERATING VOLTAGE RANGE| | | 120-500 VDC
NOMINAL MPP VOLTAGE| | | 360 VDC
MAXIMUM UTILIZED SOLAR POWER| | | 12000W
RECOMMENDED MAXIMUM SOLAR INPUT| | | 15000W
EFFICIENCY| | |
MAXIMUM EFFICIENCY (PV TO GRID)| | | 97.5%
MAXIMUM EFFICIENCY (BATTERY TO GRID)| | | 94%
CEC WEIGHTED EFFICIENCY| | | 96.4%
MAXIMUM EFFICIENCY (PV TO BATTERY)| | | 99.9%
IDLE CONSUMPTION (STANDBY MODE)| | | <55W
BATTERY DATA|
---|---
COMPATIBLE BATTERY TYPES| Lead-Acid/Lithium
MAX. CHARGE/DISCHARGE CURRENT| 167A @ 48 VDC
NOMINAL VOLTAGE| 48 VDC
VOLTAGE RANGE| 40-60 VDC (Lithium); 40-60 VDC (Lead-Acid)
RECOMMENDED BATTERY CAPACITY PER INVERTER| >200Ah
GENERAL DATA|
MAX. UNITS IN PARALLEL| 10
PRODUCT DIMENSIONS (H×W×D)| 29.5×20.5×11.2 in (750×520×285mm)
UNIT WEIGHT| 110 lbs. (50kg)
DESIGN TOPOLOGY| High Frequency – Transformerless
RELATIVE HUMIDITY| 0-100%
OPERATING ALTITUDE| <2000m (<6561ft)
OPERATING AMBIENT TEMPERATURE RANGE| -13°F – 140°F (-25°C – 60°C)
STORAGE AMBIENT TEMPERATURE RANGE| -13°F – 140°F (-25°C – 60°C)
NOISE EMISSION (TYPICAL)| <50 dB @ 3ft
COMMUNICATION INTERFACE| RS485/Wi-Fi/CAN
STANDARD WARRANTY| 10-year standard warranty**
INGRESS PROTECTION RATING| IP65
SAFETY FEATURES
| PV Arc Fault Protection, PV Ground Fault Protection, PV Reverse Polarity
Protection, Pole Sensitive Leakage Current Monitoring Unit, Surge Protection
Device, integrated PV disconnect
STANDARDS AND CERTIFICATIONS|
UL1741 SB|
CSA C22.2#107.1:2016|
CSA C22.2#330:2017 ED 1|
HECO SRD-IEEE-1547.1:2020 ED 2|
RAPID SHUT DOWN (RSD) NEC 2020:690.12|
FCC PART 15, CLASS B (PENDING)|
SAFETY INSTRUCTIONS
International safety regulations have been strictly observed in the design and testing of the inverter. Before beginning any work, carefully read all safety instructions, and always observe them when working on or with the inverter. The installation must follow all applicable national or local standards and regulations.
Incorrect installation may cause:
- Injury or death to the installer, operator or third party
- Damage to the inverter or other attached equipment
IMPORTANT SAFETY NOTIFICATIONS
There are various safety concerns that must be carefully observed before,
during, and after the installation, as well as during future operation and
maintenance. The following are important safety notifications for the
installer and any end users of this product under normal operating conditions.
- Beware of high PV voltage. Please install an external DC disconnect switch or breaker and ensure it is in the “off” or “open” position before installing or working on the inverter. Use a voltmeter to confirm there is no DC voltage present to avoid electric shock.
- Beware of high grid voltage. Please ensure the AC switch and/or AC breaker are in the “off” or “open” position before installing or working on the inverter. Use a voltmeter to confirm there is no voltage present to avoid electric shock.
- Beware of high battery current. Please ensure that the battery module breakers and/or on/off switches are in the “open” or “off” position before installing or working on the inverter. Use a voltmeter to confirm there is no DC voltage present to avoid electric shock.
- Do not open the inverter while it is operating to avoid electric shock and damage from live voltage and current within the system.
- Do not make any connections or disconnections (PV, battery, grid, communication, etc.) while the inverter is operating.
- An installer should make sure to be well protected by reasonable and professional insulative equipment [e.g., personal protective equipment (PPE)].
- Before installing, operating, or maintaining the system, it is important to inspect all existing wiring to ensure that it meets the appropriate specifications and conditions for use.
- Ensure that the PV, battery, and grid connections to the inverter are secure and proper to prevent damage or injuries caused by improper installation.
- Some components of the system can be very heavy. Be sure to utilize team-lift among other safe lifting techniques throughout the installation.
WARNING! To reduce the risk of injury, read all instructions
All work on this product (system design, installation, operation, setting,
configuration, and maintenance) must be carried out by qualified personnel. To
reduce the risk of electric shock, do not perform any servicing other than
those specified in the operating instructions unless qualified to do so.
- Read all instructions before installing. For electrical work, follow all local and national wiring standards, regulations, and these installation instructions.
- Make sure the inverter is properly grounded. All wiring should be in accordance with the National Electrical Code (NEC), ANSI/NFPA 70.
- The inverter and system can inter-connect with the utility grid only if the utility provider permits. Consult with the local AHJ (Authority Having Jurisdiction) before installing this product for any additional regulations and requirements for the immediate area.
- All warning labels and nameplates on the inverter should be clearly visible and must not be removed or covered.
- The installer should consider the safety of future users when choosing the inverter’s correct position and location as specified in this manual.
- Please keep children from touching or misusing the inverter and relevant systems.
- Beware! The inverter and some parts of the system can be hot when in use, so please do not touch the inverter’s surface or most of the parts when they are operating. During operation, only the LCD and buttons should be touched.
PV CONNECTION
CONNECTING PV TO THE INVERTER
Consult with an installer to ensure that appropriate cable sizing is used due
to various factors such as voltage drop and Voc.
PV CABLE SIZE | MINIMUM INSULATOR VOLTAGE |
---|---|
10 AWG – 6AWG (Max) (6 mm2 – 16 mm2) | 600V |
REMINDER : Verify the lowest ambient temperature of the installation location. The rated Voc on the solar module nameplate is obtained at Standard Testing Conditions (STC) (77°F/25°C). As the ambient temperature drops, the solar module Voc increases. Please ensure the maximum solar string voltage, corrected at the lowest temperature, does not exceed the inverter’s maximum input voltage of 600VDC.
PV INPUT DATA | DESCRIPTION | PARAMETER |
---|---|---|
DC Input Voltage Range | Range required for the unit to operate up to max | |
input | 100–600 VDC | |
Unit Startup Voltage | Voltage needed for the LCD to power on | 100 VDC |
Load Output Minimum Voltage | Minimum voltage needed to output power on Load | |
side | >140 VDC | |
MPP Operating Voltage Range | Range where the MPPT can track | 120–500 VDC |
Nominal MPPT Voltage | The MPPT will operate most optimally at this voltage |
360 VDC
Maximum Utilized Solar Power| Watts the unit can utilize from array after
considering all power loss factors| 12kW
Rec. Maximum Solar Input| The suggested PV power input into the device for it
to utilize the full 8kW of PV| 15kW
DANGER : Damage WILL occur if the string voltage exceeds the inverter’s maximum input voltage of 600VDC!
STRING SIZING
When solar modules are put in a series string, the voltage multiplies times
the number of modules and the amperage stays the same as the rating of each
module.
For example: Using solar modules that have a 40VDC VOC (@77ºF) with a Max Power current of 10 Amps (Imp) – 10 modules wired in a series string would have a VOC of 400 VDC (@77ºF) and a string amperage of 10 Amps. When the temperature lowers, the voltage can rise above the maximum allowed by the MPPT and damage will result.
Finally, calculate the maximum current of the string so as not to exceed the Inverter’s MPPT circuit ratings. Double check if the calculated Vmp range is within the 120-500 VDC optimal MPPT circuit operating range. It is recommended to consult a solar designer for assistance.
FOR ALL MODULES, THE CALCULATIONS NEED TO BE PERFORMED OR VERIFIED BY USING A STRING CALCULATOR AND CONSULTING A PROFESSIONAL.
CAUTION : To determine how many modules are ideal per string; first verify the lowest possible ambient temperature of the installation location. Next, find the rated Voc, Vmp, Isc and Imp of the solar module at 25ºC and the temperature coefficients for voltage and power. Then calculate highest possible Voc for the entire string when the ambient temperature falls to the lowest possible ambient temperature upon sunrise. To make this calculation, use a string calculator or consult a solar designer or solar electrician.
The inverter has two separate MPPTs which will utilize up to 25A each.
Likewise, two strings can be paralleled for any modules having less than 12.5A
(Imp) rating.
When sizing strings for each MPPT, they MUST be the same model, brand and
number per string (series and parallel).
All panels in a series/parallel string should face the same orientation and be exposed to roughly the same shading across the string. Consideration should be placed on string location and wiring order on the racking to minimize shading effects. One shaded module can disproportionately reduce output for the entire string. This is because shading on a solar module will cause a drop in voltage. All panels in a string will drop to match the lowest voltage experienced in any module. Using Optimizers and/or avoiding linear strings in favor of rectangular strings can minimize losses due to shading.
NOTE : The array may have a higher Imp than the 25A specified, but the MPPTs will not make full use of the extra current and may lead to component deterioration over time.
PV WIRING INSTRUCTIONS
Please follow the steps listed below to ensure proper PV connections:
- Step 1: It is recommended to install a separate PV Isolator disconnect near the inverter for ease of installation and added safety. Before installing PV wiring into the inverter, please ensure all breakers and disconnects are open (off) and confirm the PV strings are not energized by using a multimeter to ensure there is no DC voltage on the lines. Once that has been verified, please proceed to step 2.
- Step 2: Strip off 1/4–5/16 in. (6–8mm) insulation from the PV strings’ positive and negative conductors
- Step 3: Use wire ferrules for the PV string conductors if they are stranded wire.
- Step 4: Insert the conduit fitting into the opening for the PV connection and tighten it from the inside using the counter nut.
- Step 5: Route the PV conductors through the conduit fitting and into the inverter.
- Step 6: Secure the PV conductors in place into the inverter inputs. Verify that they are secured properly by lightly pulling on them.
- Step 7: Ensure the conduit and conduit fittings are fastened reliably and the cable entry holes are sealed.
NOTE : It is recommended to install a separate DC earth ground for
grounding of the solar panel frames. All exposed metal parts of the system
must be grounded regardless of voltage.
DO NOT GROUND NEGATIVE PV LINES, ONLY SOLAR PANEL FRAMES.
Please see the diagram below for PV terminal labeling.
BATTERY CONNECTION
The EG4 12kPV can utilize either lithium or lead-acid batteries. There is a
combination of settings that need to be changed depending on the battery type.
(See the battery user manual for more information.)
BATTERY CABLE CONNECTION
Follow the steps below to properly connect the battery cables.
- Step 1: Place all breakers in the open (off) position before connecting or disconnecting wires. Ensure that there is no voltage present by using a voltmeter.
- Step 2: Assemble the battery ring terminal based on recommended battery cable and terminal size (see table below).
- Step 3: If using a battery rack, ensure that all battery connections are installed properly before proceeding. Please refer to the battery rack manual for more information.
- Step 4: Connect the positive battery cable (RED) to the positive battery terminal (BAT+) and the negative battery cable (Black) to the negative battery terminal (BAT-) with a torque rating of 150 in-lbs. (17 Nm) per connection.
- Step 5: Be sure not to cross polarize, as this will damage the equipment.
NOTE : The recommended battery capacity of one 12kPV inverter is ≥200AH
The recommended battery cable and terminal size are as follows:
MAX. CONTINUOUS CHARGE/DISCHARGE AMPERAGE|
BATTERY CAPACITY
|
WIRE SIZE
| RING TERMINAL| TORQUE VALUE
---|---|---|---|---
CABLE (MM 2)| DIMENSIONS
Depth| Length
167A| 200AH| 2/0 AWG| 38| .25 in (6.4mm)| 1.5 in
39.2mm
| 150 in-lbs. (17 Nm)
LITHIUM BATTERY COMMUNICATIONS
Upon successful installation of the batteries, follow the next steps to enable
closed-loop communications (with compatible battery modules) between batteries
and inverter.
- Connect either the CAN or RS485 (depending on make/model of battery) communications cable between inverter and battery. See diagram below.
- For the inverter to communicate with the battery BMS, setting 3 must be changed to “Li-ion”.
- The inverter will then switch to a secondary setting. Here, select the appropriate model of battery and press enter.
AC WIRING INFORMATION
When sizing AC wires, please adhere to the following information.
AC Cable Requirements:
TERMINAL CONNECTION | WIRE SIZE | TORQUE VALUES |
---|---|---|
GRID | 6 AWG (13.3 mm2) | 17.7 in. lbs. (2Nm) |
GEN | Max. 4 AWG (21.2 mm2) | 17.7 in. lbs. (2Nm) |
LOAD | 6 AWG (13.3 mm2) | 17.7 in. lbs. (2Nm) |
Ground-Neutral Bonding
The information below describes the nature of the ground and neutral in the
inverter and their relationship to the system. Always consult with an
installer or a licensed electrician to ensure that the right configuration is
being used:
- The neutral line is a solid connection between AC input and AC output (known as a Common Neutral Architecture).
- The neutral line between the AC input and AC output is never disconnected.
- This architecture assumes there is a single neutral-ground bond in the system. Typically, the neutral-ground bond for a system will be located at the first means of disconnect for the grid.
IMPORTANT : The system should have one and only one ground-neutral bond. (This is typically the Main Bonding Jumper located at the first grid system disconnect.)
STEPS FOR AC CONNECTION
Please follow the steps outlined below to ensure proper AC Input/Output
connections.
-
Step 1 : Before installation of any wiring, please ensure all breakers are open (off) before making any connections. Use a multimeter to confirm the AC Input lines (L1, L2 and neutral) are not energized.
-
Step 2: Strip off 5/16-3/8 in. (8-9.5 mm) insulation from the AC cables.
NOTE : If using fine stranded wire, use ferrules to secure the connection. -
Step 3: Fasten the AC Input wires into their respective terminals using the proper torque (17.7 in. lbs. – 2Nm). The terminals located above “N.BUS” (neutral bus) are defined as such: LOAD is the AC output, GRID (input) is the AC terminal, and GEN is the generator’s input.
Please see the diagram below for terminal labeling.
NOTE : Always be sure to connect the AC Output ground wire to the Ground terminal first before installing the AC Outputs L1 and L2.
REMINDER : After connecting all AC wiring, put the built-in LOAD breaker back to the ON position before providing power to the load.
CURRENT TRANSFORMER (CT) CONNECTION
To measure the power imported from and exported to the grid, a pair of CTs or
one three-phase meter must be installed at the service entry point in or near
the main service panel. Two CTs are provided with each inverter.
CT Port Pin Definition
The interface for the CT connections is one RJ45 port labeled: CT1/CT2. The
included CTs come with prewired connectors so they can be connected directly
to their respective ports.
PIN(S) | DESCRIPTION |
---|---|
1-4 | Reserved |
5 | CT2N CT2P |
6 | CT2P |
7 | CT1N |
8 | CT1P |
If a cable for CT connections is needed, the diagram on the right and the
table above show which pins are utilized for proper operations.
The following diagram shows the connections and installation orientation of
the CTs.
For the CTs to function as intended, they must be installed as shown in the
diagram to the right.
Begin by clamping CT1 (labeled) on the AC Input Line 1 (L1). Clamp CT2
(labeled) on AC Input Line 2 (L2), and make sure the arrows on the CTs are
pointing towards the inverter.
Once the CTs are clamped on the AC Input Lines, connect the CT communications
cable (RJ45) to the port on the inverter.
NOTE : The CTs must be installed in or near the Main Service Panel for
accurate readings.
CT Clamp Ratio
The 12kPV supports 3 ratios of CT clamps – 1000:1, 2000:1 and 3000:1. The CT
clamps included with the inverter are rated at 3000:1. If using a 3rd party
CT, please ensure that the CTs match one of the above ratios. Next, navigate
to the inverter settings (either on the physical display or via the monitoring
page) and select the correct CT ratio according to the hardware.
Extending the CT Clamp Cable
The CT communications cable can be extended with a common ethernet cable if
more length is required. An RJ45 jack-to-jack adapter is required to extend
the existing cable. The CT communications cable can be extended up to 300 ft.
(around 100 m).
WORKING WITH A GENERATOR
GENERATOR SYSTEM CONNECTION
The 12kPV can utilize a minimum 5kW (≥12kW recommended) generator for backup
power in the case of grid failure. When sizing generators to provide adequate
power and optimal frequency, the Total Harmonic Distortion (THD) of the
generator must be <3%. To achieve this optimal THD value, it is recommended to
size the generator for at least 1.5x the output of the inverter to allow for
powering loads and charging batteries. The table on the next page shows the
recommended generator capacity for optimal operations.
NUMBER OF INVERTERS IN PARALLEL | RECOMMENDED GENERATOR CAPACITY |
---|---|
1 | >12kW |
2 | >24kW |
3 | >36kW |
4 | >48kW |
When properly wired and configured, the generator will start automatically when the battery voltage is lower than the cut-off value or there is a charge request from the BMS. When the generator is running, it will charge the batteries and excess AC power will be diverted to the AC output (LOAD) to power loads. The pass-through relay on the inverter’s Generator terminal (GEN) is 50A. When the generator is on, please ensure the total load and charge current does not exceed 50A. If the generator’s power is not adequate to power all loads, the inverter will pull from batteries as supplemental power. When the battery voltage exceeds the threshold for AC charging, the generator will stop.
DRY CONTACT INFORMATION (GEN PORT)
This inverter has a dry contact connection that can be used to remotely enable
external devices such as a generator. The GEN Port (NO1, CO1) can be used to
remotely start a generator. To do so, the generator start signal must be
connected to the inverter GEN contacts, NO1 and CO1.
NOTE: NO1 = Normally Open, CO1 = Common. GEN relay maximum specification: 250VAC, 5A
GENERATOR AC CONNECTIONS
Please follow the steps listed below to ensure the generator connections are
installed correctly.
NOTE : If running more than one inverter in the system, you must wire the
generator to provide power to every inverter running in parallel for the
inverters to function as intended.
- Step 1: Before making any wiring connections, be sure to have the inverter(s) powered off, the generator powered off, and all circuit breakers open (off) to prevent damage to the unit.
- Step 2: Properly identify the generator’s output lines. By US wiring standards, the L1 wire will be black and the L2 will be red, Neutral will be white, and ground will be green or bare. Once identified, remove approximately 3/8in. (10mm) from the insulation sleeve on the wires.
- Step 3: Ground the generator’s output ground to the Ground Bus (Labelled PE) of the inverter.
- Step 4: Install L1 (Black) to the GEN port’s L1 terminal, then install L2 (Red) to the GEN port’s L2 terminal. Next, fasten the Neutral (White) wire (represented by grey wire in image) from the generator into the N-BUS GEN port terminal.
GENERATOR START AND STOP SETTINGS
Using the EG4 Monitoring Software, go to the “Maintenance” page where “Remote
Set” will be selected automatically. Scroll down to the “Charge
Setting”/”Generator Charge” section and select the “Generator Charge Type”
(see screenshot below). Normally, lead-acid batteries are charged according to
voltage and lithium batteries are charged according to SOC.
Generator Start Conditions:
The generator will start when utility fails and one of the following
conditions are met:
- The battery is discharged to the cut-off setting or
- There is a force charge request from battery or
- The battery voltage or SOC is lower than the ‘Generator Charge Start Battery Volt/SOC’ setting
Generator Stop Conditions:
When battery voltage or SOC is higher than the “Generator Charge End Battery
Volt/SOC” settings.
OFF-GRID
The 12kPV can function fully in off-grid only mode, eliminating the need for
utility or a generator. It is highly recommended that purely off-grid systems
without access to the utility have a backup generator with remote start for
extended cloudy periods (minimum 5kW diesel generator per 12kPV inverter).
Off-grid systems should have robust battery banks sized to ensure multiple
days of power and to reduce generator run time.
The 12kPV can also utilize AC-coupled solar input through the GEN port in purely off-grid systems. The generator can then be connected to the grid port in case of emergency. The inverter must be set to Microgrid anytime a generator is connected to the grid port.
OFF-GRID WIRING
The 12kPV can accept up to 50 Amps (12kW) of generator power and will pass
through all available power to the loads. The main breaker in the Loads
subpanel can be selected based on the number of inverters, with a 60A minimum
per inverter.
PARALLELING INFORMATION
PARALLEL COMMUNICATION CONNECTIONS
Multiple 12kPVs can be paralleled to expand energy storage and backup capacity
to suit different scenarios. Up to 10 units can be paralleled to reach a load
capacity of up to 80kW. The parallel communication wiring diagrams are shown
below. The manual bypass switch connects the loads to LOAD panel as default.
If the inverters fail, users can switch the loads to utility.
Please contact the inverter supplier for more detailed guidance on paralleling
systems.
REMINDER : Put the CAN communication PIN to ON status for the first and
the last inverter and OFF for inverters in between.
NOTE : Both switches in the “ON” position translates to address 1. Both switches in the “OFF” position translates to address 0.
PARALLEL CONFIGURATION
Important notices for parallel system:
- If utilizing the Generator input (GEN), ensure that the generator is connected to all inverters in parallel.
- If it is not possible to evenly divide solar strings per inverter, it is recommended to have more PV strings on the master inverter.
- The values shown on the LCD of each inverter display the individual inverter’s contribution to the system, not the system’s total.
REMINDER : If needing to extend the inverter-to-inverter paralleling cable, ensure the cable is a straight-through CAT5 and up cable. See image below for reference.
Before commissioning
- Verify that all inverters in the system are updated to the latest firmware. Please contact the distributor to confirm the latest version.
- Make sure the power cables and parallel communications cables have been properly connected and verify the DIP-switch settings are correct.
- Power on the inverters and set them to standby via the “Basic” page in the settings.
- Verify that the inverter status is set to “0.”
- Select which unit will be the Master by selecting “1 phase master” in Advanced Settings. Set all others to “Slave.”
- Ensure all inverters are set to “R” phase.
- For closed-loop communications, enable “Share Battery” setting for all paralleled inverters.
- Ensure the battery to inverter communications cable is properly connected from master battery to the master inverter.
Commissioning steps
- Turn on the battery and make sure the communication works on all units.
- Check the parallel info via the Home page.
- Turn on the “Off-grid output” function in the “Advanced” page.
- Before connecting load to load output terminal, check the output of L1 to N (120V in the U.S.), L2 to N (120V in the U.S.) and L1 to L2 (240V in the U.S.).
- Add some small loads to the load output and verify power output.
CONTACT US
support@eg4electronics.com
903-609-1988
www.eg4electronics.com
References
Read User Manual Online (PDF format)
Read User Manual Online (PDF format) >>